interface LoopBack0
ip address 5.5.5.9 255.255.255.255
#
ospf 1
area 0.0.0.0
network 5.5.5.9 0.0.0.0
network 40.1.1.0 0.0.0.255
#
return
l
Configuration file of CE-B
#
sysname CE-B
#
vlan batch 160
#
interface Vlanif160
ip address 100.1.1.2 255.255.255.0
#
interface GigabitEthernet1/0/0
port hybrid pvid vlan 160
port hybrid untagged vlan 160
#
return
6.37.26 Example for Configuring an NQA Test Group
Networking Requirements
Switch A functions as the NQA client to check whether Switch B and Switch C are reachable.
Figure 6-28
Networking diagram for configuring an NQA test group
SwitchC
SwitchB
test2
GE1/0/0
VLANIF110
10.1.1.1/24
GE1/0/0
VLANIF110
10.1.1.2/24
GE1/0/0
VLANIF120
10.2.1.2/24
GE2/0/0
VLANIF120
10.2.1.1/24
test1
SwitchA
Configuration Roadmap
The configuration roadmap is as follows:
1.
Configure Switch A as the NQA client.
2.
Create an NQA test group that consists of two tests to check whether the test packets from
Switch A can reach Switch B and Switch C and to check the RTT of the packets.
Quidway S9300 Terabit Routing Switch
Configuration Guide - Network Management
6 NQA Configuration
Issue 03 (2010-09-20)
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
6-225