Procedure
1.
Connect fibre channel cables according to Table 25 on page 68 and Figure 28 on
page 67.
Note:
The customer must use an additional connectivity device between the
optical Fibre directly connected to RMSS optical adapters (for example, Fibre,
ESCON, or FICON) and an external public network. It can be a patch panel,
router, switch, or other suitable device. Optical Fibre connectivity that does not
go over a public network does not require an additional connectivity device.
2.
Use Table 25 on page 68 and Figure 28 on page 67 to verify that the
recommended disk components are cabled correctly. (Connections to the
customer's host network not shown).
3.
Make any necessary adjustments to cable labeling or placement, then go to
“Powering-up the components.”
Powering-up the components
Power-up the recommended hardware components in the order shown in Table 26.
For more information on power-up procedures for each recommended component
type, see the related sections that follow.
Important:
This document references IBM 4.8 TB Fibre Channel Disk Controllers and IBM 7.2
TB Fibre Channel Disk Expansion Units in many of the hardware installation
figures, examples, and procedures.
In addition to the IBM DS4700 disk controller, the TS7650G also supports the
DS5000 disk controller, the DS8000 disk controller and the XIV disk controller, as
well as various non-IBM storage solutions. If the customer has elected to use disk
storage components other than the IBM disk controllers mentioned above, the
figures, examples, and procedures in this document will not apply to the
configuration on which you are working. Therefore, it is suggested that you
determine the make and model of the disk storage components in use and, if
necessary, obtain the related product documentation before you begin installation
of the gateway.
The RAS code no longer sends call home packages for problems with any of the
disk storage products attached to the gateway including DS4700. DS5000, DS8000
and XIV.
However, if the IP address of an SMTP server is provided during RAS package
configuration, the disk storage subsystems that communicate with the RAS
package (which includes DS4700 and DS5000 if they have firmware levels
supported by RAS) will send problem reports to the customer via email.
Table 26. Power-on sequences
Stand-alone configuration
Clustered configuration
Frame breakers
Frame breakers
Power distribution units (PDUs)
Power distribution units (PDUs)
Disk expansion modules
Disk expansion modules
Disk controllers
Disk controllers
Chapter 4. Installing the TS7650G hardware
69
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Summary of Contents for System Storage TS7650G 3958 DD4
Page 2: ......
Page 7: ...Russia Electromagnetic Interference EMI Class A Statement 189 Index 191 Contents v...
Page 8: ...vi IBM System Storage TS7600 with ProtecTIER Installation Roadmap Guide...
Page 10: ...viii IBM System Storage TS7600 with ProtecTIER Installation Roadmap Guide...
Page 12: ...x IBM System Storage TS7600 with ProtecTIER Installation Roadmap Guide...
Page 16: ...xiv IBM System Storage TS7600 with ProtecTIER Installation Roadmap Guide...
Page 30: ...xxviii IBM System Storage TS7600 with ProtecTIER Installation Roadmap Guide...
Page 38: ...xxxvi IBM System Storage TS7600 with ProtecTIER Installation Roadmap Guide...
Page 44: ...6 IBM System Storage TS7600 with ProtecTIER Installation Roadmap Guide...
Page 46: ...8 IBM System Storage TS7600 with ProtecTIER Installation Roadmap Guide...
Page 54: ...16 IBM System Storage TS7600 with ProtecTIER Installation Roadmap Guide...
Page 89: ...Figure 20 Clustered TS7650G power cabling Chapter 4 Installing the TS7650G hardware 51...
Page 120: ...82 IBM System Storage TS7600 with ProtecTIER Installation Roadmap Guide...
Page 148: ...110 IBM System Storage TS7600 with ProtecTIER Installation Roadmap Guide...
Page 150: ...112 IBM System Storage TS7600 with ProtecTIER Installation Roadmap Guide...
Page 156: ...118 IBM System Storage TS7600 with ProtecTIER Installation Roadmap Guide...
Page 172: ...134 IBM System Storage TS7600 with ProtecTIER Installation Roadmap Guide...
Page 192: ...154 IBM System Storage TS7600 with ProtecTIER Installation Roadmap Guide...
Page 198: ...160 IBM System Storage TS7600 with ProtecTIER Installation Roadmap Guide...
Page 210: ...172 IBM System Storage TS7600 with ProtecTIER Installation Roadmap Guide...
Page 220: ...182 IBM System Storage TS7600 with ProtecTIER Installation Roadmap Guide...
Page 228: ...190 IBM System Storage TS7600 with ProtecTIER Installation Roadmap Guide...
Page 231: ......
Page 232: ...Part Number 46X6052 Printed in USA or Mexico GC53 1154 09 1P P N 46X6052...