2105 Enterprise Storage Server Clearances and Floor Loading
Service clearances are 1145 mm (45 in) front and 1145 mm (45 in) back.
The following table shows service clearances, floor loading, and side clearance requirements.
Configuration and
Weight kg (lbs.)
Service Clearance
Floor Loading See notes
1 and 3)
Side Clearances (both
Sides) See note 4
Front
mm (in)
Rear
mm (in)
kg/sq m (lbs/sq ft)
mm
inches
Model E10, F10
980 (2160)
1145 (45)
1145 (45)
522 (107)
488 (100)
440 (90)
342 (70)
0
76
178
559
0
3
7
22
Models E20, F20, 800
1175 (2590)
1145 (45)
1145 (45)
610 (125)
488 (100)
440 (90)
342 (70)
0
229
356
762
0
9
14
30
Models E20, F20, 800
with Expansion Enclosure
2495 (5500)
1145 (45)
1145 (45)
586 (120)
488 (100)
440 (90)
342 (70)
0
406
686
See notes 2
and 5
0
16
27
See notes 2
and 5
Notes:
1. It is recommended that the Enterprise Storage Server (ESS) be installed on a floor with a minimum of
342 kilograms per square meter (kg/sq m) (70 pounds per square foot (lbs/sq ft)) strength.
2. If you install a Model E20 or F20 with an expansion enclosure, the minimum floor strength must be
440 kg/sq m (90 lbs/sq ft). At 342 (kg/sq m) (70 (lbs/sq ft)), the side clearance exceeds the 762 mm
(30 in.) maximum allowed. Consult a structural engineer if you are unsure about correct placement and
clearances of these machines for floor loading distribution. You need to install a 28 mm (11 in) spacer
between a Model E20 or a Model F20 and an expansion enclosure.
3. Floor loadings are calculated for maximum weight of the storage server.
4. Side clearances are for both sides of an ESS expansion enclosure. Clearances on both sides are
dedicated to the ESS. Adjoining expansion enclosures must have their own floor loading clearance.
5. Multiple expansion enclosures are bolted together using 28 mm (11 in) spacers. Move the side cover
of the E20 or F20 to the side of the expansion enclosure.
240
Site and Hardware Planning Information
Summary of Contents for 7012 397
Page 1: ...RS 6000 and Eserver pSeries Site and Hardware Planning Information SA38 0508 20...
Page 2: ......
Page 3: ...RS 6000 and Eserver pSeries Site and Hardware Planning Information SA38 0508 20...
Page 11: ...Appendix Notices 385 Index 387 Contents ix...
Page 12: ...x Site and Hardware Planning Information...
Page 16: ...xiv Site and Hardware Planning Information...
Page 18: ...xvi Site and Hardware Planning Information...
Page 26: ...8 Site and Hardware Planning Information...
Page 238: ...220 Site and Hardware Planning Information...
Page 246: ...228 Site and Hardware Planning Information...
Page 284: ...266 Site and Hardware Planning Information...
Page 296: ...278 Site and Hardware Planning Information...
Page 366: ...348 Site and Hardware Planning Information...
Page 372: ...Async Adapter Cable Planning Chart 354 Site and Hardware Planning Information...
Page 377: ...Standard I O Cable Planning Chart Chapter 12 Cable Planning 359...
Page 380: ...Cable Planning Chart Other Adapters 362 Site and Hardware Planning Information...
Page 384: ...366 Site and Hardware Planning Information...
Page 402: ...384 Site and Hardware Planning Information...
Page 404: ...386 Site and Hardware Planning Information...
Page 413: ......
Page 414: ...Printed in USA SA38 0508 20...
Page 415: ...Spine information RS 6000 and Eserver pSeries Site and Hardware Planning Information...