9.

Mark the bottom EIA unit.

10.

Mark the corresponding holes on the left side of the rack.

Installing the HMC into the rack using the fixed rails

If you are installing the 7063-CR1 HMC into the rack using the fixed rails, complete the following tasks.

Attaching the fixed rails to the system chassis and to the rack

You must install the rails onto the chassis and into the rack. Use this procedure to perform this task.

Attention:

To avoid rail failure and potential danger to yourself and to the unit, ensure that you have

the correct rails and fittings for your rack. If your rack has square support flange holes or screw-thread
support flange holes, ensure that the rails and fittings match the support flange holes that are used on
your rack. Do not install mismatched hardware by using washers or spacers. If you do not have the
correct rails and fittings for your rack, contact your IBM reseller.

Note:

The system requires 1 EIA rack unit (1U) of space.

Ensure that you have the necessary parts to install the rails. The following parts are included with the
rail kit:

v

Slide rail screws, used to attach the two parts of each slide rail

v

Slide rail rack screws, used to secure the rails to the rack

v

Rails

v

10 - 32 x 0.635 cm (0.25 in.) screws, used to attach the rails to system chassis

1.

Remove the rail pieces from the packaging and put them on a work surface.

2.

Connect the two parts of each rack slide rail. To connect the two parts of the rack slide rail, perform
the following tasks:

a.

Identify the two pieces of the left rack slide rail. Align the short and long pieces (C). Ensure that
the rack rail pins are pointing in the same direction (A) and (D).

b.

The shorter piece of the rack slide rail has a metal pin. Insert the pin into the hole in the longer
piece of the rack slide rail (B). Slide the shorter piece of the rack rail into the longer piece of the
rack rail.

c.

Align the holes in the two pieces of the rack slide rails. Using a Philips-head screwdriver, attach
the two parts by loosely screwing two rail screws through the holes in the rack slide rail.

Installing the 7063-CR1 into a rack

3

Summary of Contents for Power Systems 7063-CR1

Page 1: ...Installing the 7063 CR1 into a rack IBM...

Page 2: ...ii Installing the 7063 CR1 into a rack...

Page 3: ...7063 CR1 system 1 Installing the HMC into the rack using the fixed rails 3 Attaching the fixed rails to the system chassis and to the rack 3 Installing the system into the rack and connecting and rou...

Page 4: ...iv Installing the 7063 CR1 into a rack...

Page 5: ...tures http www ibm com support knowledgecenter POWER8 p8hbf p8hbf_8xx_kickoff htm Completing inventory for your system Use this information to complete inventory for your system 1 Verify that you rece...

Page 6: ...w access to the inside of the rack enclosure where you plan to place the unit as shown in Figure 1 4 Determine to place the system in the rack Record the EIA location 5 Facing the front of the rack an...

Page 7: ...pace Ensure that you have the necessary parts to install the rails The following parts are included with the rail kit v Slide rail screws used to attach the two parts of each slide rail v Slide rail r...

Page 8: ...e front of the rack rail toward the front of the rack rail flange Align the slide rail pins with the holes in the rail flange and pull them until the rail latch clicks into place f Using a screwdriver...

Page 9: ...e is supported Text based capability is only supported at this time 9 Plug the system power cords and the power cords for any other attached devices into the alternating current AC power source 10 Con...

Page 10: ...arrive fully assembled To install the slide rails into the rack you must disassemble the slide rails into four pieces 1 Remove the lower direct access storage device DASD backplane screw on either sid...

Page 11: ...ng it to the front of the rack and locate the selected EIA unit 5 From the front of the rack insert the pins on the front of the slide rail 1 into the holes on the front of the rack that you previousl...

Page 12: ...the rack Pull the slide rail toward you to insert the two pins 1 into the rack holes 2 Pull the rail until the rail spring clip 3 clicks into place Install the screw 4 to secure the slide rail to the...

Page 13: ...m requires two people to install the system into the rack 1 Fully extend the slide rails until the rails click into the service position A 2 Using two people lift the system and align the lower roller...

Page 14: ...with a green arrow 4 Push the system into the rack 5 Tighten the thumbscrews on either side of the system to secure the system to the rack Figure 9 Aligning the lower roller pins on the chassis rails...