Figure 3-41
Installing a door frame
Step 3
Put M6x16 screws through the fixing plate, as shown in 4 in
. Then secure the
door post to the cabinet side post using the fixing plate, as shown in 3 in
The space around the lower part of a door post is narrow. Therefore, use a small box-end wrench or a
small adjustable wrench if required.
, 3 is a magnified view of the left post, and should contain a fixing plate as the screw
washer. The figure is for reference only.
, the recommended torque for 4 is 2.94 N•m±10%.
If the cabinet side beam has a hole, secure it to the cabinet bottom. If the side beam does not have a
hole, secure it to the cabinet bottom sealing plate. If an adaptive frame is available, secure it to the
bottom of the adaptive frame.
----End
Leveling the Doorhead
Context
Check whether the doorhead is level by using a spirit level. Adjust the doorhead if the
levelness deviation exceeds 0.5°.
Procedure
Step 1
Observe the levelness of the doorhead. Adjust the anchor bolts of cabinets if it is not level.