Use and settings of the INGECON SUN STORAGE 1Play TL M working with eBick Ultra
175 of CEGASA
ABH2010IMC25_
15
3 FINAL CHECK
This chapter describes the instructions to check that all the connections and settings have been
successfully done.
1) Verify that the CAN communication cable from the battery to the inverter is connected.
2) Verify that the inverter is on.
3)
Access to the inverter and verify that there is no “Communication Error with BMS”
alarm.
3.1
Configuration of the battery settings
After
the commissioning or the final check, it’s recommended to configure the SOC levels in the
inverter.
Operation mode: connected to grid
Setting
Description
SOC Max
Maximum state of charge for charging the batteries from the photovoltaic
energy (%).
SOC Min
Charge status under which battery discharge is not allowed when the grid
is available. SOC Recovery must be reached to resume the self
consumption with battery input.
SOC Recovery
Charge status above which the battery discharge resumes, once coming
from SOC Min.
This prevents excessive cycling, extending their work life.
Battery-Backup
In the event of a power outage, the energy required for critical loads is
supplied from the batteries and PV array. If this function is activated, the
SOC Recx and SOC Descx parameters need to be configured.
If the operation mode is stand alone or the Battery-
Backup function, it’s activated. It’s
recommended to configure the following settings.
Operation mode: off grid
Setting
Description
SOC Recx
Charge status above which the power supply to the critical loads is
restarted, once coming from SOC Descx (%)
SOC Descx
Charge status below which the power supply to the critical loads when the
grid is not available and the Battery- Backup function is enabled (%)
The inverter allows managing the battery charge daily through the scheduling. By default, this
function is disactivated. For more detail, check the Installation and Operation Manual of the
INGECON SUN STORAGE 1PLAY TL M.