HUAWEI  BTS3012 Fast Installation Guide                                                            Internal Use 

  BTS3012 Fast Installation Guide 

Installation Process 

 

 

 

 

 

Yes

 

No

 

No

 

Yes

 

No

 

Yes

 

No

 

Yes

 

Installation starts 

Is the cabling rack needed?

 

Install the cabling rack

 

Is the grounding bar needed?

 

Install the grounding bar

 

Install the cabinet

 

Install the boards

 

Is the sidepower power system needed? 

 

Install cables

 

Check the installation of hardware 

 

Does the installation pass the check?

 

Reinstall the parts that do not pass the check

 

Installation ends

 

Install the sidepower power system 

 

Summary of Contents for BTS3012

Page 1: ... cabling rack needed Install the cabling rack Is the grounding bar needed Install the grounding bar Install the cabinet Install the boards Is the sidepower power system needed Install cables Check the installation of hardware Does the installation pass the check Reinstall the parts that do not pass the check Installation ends Install the sidepower power system ...

Page 2: ... can be installed in the following modes Install the cabinet on the cement ground with enough bearing capacity Install the cabinet on the antistatic floor Install the cabinet on the cement ground with insufficient bearing capacity Install combined cabinets The guide describes how to install a BTS3012 cabinet on the cement ground with enough bearing capacity To know other installation modes refer t...

Page 3: ... sealing window of feeder cables to reduce the length of feeder cables In all installation conditions use a horizontal ruler to measure the levelness of cabinets and ensure that the cabinet to be installed is on a horizontal surface with other cabinets in the equipment room Notes Do not install a cabinet close to the wall When installing a cabinet along the wall reserve a gap of at least 10cm Cabi...

Page 4: ...n of the front door of the cabinet Caution In a building made of lift slabs do not install multiple cabinets on a slab Install expansion bolts Use a Ф16 drill hammer to install M12 expansion bolts For the process of installing expansion bolts refer to the HUAWEI BTS3012 Base Station Installation Manual Cabinet Installation 457 1 600 Front Rear Left Right 24 370 1 450 Hole position of expansion bol...

Page 5: ... bottom frame If the bottom frame is out of the horizontal add leveling washers below the insulation plate to level the bottom frame Check the insulativity Check the resistance of the bottom frame If the resistance is equal to or bigger than 5MΩ the bottom frame is insulated from the ground You can fix the cabinet then If the resistance is smaller than 5MΩ the bottom frame is not insulated You nee...

Page 6: ...ttom frame tightly combined 3 Use two bolts to fasten the upper and bottom frames 4 Fix the panel at the front of the base 5 Fasten the assembled bolts on the panel Finish the installation After a cabinet is installed check the surface of the cabinet Paint the cabinet if the paint on the cabinet peels off Install the boards Prepare for the installation Notes Before installing a board pay attention...

Page 7: ... 1 8 E1 cables S3 is reserved For the description of DIP switches refer to the silk print on the board or the HUAWEI BTS3012 Base Station Installation Manual Cabinet Installation ON S4 S5 S6 S7 OFF S3 4 1 4 1 4 1 4 1 4 1 2 Rotate the foursquare bolts clockwise on the panel of the board clockwise to ensure that the bolts are movable Pull out the handle bars on the DTMU panel and push the DTMU board...

Page 8: ...en DIP switches can be set through dynamic data configuration console Remove the anti dust cover when setting the DIP switch SW_AV 1 Set DIP switches on the DEMU board according to the type of sensor signals Eight DIP switches are distributed on the DEMU board For description of DIP switches refer to the silk print on the board or the HUAWEI BTS3012 Base Station Installation Manual Cabinet Install...

Page 9: ...sion tubes into the installation holes 4 Use bolts to fasten the door status sensor on the doorframe and door Water sensor Place the sensor at the place where water easily penetrates or lower place in the equipment room To install the water sensor do as follows 1 Select a lower position in the equipment room or the position below the BTS equipment and clean the position 2 Place the water sensor ho...

Page 10: ...1 5m To install the temperature and humidity sensor do as follows 1 Remove the backplane of the temperature and humidity sensor 2 Use a pencil to mark three hole positions for the backplane on the wall 3 Use a percussion drill to drill holes at the marked positions 4 Put the plastic expansion tubes into the installation holes 5 Use bolts to fix the backplane of the temperature and humidity sensor ...

Page 11: ... boards to avoid scald The DDPU boards are hot swappable After removing a DDPU board install protective caps on connectors of the power cables so that the inner conductor in the cable connectors do not contact the edges or corners of the cabinet which may cause accidents After installation put the removed protective caps at the bottom of the cabinet for the sake of future use Install protective ca...

Page 12: ... R15 R16 P14 S9 S10 S10 S11 S11 S12 2 S12 1 S12 3 S12 4 S12 6 S12 DCCU Signal cable Power cable RF cable S12 S9 S13 1 S13 2 DATU R20 R7 R2 R21 R22 R23 R24 R25 R26 R27 R28 R30 R29 R11 R17 R18 D T R B DCSU S14 S13 S16 S16 S17 S17 1 S17 2 P15 BBU Transmission subrack P15 P10 P13 P15 P15 S15 S15 P7 P8 Notes In the preceding figure the RF connection cables are configured between the DTRU and DDPU board...

Page 13: ...ector of the Rx cable to the RX port of the DDPU board and screw down the cable connector 2 Connect the other SMA angle male connector of the Rx cable to the Rx port of the DTRU board and screw down the cable connector 3 Connect one N angle male connector of the Tx cable to the Tx port of the DDPU board and screw down the cable connector 4 Connect the other N angle male connector of the Tx cable t...

Page 14: ... the upper and the bottom connectors at the same time Install 1 2 inch indoor jumpers Installing 1 2 inch indoor jumpers Caution Tightly connect 1 2 inch indoor jumpers to avoid leakage of radio frequency signals Connect one end of 1 2 inch indoor cable to the ANT port of the DDPU board and connect the other end to the feeder cable through the feeder connector To install the 1 2 inch indoor cable ...

Page 15: ...ge distance from each other and in a proper degree of tightness The cables should have a good shell The radius of the cable curve cannot be smaller than 20 times of the core diameter of the cable Distribute power cables according to the requirements of engineering drawing When distributing power cables do not connect two power cables with connectors or by soldering if a power cable is not long eno...

Page 16: ...hat the adjustable wrench is bounded with insulated tape Install the protection ground cable Installing a protection ground cable The protection ground cable is a plastic insulation copper core cable of which the colors are yellow and green and the cross sectional area is bigger than 16mm2 usually 25 mm2 To connect a protection ground cable do as follows 1 Get a piece of power cable with a proper ...

Page 17: ... as follows 1 Insert the DB25 male connector of the E1 cable into the DB25 female socket on the DELC board at the top of the cabinet and screw down the bolts 2 Get cables of proper length according to the actual situation create cable connectors distribute cables on cabling racks and connect the connectors to the cable connection terminals on the cabling racks 3 Stick labels on the E1 cables Insta...

Page 18: ...minal Lightning arrester of power Anti lightning failure alarm cable of combined cabinets S1 S1 and S2 S2 interfaces of the DSAC 2PIN phoenix terminal Corresponding interface of the slave cabinet Environment monitoring device signal cable COM1 port and COM2 port of the DSAC DB9 male connector Environment monitoring device The installation specifications of signal cables at the top of the cabinet a...

Page 19: ...f the DTMU 1 Turn the power switch of the public subrack to ON 2 Observe the RUN indicator on the DTMU board in the public subrack The RUN indicator should be slowly blinking lighted 1s and off 1s if the DTMU is normal Power on check of the DTRU 1 Turn on the DC air break switch of the DTRU subrack 2 Check the RUN indicator on the DTRU plane The RUN indicator should be slowly blinking lighted 1s a...

Page 20: ... ANT1 ANT2 ANT3 Cable TX Cable RX Cable TX Cable RX Cable TX Cable RX CELL0 Label Ant_0A Ant_0B Ant_0C Ant_0D Ant_0E Ant_0F CELL1 Label Ant_1A Ant_1B Ant_1C Ant_1D Ant_1E Ant_1F CELL2 Label Ant_2A Ant_2B Ant_2C Ant_2D Ant_2E Ant_2F By sticking the preceding labels you can distinguish three different feeder cables of three sectors The same method can be used to stick labels to jumpers in the antenn...

Page 21: ...rounding network All outdoor BTSs need grounding network Establish the grounding network and test the quality of grounding network before civil construction For construction of the grounding network refer to the following picture D D P U Dual polarization antenna Feeder cable 1 2 inch jumper 1 4 inch jumper CR1 CR2 CR3 CR4 CR5 CR6 CR7 CR8 CRn indicates the code of colored rings The feeder cables o...

Page 22: ...ed tilt of the antenna lever to 0 namely pull out the electric adjusted antenna lever and fix it to 0 2 During the construction do not pull the lever out from the electric adjusted antenna Pull out the lever and set it to 0 after the antenna is mounted 3 Make simple waterproof processing of the two unused antenna interfaces in the dual band antenna 4 The angle between the antenna and support shoul...

Page 23: ...th at the antenna side and the cabinet side to avoid incorrect connection of feeder cables 6 When distributing feeder cables at the rear of the cabinet keep the feeder cables a proper distance away from the power cables and transmission cables to avoid horizontal cross connection 7 The feeder cables may cross the top of the building to the outside of the wall so you need wear a protective tube on ...

Page 24: ...nding bar 4 The angle between a feeder cable and its grounding cable should be smaller than 15 Testing the antenna system 1 Use a radio analyzer to test the standing wave ratio of DIN male connector of the 1 2 inch jumper connecting the antenna system 2 The standing wave ratio should be smaller than 1 3 3 If the standing wave ratio is equal to or bigger than 1 5 the antenna system has faults In th...

Page 25: ... tapes and PVC tapes to make waterproof processing for cables at the positions where jumpers connect to the tower amplifier and the positions where jumpers connects feeder cables To protect the cables against water and avoid the standing wave alarms create waterproof curves at the positions where jumpers and feeder cables connect Use the tape to wrap a jumper where it connects to another cable Exp...