69
(refer to FSG-PL-01209) and Qmax (refer to FSG-PL-01510) port diagram located on the flash
drive provided with the pump or available from the Hale Products website (www.hale-
products.com).
Refer to Table 24 for a list of tools and/or consumables required for this procedure.
Table 24. Akron Brass Valve R&R Tools And Consumables List
Standard Tools
Special Tools
Consumables
PPE (Eye and Hand Protection)
None
Shop Rag(s) (As Required)
7/16-in Wrench
Cable Ties (As Required)
9/16-in Socket (Or Wrench)
(All valves except 4-in)
Akron Brass Swing-Out™ Valve
<See FSG-PL-01506>
3/4-in Socket (Or Wrench)
(Only 4-in valves)
Driver (Ratchet)
Wire Cutter
Optional (Only Required For Valve Clocking)
3/32-in (T-Handle) Allen Wrench
(Gen I and Gen II Housing Screws)
Loctite 222 (or equivalent)
5/32-in (T-Handle) Allen Wrench
(Gen I Motor Driver Screws)
7/64-in (T-Handle) Allen Wrench
(Gen II Motor Driver Screws)
Perform the following to remove and replace an Akron Brass motorized Swing-Out™ valve used in
a SAM system.
Removal
A.
Tag and disconnect all electric valve actuator connections.
B.
If required, tag and disconnect all drain lines. ONLY disconnect drains required to
remove valve.
C.
If required (applies to all discharge valves), tag and disconnect pressure sensor
electrical connector. Note/record sensor and/or 45-degree adapter orientation.
D.
If required (applies to all discharge valves), tag and disconnect flowmeter electri-
cal connector. (Flowmeters are optional and may NOT be present.)
E.
Remove outlet flange/adapter as follows.
For all except 4-in valves, use a 9/16-in socket and driver (or socket and ratchet, or
wrench), remove four [4] 3/8–16 X 1 1/2-in long screws (with lock and flat washers).
For 4-in valves, use 3/4-in socket and driver (or ratchet, or wrench) to remove four [4]
1/2–13 X 1 1/ 2-in long screws (with lock and flat washers).
Separate flange/adapter from valve.
F.
Remove valve from inlet flange/adapter as follows.
Support valve while removing screws from inlet flange/adapter.
Summary of Contents for Hale Sam
Page 2: ......
Page 37: ...17 Figure 14 SAM Blue CAN Buss Architecture With Three SAM Control Centers Diagram...
Page 38: ...18 Figure 15 SAM Green CAN Buss Architecture With Three SAM Control Centers Diagram...
Page 39: ...19 Figure 16 SAM Red CAN Buss Architecture With Three SAM Control Centers Diagram...
Page 40: ...20 Figure 17 SAM System Drain And Pneumatic Diagram...
Page 41: ...21 Figure 18 SAM Speaks Diagram...
Page 42: ......
Page 58: ...38 THIS PAGE INTENTIONALLY BLANK...
Page 62: ...42 THIS PAGE INTENTIONALLY BLANK...
Page 192: ...172 THIS PAGE INTENTIONALLY BLANK...
Page 206: ...186 THIS PAGE INTENTIONALLY BLANK...
Page 220: ...200 THIS PAGE INTENTIONALLY BLANK...