7. Draw the top panel forward and lift it off the boiler.
8. Remove the 2 screws securing the LH side panel to the
turret front panel and baseplate.
9. Pull the panel forward, disengaging from the collector hood
tab, lifting it clear of the locating peg and remove.
10. Repeat steps 8 and 9 to remove the RH panel.
FLUE KITS
Pack B: supplied as standard.
Pack D: optional extension kit for
side flue or rear flue outlet. Refer
to 'Flue Extension Ducts'
1. A maximum of 3 extension
ducts (plus the standard flue
duct) may be used together.
2. Flue extensions of greater
than 1m (39") should be
supported with the bracket
provided.
It is MOST IMPORTANT that the boiler is installed in a vertical position.
7
DETERMINING THE FLUE LENGTH
6
BOILER CASING REMOVAL - continued
11. The boiler is held to the packaging base by 4 M6
hex head screws. Remove the front screws,
slacken the rear screws and remove the boiler
from the packaging base.
Flue length mm
Pack Requirement
Product No.
Up to 600
B, 1 off
152 227
600 to 1550
B, 1 off + D, 1 off
152132
1550 to 2500
B, 1 off + D, 2 off
152 227+
152132, 2 off
2500 to 3000
B, 1 off + D, 3 off
152 227+
152132, 3 off
WARNING.
For top outlet installation the flue terminal
MUST always be in the horizontal position.
Top outlet flue length
= A + B + Elbow allowance
90
o
Elbow = 1m
45
o
Elbow = 0.7m
INST