INSTALLATION:
Prior to any installation works, the power supply must always be disconnected.
It also must be secured to prevent accidental reconnections.
The pump can be connected after all the installation works are carried out on the
pipework which will form a part of the installation with the pump. It must be
remembered that welding or soldering works can introduce mechanical
impurities into the pipework. The pipework should be flushed through, prior to
the installation of the pump.
The pump should be installed with its shaft in a horizontal position. The pump’s
ports can be in different positions to the ones shown in the picture below,
however, the shaft of the pump must always be in a horizontal position.
If the pump is installed with its shaft in a vertical position, the bearings may
become quickly damaged and the pump may fail. This type of equipment
damage is not covered by the warranty and any repairs will have to be paid for.