In addition to the safety measures indicated in this manual, any general measures that may be appli-
cable should also be taken into account (installation-specific, country-specific, etc.).

The electrical installation must not entail fire or explosion hazards. Workers must be properly protected 
against the risk of accidents caused by direct or indirect contact. The electrical installation and the 
protective devices must take account of the voltage, all external conditioning factors and the compe-
tence of those people having access to the installation parts.

All work equipment must be adequate for protecting exposed workers against the risk of direct or 
indirect contact with electricity. At any event, the electrical parts of the equipment must comply with 
the provisions of the corresponding specific standards and regulations.

All workers performing work in the open air shall stop work in the event of storms, heavy rainfall, 
strong winds, snow or any other unfavourable environmental condition that hinders visibility or the 
handling of tools. Work on indoor installations directly connected to overhead electricity lines must be 
interrupted in the event of a storm.

Ingeteam assumes no liability whatsoever for damages caused by the improper use of the equipment. 
Any work on any of this equipment and involving a change in the original electrical layout, must first be 
proposed to Ingeteam. This proposed new layout must then be studied and authorised by Ingeteam.

The necessary safety measures must be in place to prevent unauthorised persons from 
handling the equipment and to keep them away from the vicinity of the equipment.

• 

Warning signs to indicate the presence of personnel at work.

• 

Lockout mechanisms or mechanical locking, by padlocks with keys.

These instructions must be easily accessible, close to the equipment and within easy reach of all users.

Before installing and commissioning the equipment, please read these safety instructions and warnings carefully 
and all the warning signs placed on the equipment. Ensure that all warning signs are perfectly legible and that any 
damaged or missing signs are replaced.

4.3.1.  Inspection tasks

Tasks involving the opening of the enclosure to make visual inspections.

4.3.2.  Operational tasks

Tasks involving loading software from the communications connector and tasks involving the start-up of the wind 
turbine.

4.3.3.  Manipulation tasks

Tasks involving the mounting and/or replacement of parts (fuses, switchgear in general, etc.), voltage disconnection 
and reconnection tasks, connection of other equipment to the unit, and connection of the communication wiring to 
the equipment. All tasks not considered to be Inspection or Operational tasks shall be classed as Manipulation tasks.

4.4.  General points

This section defines the preventive measures to be adopted when performing all types of work on the equipment, in 
order to work safely and control unavoidable hazards.

Protection against direct contact is provided by the enclosure which has a protection rating of IP 65.

The equipment has been tested to the applicable standards and regulations to ensure that it complies with the safety 

Summary of Contents for Ingecon mWind Interface

Page 1: ...Ingecon Wind Interface Installation manual...

Page 2: ...may exist Liability will not be assumed for total concordance The information contained in this document is regularly reviewed and it is possible that there may be changes in subsequent editions Other...

Page 3: ...for ensuring that such personnel is familiar with the contents of this manual You are reminded that it is mandatory to comply with all applicable safety legislation for electrical work There is an ele...

Page 4: ...must be followed 1 Disconnect 2 Prevent any possible re connection 3 Check that no voltage is present 4 Ground and short circuit 5 Protect against nearby live equipment where appropriate and place sa...

Page 5: ...wind turbine and power supply Strictly follow the mandatory voltage disconnection steps contained in this manual DANGER Crushing and joint injuries Always follow the instructions contained in the manu...

Page 6: ...ting Only then should the equipment be connected following the instructions contained in the manual Do not touch the electronic boards or components The more sensitive components could be damaged or d...

Page 7: ...t 16 3 4 Storage 16 3 5 Conservation 17 3 6 Waste disposal 17 4 Safety instructions 18 4 1 Contents 18 4 2 Symbols 18 4 3 Definition of the tasks to be performed 18 4 3 1 Inspection tasks 19 4 3 2 Ope...

Page 8: ...nd turbine 29 Connection to a wind turbine with an AC voltage output 30 Connection to a wind turbine with a DC voltage output 30 5 4 Electrical disconnection 30 6 Commissioning 31 6 1 Equipment inspec...

Page 9: ...C voltage generated by the wind turbine to the Ingecon Wind DC voltage input Protect the system against an excessive rotational speed and over voltages and also to limit the power intake when the wind...

Page 10: ...o adapt them to the standards and regulations in all European countries and also those in force in other continents 1 3 1 CE Marking The CE marking is essential for marketing any product in the Europe...

Page 11: ...at outdoor installation is possible IP65 means that the equipment is fully dust tight and also protected against the impact of water jets in any direction as defined for this protection rating in stan...

Page 12: ...d 20 cm around the base This is to ensure that the inverter cooling system operates correctly Facilitate the circulation of incoming and outgoing air through the ventilation grids 2 1 8 Mounting and a...

Page 13: ...20 C Minimum temperature of the surrounding air 20 C Maximum temperature of the surrounding air 70 C Maximum relative humidity with no condensation 95 For more detailed information please refer to Cha...

Page 14: ...to the sender s address Do not unpack the equipment until it is ready to be installed It should remain in a horizontal position at all times INGETEAM POWER TECHNOLOGY S A Avda Ciudad de la Innovaci n...

Page 15: ...g should be used Packaging disposal All the packaging can be given to an authorised manager of non hazardous waste In any case each part of the packaging should be disposed of as follows Plastic polys...

Page 16: ...close as possible to the connection between the fork and the chassis 3 Ensure that the forks are perfectly level to prevent the equipment from possibly being tipped off 4 En any event observe the inst...

Page 17: ...ation Ingeteam assumes no liability for possible damage if this condition is not met 3 6 Waste disposal During the installation commissioning and maintenance procedures the waste generated must be ade...

Page 18: ...the presence of hot parts that could cause serious burns All work specific safety warnings and notes are included in each corresponding chapter and are also repeated and completed at the critical poin...

Page 19: ...ied and authorised by Ingeteam The necessary safety measures must be in place to prevent unauthorised persons from handling the equipment and to keep them away from the vicinity of the equipment Warni...

Page 20: ...ts inside the equipment time to cool down 4 4 3 Personal Protection Equipment PPE It is mandatory to wear safety footwear compliant with standard EN 345 1 1992 It is also mandatory to wear kid gloves...

Page 21: ...e latter short circuits the turbine Do not turn on the IWI until all the devices have been installed brake resistor and Wind and grid voltage is available to dissipate the energy produced to the power...

Page 22: ...onment must be suitable and must comply with the guidelines set out in section 2 System description Furthermore the items used in the rest of the installation must be compatible with the equipment and...

Page 23: ...stallation manual Ingeteam Power Technology S A location of top screws location of bottom screws 4 Drill the two bottom holes and insert the appropriate screws 5 Check that the equipment is firmly anc...

Page 24: ...he shutdown protocol explained in 4 5 3 Manipulation work The Ingecon Wind Interface cable ports are located at the bottom of the enclosure Each type is described below Communication To connect the co...

Page 25: ...equipment is to be located should always be complied with Wiring diagram for the Ingecon Wind TL equipment with a connection to the Ingecon Wind Interface IWI For Ingecon Wind 2 5 TL 3 TL 3 3 TL 3 68...

Page 26: ...inserted screw down the hood to guarantee the IP65 insulating rating Once the assembly has been completed it will be possible to establish communications with the Ingecon Wind Interface through the qu...

Page 27: ...e cable gland to ensure that the equipment is airtight The analog input cable diameter must not be greater than 9 mm 5 3 6 DC output The Ingecon Wind Interface and the Ingecon Wind power stages are co...

Page 28: ...erform the wind turbine emergency stop The resistors must be sized according to the wind turbine characteristics power and output voltage The power delivered by the wind turbine is governed by the fol...

Page 29: ...R 4 Ohm R 5 Ohm R 6 Ohm R 7 Ohm R 8 Ohm R 9 Ohm R 10 Ohm Peak power W VLL Vrms 3 Ohm 4 Ohm 5 Ohm 6 Ohm 7 Ohm 8 Ohm 9 Ohm 10 Ohm Peak power W 19200 25600 32000 36816 7 31557 1 27612 5 24544 4 22090 VLL...

Page 30: ...S Never forget that when the wind turbine is moving voltage may be present at its terminals In both cases the wind turbine cable diameter must not be greater than 17 mm R S T 5 4 Electrical disconnec...

Page 31: ...on Check that the equipment is firmly anchored and runs no risk of tipping over 6 1 2 Hermetic seal of the equipment During installation a check should be made to ensure that the equipment connection...

Page 32: ...conditions including those specified by the customer for this type of operation The condition of the enclosure A visual inspection should be made of the condition of the enclosure checking the conditi...

Page 33: ...ny query or problem relating to the equipment please call the Ingeteam customer service Ingeteam Power Technology S A Avda Ciudad de la Innovaci n 13 31621 SARRIGUREN Navarra Spain Tel 34 948 28 80 00...

Page 34: ...Notes...

Page 35: ...Notes...

Page 36: ...00 00 Fax 33 0 5 61 25 00 11 e mail solar energie ingeteam com Ingeteam INC 5201 Great American Parkway Suite 320 SANTA CLARA CA 95054 USA Tel 1 415 450 1869 1 415 450 1870 Fax 1 408 824 1327 e mail...