DBS3900 LampSite
Installation Guide
7 Installing a pRRU3901
Issue 08 (2016-05-30)
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
106
Figure 7-42
Installing jumpers between the pRRU3901 and external antennas
----End
Follow-up Procedure
1.
Route the cable, and then use a cable tie to bind the cable. For details, see 7.5.1
Requirements for Cable Layout.
2.
Label the installed cable. For details, see section 15.4 Attaching an L-Shaped Label.
7.6 Checking the pRRU3901 Hardware Installation
pRRU3901 hardware installation checking includes hardware and cable installation checking.
Table 7-9 lists the hardware installation checking items.
Table 7-9
Hardware installation checking list
No.
Item
1
Ensure that the pRRU3901 is not grouned.
2
The position for each device conforms to the engineering design and meets the
space requirement.
3
Ensure that the pRRU3901 is properly installed.
4
The surface of the pRRU3901 is neat and clean. The external paint is intact.
The labels, tags, and nameplates are correct, legible, and complete.
Table 7-10 lists the check items of the signal cable connection.
Table 7-10
Checklist for the signal cable connection
No.
Item