www.austin-hughes.com
UM-IPM-02-Q414V3
P.37
InfraPower Manager - IPM-02
1. What is InfraPower Manager?
The InfraPower Manager IPM-02 is a Windows based system to consolidate management of max.
240 PDUs via 15 IP dongles, using a simple web interface which monitors and controls the WS kWh
switched / W kWh Monitored PDUs in the data center. Authorized users have a secure control over
outlets to power ON / OFF at the managed device level. It also provides the detailed PDU, daily en-
ergy consumption and event logged records, and sends alarm email once ampere & Temp. / Humid.
over the prede
fi
ned alarm threshold.
Please
fi
nd the link below:
http://www.austin-hughes.com/support/software/infrapower/IPM-02.msi
2. Which OS platform does IPM-02 support?
- MS Windows XP Professional with SP3 (32bit only)
- MS Windows 7 Professional with SP1
- MS Windows 7 Ultimate with SP1
- MS Windows Server 2003 R2 Standard Edition with SP2
- MS Windows Server 2008 Standard Edition SP2
- MS Windows Server 2008 R2 Standard Edition SP1
Ensure the user logins in the management PC as a member of “Administrators” Group
before IPM-02 Installation and execution.
3. Why user can’t login to the Management PC remotely ?
Make sure the port for web server is added in the
fi
rewall setting and the services of web server is
started in the management PC.
4. Which database does the IPM-02 support?
PostgreSQL
5. What is the PostgreSQL default password for IPM-02?
1qaz2WSX
6. How can I receive alarm email and get full log report?
Ensure that IPM-02 is executed and the alarm server is con
fi
gured properly and being enabled.
7. What is the default user name & password of IPM-02?
Default user name “admin” & password “00000000”
8. What is the command password of IPM-02?
Each IP dongle group has its command password. It will be requested for any PDU con
fi
guration and
control. The administrator can set different command password for different IP dongle group or all IP
dongle groups use the same password.
9. The WS kWh switched / W kWh Monitored PDUs can’t be found by IPM-02?
Please double check the cable connection and the level setting of each PDU. If a cascade chain has
duplicate the level PDUs, it will cause this problem.
10. Is it possible to manage the WS kWh switched / W kWh Monitored PDUs from different
workstations?
Yes, the InfraPower manager supports 5 concurrent login users from different workstations.
Part VII.
FAQ