7.2.4.3 Installing Holding Rails
The holding rails apply to a cabinet with a distance of 610 mm to 914 mm (24.02 in. to 35.98
in.) between the front and rear mounting bars.
The 2288H V5 servers are stackable onto holding rails.
Procedure
Step 1
Holding down the release latch at the front end of the holding rail, pull out the locking plate
by its hook. See (1) and (2) in
Step 2
Aligning the screws on the back end of the holding rail with the mounting holes of the
cabinet, insert the rail into position so that the latch clicks into place. See (3) in
Step 3
Aligning the top screw on the front end of the holding rail with the level mounting hole of the
cabinet, insert the rail into position. See (4) in
.
Step 4
Push back the locking plate by its hook until the release latch clicks into place. See (5) in
Step 5
Secure the back end of the rail with an M6 screw through the third mounting hole in the
cabinet. See (6) in
.
Although the holding rails do not need screws for installation, we recommend you use M6 screws at the
rear end to make the server more shockproof and secure.
Figure 7-7
Installing a holding rail
Step 6
Install the other guide rail in the same way.
----End