![IBM Storwize V5100 Series Quick Installation Manual Download Page 93](http://html1.mh-extra.com/html/ibm/storwize-v5100-series/storwize-v5100-series_quick-installation-manual_4472478093.webp)
Figure 81. Reinstalling enclosure end caps
6. If you are installing additional 2U SAS expansion enclosures, repeat the previous steps to complete
the installation.
Powering on the optional 2U SAS expansion enclosures
After you install all the hardware components, power on the optional 2U SAS expansion enclosures and
check their status.
About this task
Attention: Do not power on an expansion enclosure with any open bays or slots.
• Every unused drive bay must be occupied by a filler panel.
• Filler panels must be installed in all empty host interface adapter slots.
Open bays or slots disrupt the internal air flow, causing the drives to receive insufficient cooling.
Procedure
To power on the 2U SAS expansion enclosures, complete the following steps.
1. Use the supplied power cords to connect both power supply units of the first expansion enclosure to
their power sources.
If the power sources have circuit breakers or switches, ensure that they are turned on. The expansion
enclosure does not have power switches. Repeat this step for each expansion enclosure in the system.
Note: Each enclosure has two power supply units. To provide power failure redundancy, connect the
two power cords to separate power circuits.
2. From the rear of the rack, check the LEDs on each expansion enclosure (see Figure 82 on page 69).
Figure 82. Expansion enclosure LEDs
1
Power
Chapter 3. Installing a 2U expansion enclosure 69
Summary of Contents for Storwize V5100 Series