Procedure
Step 1
Connect one end of the network cable to the Ethernet port on the TCP/IP card in the
Galaxy7000 UPS.
Step 2
Connect the other end of the network cable to the Ethernet port on the switch.
----End
10.12.37 Connecting a Monitoring Cable to a Delta 120 kVA UPS
Prerequisites
An RS485 monitoring cable is prepared.
You are familiar with the functions of all ports on the CCU collector by referring to
10.12.2 Port Description for the CCU Collector
You are familiar with the functions of all ports on the ECC collector by referring to
10.12.3 Port Description for the ECC Collector
Procedure
Step 1
Connect the cord end terminal of the RS485 monitoring cable to the Modbus card in the Delta
120 kVA UPS.
lists the mapping between the wiring terminals on the Modbus
card and the colors of core wires in the cord end terminal.
Table 10-72
Mapping between the wiring terminals on the Modbus card and the colors of core
wires in the cord end terminal
Wiring Terminal on the
Modbus Card
Wiring Terminal in the
Modbus Card
Color of Core Wire in the
Cord End Terminal
CCU collector
1
Orange and white, blue
2
Orange, blue and white
ECC collector
1
Orange and white
2
Orange
Step 2
Connect the RJ45 connector of the RS485 monitoring cable to the RS485 port on the CCU
collector or ECC collector.
----End
10.12.38 Connecting a Monitoring Cable to a Riello UPS
Prerequisites
A network cable used for monitoring is prepared.