21
FP14KC-X
JAN 2023
8)
Check clearance, starting with the right front post by using a straight edge to mark the position of the
bottom of the crossbeam on the post.
9)
Raise lift to full height again. Mark second position. If the gap between two marks is less than 2
”, adjust
locking latch bar to reach clearance of 2
”. Repeat for the other three posts.
10)
Adjust locking latch bar adjustment nut so that the bottom of the top most latch bar slot is at least 2
”
below locking latch. After adjustment, tighten jam nut on post top plate.
11)
If the entire 2
” clearance cannot be attained by adjusting the locking latch bar, adjust the cable. Turn
cable adjusting nut to raise the locking latch 2
” above bottom of latch bar slot. Tighten cable jam nut.
12)
Lower lift, remove wheel chocks and carefully back vehicle off lift.
13)
Raise the lift to full height. LISTEN and WATCH as the first locking latch clicks into place. Synchronize
the other three columns with this column by adjusting their cables so all four latches click at same time.
Tighten cable jam nuts.
NOTE:
When making changes to adjustment nuts on cable end or latch bar stud, always leave
at least two threads showing between top nut and stud end. Be sure all four corners have
passed the locking latch bar slot before lowering lift on locking latches.
Step 10: Final Installation Checks
·
Check that the posts are plumb, and runways are level.
·
Check that all anchor bolts are installed, and properly torqued.
·
Check that the nylon slider guides inside posts are installed, tightened, and greased properly.
·
Check that all cable pulleys are installed correctly and properly greased using the grease zerks.
·
Check that all bolts, nuts, and screws are securely tightened.
·
Check that all cables are routed correctly and are on the correct pulleys.
·
Check that the cable in each post is properly positioned to the slack cable roller.
·
Check that all hydraulic hose connections are secure with no leakages.
·
Check that all airlines are connected properly, and shop air pressure is set 90 to 115 PSI.
·
Check that the air valve and air cylinders are functioning for proper latch release operation.
·
Check that all four latches are engaging the latch racks at the same time.
·
Check for proper oil level in reservoir tank when lift is fully lowered.
·
Check for any strange noises during lifting and lowering.
The Lift Installation is now Complete.