15
Figure 8. Installing the front rail
5.
Pull the slide forward: insert the pins and the latch into the EIA flange holes at the front of the rack.
6.
Repeat the process for the rail on the opposite side of the rack.
2.2.2
Installing the System onto the Rail Kit
After the rail kit has been installed and secured into place, the system may be installed onto the rails.
CAUTION: Prior to installing the system onto the rails, remove all compute nodes from the front of the
system and the shuttle assembly from the rear of the system.
Figure 9. Extending the rail slides
1.
Pull the rails forward until they both click into place (see Number 1).
2.
Push up the front latches (see Number 2).
3.
Pull the slides all the way out (see Number 3).