Figure 9-2
Installing guide rails
1.
Place the guide rails horizontally at the position where the cabinet is installed, as shown
by 1 in
2.
Fix the guide rails using rubber plugs, as shown by 2 in
−
In front of the guide rails: If a server is installed using the upper mounting holes,
insert rubber plugs tightly into the holes at the middle. If a server is installed using
mounting holes at the middle, insert rubber plugs tightly into the upper holes.
−
Behind the guide rails: Insert rubber plugs tightly into the upper mounting holes.
3.
(Optional) To enhance the rigidness and seismic-proof performance of a server, you can
install bolts at the rear of flexible guide rails, as shown by (3) in
Step 3
Place the RH2288 on the guide rails and push it in to the rack. As shown in
Figure 9-3
Installing the RH2288