1. Lay bath face down onto a protective surface so as not to damage the bath. Fix leg
adjusters, (Ref. G) onto bath into predrilled holes using screws (Ref H1). Assemble
legs as shown in Fig 2.
2. Push leg sets in to leg adjusters and position leg beams onto baseboard. Mark the
fixing hole positions on the baseboard. Pilot drill the 8 holes in the baseboard, using a
3mm drill to a depth of 6mm maximum. Fix the leg beams to the baseboard using
screws (Ref H1). DO NOT OVER TIGHTEN
3. Locate the 2 pan head self tapping screws (Ref. H2) into leg adjusters and tighten.
Adjust feet to give floor to top of rim height of 560mm
4. Position metal panel clips on to panel clip blocks, Fig. 2a. Pilot drill holes with a 3mm
drill. Use screws (Ref. P) for securing clips.
5. Fit side wall brackets to bath (Ref. K), using pre-drilled holes as a guide. Secure with
screws (Ref. H1). Assemble wall support bracket (Ref. J) onto bath.
6. Fit end panel spring clips (Ref. S) onto bath with screws (Ref T).
7. Fit the single support leg black end cap in a suitable area on the framework,
Figs. 2 & 3.
8. Flip bath onto feet. NOTE: If the bath is to be installed at a lower height than normal,
then provision for the waste trap to be recessed into the floor may be necessary.
Also the bath panel(s) will need to be cut down in height. If lowering panel heights,
remove the material from the bottom of the panel(s) and use wooden blocks (not sup-
plied) to secure to the floor. Reducing the panel height requires great care and Ideal-
Standard cannot accept responsibility for any damage caused.
9. Fit brassware and waste fittings. If the bath is to be installed with a monoblock mixer
a special hole (or holes) is required to accommodate the mixer and will have to be cut
by the installer in an appropriate position on the rim of a no tap hole bath to suit the
bathroom layout. Full details or a template for cutting the hole (or holes) is supplied
with monoblock fittings. A template for cutting two tap holes is supplied with the bath.
Cut tap holes, and fit supply fittings, waste, overflow and trap.
10. Fasten corner wall bracket (Ref. I) onto wall at the correct height (510mm nominal).
11. Place bath into installation position. Ensure bath is levelled and set at the correct
height (510mm to trimmed edge).
12. Fix bath to wall.
INSTALLATION
5041 Tempo Baths:Layout 1 10/09/2013 10:24 Page 9