16
Physical rigging
1
Start the rigging process by blocking the work area below and make sure the work is performed from a stable plat-
form.
2
Attach the short rigging booms with the half couplers to the rigging structure.
3
Attach a row of long rigging booms to the short rigging booms.
4
Lift the first LED panel into place (for example in the top left corner) between the mounts in the rigging booms.
5
Fasten the panel to the rigging using the 4 bolts.
When assembling a LED screen installation, mount the panels on the rigging booms one
by one. Mount one row of panels at a time starting from the top and working downwards.
Manual_LS-4.6_V0_UK_170x113,3.book Page 16 Saturday, January 11, 2014 7:13 PM
Summary of Contents for LS-4.6
Page 1: ...LS 4 6 LED PANEL Manual_LS 4 6_V0_UK_170x113 3 book Page 1 Saturday January 11 2014 7 13 PM ...
Page 8: ...8 Manual_LS 4 6_V0_UK_170x113 3 book Page 8 Saturday January 11 2014 7 13 PM ...
Page 31: ...31 User s notes Manual_LS 4 6_V0_UK_170x113 3 book Page 31 Saturday January 11 2014 7 13 PM ...
Page 32: ...Manual_LS 4 6_V0_UK_170x113 3 book Page 32 Saturday January 11 2014 7 13 PM ...