Connection Engineering Precautions
●
Air duct installation: It is recommended that flexible connections be used
between the unit and air duct. Prepare air ducts based on site requirements.
●
Pipe thermal insulation: Take thermal insulation measures for all inlet pipes
and drainpipes of the FusionCol8000-E. Reserve sufficient space for
maintenance and operations when installing thermal insulation foam for
valves and connectors. At low temperatures, take thermal insulation measures
to prevent water pipes from freezing.
3.1.2 Maintenance Space
Reserve sufficient space around the equipment for operation and ventilation.
Figure 3-1 Maintenance space (not combined) (unit: mm)
(1) Wall
(2) Indoor air supply vent
(end)
(3) Electric control box
Figure 3-2 Maintenance space (combined) (unit: mm)
(1) Wall
(2) Indoor air supply vent
(end)
(3) Electric control box
FusionCol8000-E240 Modular Indirect Evaporative
Cooling System
User Manual
3 System Installation (Building Scenario)
Issue 02 (2021-04-15)
Copyright © Huawei Technologies Co., Ltd.