1.
Connect lights in series, and connect the light near the AC actuator to the cable delivered
with the light. Here, the female connector is used as an example, as shown by (1) in
2.
Cut off the connector at the other end of the cable delivered with the light, strip the
insulation layer from the cut end, and route the cable out of the aisle containment, as
shown by (2) in
The cable outlets for aisle lights are on the outermost skylight plate.
3.
Connect the cut end to the multi-wire terminal onsite, as shown by (3) in
When connecting the cables, mark the L (brown) and N (blue) wires to ensure correct
connection.
4.
Route the other end of the connected cable (as shown by B in
) through the
cable trough to obtain power from the AC actuator.
Figure 12-17
Cable connections to aisle lights
(A) Light
(B) To the AC actuator
12.8 Installing an SMS Modem
Prerequisites
An idle serial port is available on the server.
Context
Bind an SMS modem (BOM number: 50030084) to the rack rail at the rear of the network