SFC 16-125 - Fuel Conversion to Natural Gas (LP to NG) Kit P-807

|

3

Fuel Conversion Instructions

The following procedure must be carried out by a qualified technician.

Model Number

Orifice Size

SFC 16-125

450

Table 2 

 Natural Gas Orifice Chart

Alternate Natural Gas Orifices - Calorific values 750-

900 BTU/FT

3

Model Number

Orifice Size

SFC 16-125

490

Table 3 

Alternative Naturel Gas Orifice - calorific values between 750-900 BTU/FT

3

To perform a fuel conversion:

 1.  Turn off the gas supply at the manual gas valve.

 2.  Disconnect the electrical power.

 3.  Disconnect the nut at the gas valve outlet (top of the gas valve), and remove the O-ring and orifice.

 4.  Insert the correct orifice into the O-ring, and re-install into the nut at the gas valve outlet (top of the gas valve), 

and then tighten the nut.

 5.  Restore the gas supply by opening the gas control valve.

 6.  Test for leaks by using an approved leak detection solution on all joints.

 7.  Power on the unit.

Now, carefully follow the procedures on Combustion Testing and Adjustment.