Page 30
8. Commissioning
Risk of operating error!
Start-up of the unit is restricted to expert staff
only (electricians or expert personnel with
equivalent training).
Step 1: Check of mechanical integrity and
wiring
»
Open housing cover.
»
Check cylinder seating.
»
Check steam, condensate and
drainhose clamps.
»
Check that all electrical wire connec-
tions (including steam cylinder wir-
ing) are tight and secure.
Step 2: Switching on the steam humidifier
»
Switch on main breaker.
»
Open water supply stopcock (opera-
ting pressure should be 1bar min.,
10bar max.).
»
Switch on unit by setting control
switch to “I”.
Step 3:
The unit performs a self-test and,
then, commences normal operation
•
During self-test, the On/Off button icon
flashes for a couple of seconds
•
After the self-test of the controller, the
display shows the setup view for the
basic device settings (language, date,
time and control settings). Refer to the
chapter "Commissioning" in the opera-
ting instructions for the control system.
•
Consequently, normal operation is
commenced. However, steam is not
produced without a demand pending
Step 4: Trigger steam demand
»
Set control to 1-step operation, i.e.
permanent steam demand, and
close safety interlock.
»
Allow all electrical functions to termi-
nate in their programmed order.
Step 5: Monitor unit function and check
for leakage
»
Let unit operate for 15 to 30 minutes.
»
If leaks appear, switch off the unit.
Risk of electrical shock!
Hazardous electrical voltage!
Follow safety instructions for work on live
components.
Step 6: Repair leaks
»
Find leaks and eliminate.
»
Check again for leaks.
»
When everything is o.k., reattach
housing cover.
WARNING
!
WARNING
!