background image

l

When the authentication access equipment is used, the authentication mode of Radius
(remote authentication dial-in user service) and the authentication method of EAP should
be configured, because certificate authentication is adopted at present.

l

When the AAA server is used, the CA certificates of terminal users should be uploaded,
and the file names of the user certificate and private key should be configured for the AAA
server.

Procedure

Step 1

Check the configuration of the security GW according to 

Table 6-3

.

Step 2

Ensure that Huawei root CA certificate and Huawei CRL file are configured on the security GW.

Step 3

Configure the authentication access equipment. The authentication access equipment may vary
with different operators. The example here describes a typical configuration of an authentication
access equipment. Take the Quidway S6500 series Ethernet switch as an example. Run the

dot1x

 command to enable the global 802.1x feature. Run the 

dot1x [ interface interface-

list ]

 command to enable the 802.1x feature on a specified port. Run the 

dot1x authentication-

method { chap | pap | eap }

 command to set the EAP authentication method. For details, see

the 

Quidway S6500 Series Ethernet Switches Operation Manual

.

Step 4

Configure the eNodeB CA certificate for the AAA server. The AAA server may vary with
different operators. The descriptions here take the infoX AAA as an example. For details, see
the 

infoX AAA Commissioning Guide

.

1.

Upload the CA certificate of a terminal user to the 

iscc2/config/secert

 directory of infoX

AAA.

2.

Change the file names of the user certificate and private key in the SCPCFG.INI file. Ensure
that the file names are consistent with the file names of the user certificate and private key
uploaded in step 

Step 4.1

.

----End

6.3 Upgrading Software and Configuring Data by Using the
USB Disk

You can locally upgrade software and configure data of a base station by using the USB disk on
the base station side.

Context

CAUTION

l

If a USB disk is to be used repeatedly, the target software and data configuration file in the
USB disk should be updated before the USB disk is used for a base station deployment.

l

When you save the software and data configuration file to the USB disk, ensure that the write
lock (if any) on the USB disk is unlocked. Otherwise, the software and data configuration
file cannot be updated to the USB disk.

6 Commissioning the MBTS by Using USB and M2000

3900 Series Multi-Mode Base Station

Commissioning Guide

6-12

Huawei Proprietary and Confidential

Copyright © Huawei Technologies Co., Ltd.

Issue 02 (2010-07-30)

Summary of Contents for 3900 Series

Page 1: ...3900 Series Multi Mode Base Station V100R003 Commissioning Guide Issue 02 Date 2010 07 30 HUAWEI TECHNOLOGIES CO LTD ...

Page 2: ......

Page 3: ...be within the purchase scope or the usage scope Unless otherwise specified in the contract all statements information and recommendations in this document are provided AS IS without warranties guarantees or representations of any kind either express or implied The information in this document is subject to change without notice Every effort has been made in the preparation of this document to ensu...

Page 4: ......

Page 5: ...ng table lists the product versions related to this document Product Name Version DBS3900 V100R003 BTS3900 V100R003 BTS3900A V100R003 BTS3900L V100R003 Intended Audience This document is intended for l Field engineers l Commissioning engineers 3900 Series Multi Mode Base Station Commissioning Guide About This Document Issue 02 2010 07 30 Huawei Proprietary and Confidential Copyright Huawei Technol...

Page 6: ......

Page 7: ...onitoring the MBTS Commissioning 4 15 4 6 1 Viewing the Progress and Status of an MBTS Commissioning Task 4 16 4 6 2 Handling MBTS Alarms 4 18 4 6 3 Diagnosing MBTS Faults 4 19 4 6 4 Viewing the Service Verification Results of an MBTS 4 20 4 6 5 Restarting Deleting MBTS Commissioning Tasks 4 22 4 7 Confirming the Completion of MBTS Commissioning 4 22 4 8 Obtaining the MBTS Commissioning Report 4 2...

Page 8: ...aining a NodeB Commissioning Report 5 36 5 8 3 Obtaining an eNodeB Commissioning Report 5 36 5 9 Checking the Operating Status of the Base Station 5 37 5 9 1 Checking the Running Status of the GBTS 5 37 5 9 2 Checking the Running Status of the NodeB 5 38 5 9 3 Checking the Running Status of the eNodeB 5 38 5 10 Testing the Basic Services of the eNodeB 5 41 5 11 Confirming the Commissioning Task 5 ...

Page 9: ...P address of the SMT Client 7 6 7 2 2 Connecting the SMT Client and the Base Station 7 7 7 2 3 Logging In to the SMT 7 8 7 3 Configuring the Basic Data of the GBTS 7 9 7 3 1 Obtaining the Site Management Rights 7 10 7 3 2 Configuring Base Station Boards 7 11 7 3 3 Configuring BTS Logical Objects 7 16 7 4 Checking the Transmission Between the BBU and the BSC on the BTS Side 7 28 7 5 Running the Nod...

Page 10: ......

Page 11: ...re 5 11 Monitor tab page 5 46 Figure 5 12 Service Verification tab page 5 47 Figure 5 13 Summary information in the GBTS commissioning report 5 48 Figure 5 14 Page of details of a GBTS in the commissioning report 1 5 49 Figure 5 15 Page of details of a GBTS in the commissioning report 2 5 50 Figure 5 16 NodeB Auto Deployment window NodeB List tab page 5 52 Figure 5 17 NodeB Auto Deployment window ...

Page 12: ...figuration dialog box 6 7 23 Figure 7 20 Configured cell and channels 7 24 Figure 7 21 Site Opstart dialog box 7 25 Figure 7 22 Cell Opstart dialog box 7 25 Figure 7 23 BT Opstart dialog box 7 26 Figure 7 24 RC Attributes Management dialog box 7 26 Figure 7 25 RC Opstart successfully dialog box 7 27 Figure 7 26 Board Management window 7 28 Figure 7 27 Physical loopback of the E1 T1 cable at the DD...

Page 13: ...e 5 45 Table 5 7 Monitor tab page 5 46 Table 5 8 Page of summary information in the GBTS commissioning report 5 48 Table 5 9 Page of details of a GBTS in the commissioning report 1 5 49 Table 5 10 Page of details of a GBTS in the commissioning report 2 5 50 Table 5 11 Parameters in the NodeB deployment list 5 54 Table 6 1 Saving path of the file 6 7 Table 6 2 Tools required for the local commissio...

Page 14: ...Table 7 7 Data sheet for eNodeB commissioning 7 46 Table 8 1 Communication ports on the GBTS 8 1 Table 8 2 Communication ports on the NodeB 8 1 Table 8 3 Communication ports on the eNodeB 8 3 Tables 3900 Series Multi Mode Base Station Commissioning Guide xii Huawei Proprietary and Confidential Copyright Huawei Technologies Co Ltd Issue 02 2010 07 30 ...

Page 15: ...utions for the commissioning scenarios are provided 4 Commissioning the MBTS in GU Mode on the M2000 The description of the preparation and procedure for commissioning the MBTS using the MBTS plug and play commissioning function is optimized 5 Commissioning the MBTS in GL or UL Mode on the M2000 The remote commissioning solution is optimized 6 Commissioning the MBTS by Using USB and M2000 The comm...

Page 16: ... prerequisites is integrated into the description of commissioning modes Commissioning prerequisites 01 2010 05 04 This is the draft release of V100R003 1 Changes in 3900 Series Multi Mode Base Station Commissioning Guide 3900 Series Multi Mode Base Station Commissioning Guide 1 2 Huawei Proprietary and Confidential Copyright Huawei Technologies Co Ltd Issue 02 2010 07 30 ...

Page 17: ...it is physically an MBTS and does not provide services of the two modes Now the base station starts to provide services of two modes l The base station has been providing services of one mode and now starts to provide services of the other mode In this scenario when a base station is deployed it is physically an MBTS and has been providing services of one mode Therefore the base station starts to ...

Page 18: ... preceding commissioning solution without co transmission l If the base station starts to provide services of mode B configure the base station in mode A and then commission the base station in mode B For details see 3 Procedure for Commissioning the Base Station that Starts to Provide Services of One Mode 3 One scenario The base station starts to provide services of two modes The other scenario T...

Page 19: ...ode Commission the base station in each mode respectively on the M2000 For details see 5 Commission ing the MBTS in GL or UL Mode on the M2000 3900 Series Multi Mode Base Station Commissioning Guide 2 Introduction to MBTS Commissioning In Typical Scenarios Issue 02 2010 07 30 Huawei Proprietary and Confidential Copyright Huawei Technologies Co Ltd 2 3 ...

Page 20: ...oftware is upgraded and the MBTS data is configured detect faults according to the LED status and rectify the faults immediately In this way maintenance personnel do not need to go to the site twice For details see 6 Commissionin g the MBTS by Using USB and M2000 2 Introduction to MBTS Commissioning In Typical Scenarios 3900 Series Multi Mode Base Station Commissioning Guide 2 4 Huawei Proprietary...

Page 21: ...establish a remote OM link quickly This commissioning mode requires a portable computer and has a high demand on the skill of commissioning personnel In addition the deployment cost is high in this commissioning mode Therefore this commissioning mode serves as an auxiliary solution For details see 7 Commissionin g the MBTS by Using Local Maintenance Terminal and M2000 3900 Series Multi Mode Base S...

Page 22: ...troduction to MBTS Commissioning In Typical Scenarios 3900 Series Multi Mode Base Station Commissioning Guide 2 6 Huawei Proprietary and Confidential Copyright Huawei Technologies Co Ltd Issue 02 2010 07 30 ...

Page 23: ...d Commissioning Procedure Without Co transmission Assume that the MBTS supports mode A and mode B that co transmission is unavailable to the two modes and that services of only mode A starts to be provided NOTE The alarm Inter System Communication Failure may be reported when the base station in mode A is commissioned and the alarm RRU Network Topology Type and Configuration Mismatch Inter System ...

Page 24: ...ccordingly l The MBTS works in GU mode and UMTS services are provided at first Or the MBTS works in GL mode and LTE services are provided at first Commission the MBTS in mode A by following the procedure for commissioning a single mode base station For details see the GBTS Commissioning Guide NodeB Commissioning Guide or eNodeB Commissioning Guide accordingly Commissioning Procedure With Co transm...

Page 25: ...d the data configuration file locally using a USB disk For details see 6 3 Upgrading Software and Configuring Data by Using the USB Disk NOTE You can configure other data of the base station in mode A after it is planned The data configuration of boards such as PMU and FUN in mode A must comply with mode B Otherwise alarm are reported because of configuration conflict 2 Commission the MBTS in mode...

Page 26: ......

Page 27: ... MBTS commissioning 4 3 Creating an MBTS Commissioning Task This chapter describes how to create an MBTS commissioning task After completing MBTS commissioning preparations you can create an MBTS commissioning task on the M2000 and enable the M2000 to commission the MBTS automatically 4 4 Manually Intervening the MBTS Transmission Detection This section describes how to manually intervene GBTS tra...

Page 28: ...about the commissioning process When a commissioning task is still in progress or is complete you can obtain and analyze the commissioning report to learn the commissioning details to view the exceptions that occur during the commissioning or to determine whether to complete the commissioning 4 9 References for the MBTS Commissioning Interface This chapter describes the interfaces and parameters f...

Page 29: ...site Prepare for MBTS commissioning by referring to 4 2 Preparing for MBTS Commissioning Commissioning Flowchart Figure 4 1 shows the procedure for commissioning an MBTS in GU mode Figure 4 1 Flowchart for MBTS commissioning in GU mode on the M2000 3900 Series Multi Mode Base Station Commissioning Guide 4 Commissioning the MBTS in GU Mode on the M2000 Issue 02 2010 07 30 Huawei Proprietary and Con...

Page 30: ...etails see 4 7 Confirming the Completion of MBTS Commissioning Step 6 Obtain the MBTS commissioning report For details see 4 8 Obtaining the MBTS Commissioning Report End 4 2 Preparing for MBTS Commissioning This section describes how to prepare for MBTS commissioning Prepare for MBTS commissioning by referring to Table 4 1 Table 4 1 Preparing for MBTS commissioning in case of new deployment of bo...

Page 31: ...p Operation 1 Run the ACT BTS command to activate the GBTS 2 Upload the GBTS configuration data to the controller and validate it on the controller side 3 Upload the GBTS target version software package to the controller Prepare for MBTS commissioning at NodeB by referring to Table 4 3 NOTE Before both a GBTS and a NodeB are newly deployed or before a NodeB is newly deployed while a GBTS is runnin...

Page 32: ...BTS commissioning task when the NodeB is normal and you need to deploy a GBTS After making MBTS commissioning preparations you can create an MBTS commissioning task on the M2000 and enable the M2000 to commission the MBTS automatically 4 3 1 Creating an MBTS Commissioning Task Deploying Both the GBTS and the NodeB This section describes how to create an MBTS commissioning task when you need to dep...

Page 33: ... on the toolbar to import the MBTS deployment list Only GBTS deployment lists in csv format can be imported to the M2000 After the MBTS deployment list is imported the M2000 checks whether any mandatory parameter in the list is null and whether the MBTS is valid In addition the information indicating whether the import succeeded or failed is displayed on the Operation Information tab page l The im...

Page 34: ...rmed successfully For details see 4 6 1 Viewing the Progress and Status of an MBTS Commissioning Task 4 3 2 Creating an MBTS Commissioning Task Deploying a NodeB When the GBTS Is Normal This section describes how to create an MBTS commissioning task when the GBTS is normal and you need to deploy a NodeB After making MBTS commissioning preparations you can create an MBTS commissioning task on the M...

Page 35: ...ployment Type is set to NodeB it indicates that you need to add a NodeB when the GBTS is normal l If Auto Deployment Type is set to GBTS it indicates that you need to add a GBTS when the NodeB is normal Step 3 Click on the toolbar to import the MBTS deployment list Only GBTS deployment lists in csv format can be imported to the M2000 After the MBTS deployment list is imported the M2000 checks whet...

Page 36: ...k 4 3 3 Creating an MBTS Commissioning Task Deploying a GBTS When the NodeB Is Normal This section describes how to create an MBTS commissioning task when the NodeB is normal and you need to deploy a GBTS After making MBTS commissioning preparations you can create an MBTS commissioning task on the M2000 and enable the M2000 to commission the MBTS automatically Prerequisite l The M2000 client is st...

Page 37: ...eployment Type is set to GBTS it indicates that you need to add a GBTS when the NodeB is normal Step 3 Click on the toolbar to import the MBTS deployment list Only GBTS deployment lists in csv format can be imported to the M2000 After the MBTS deployment list is imported the M2000 checks whether any mandatory parameter in the list is null and whether the MBTS is valid In addition the information i...

Page 38: ...anually Intervening the MBTS Transmission Detection This section describes how to manually intervene GBTS transmission during MBTS commissioning By intervening GBTS transmission you can query the real time status of the E1 T1 port to ensure that the GBTS transmission is normal and that you can proceed with the GBTS deployment Prerequisite The automatic software commissioning already starts and the...

Page 39: ...normal the M2000 terminates the commissioning and reminds the user of the situation Table 4 4 Automatic commissioning procedures of the MBTS Commissioning Procedure Description Establishing OM channel automatically The M2000 can automatically establishes an OM channel with the base station based on the deployment list provided that the transport network is functional Then the M2000 commissions the...

Page 40: ...ion and configuration data of the base station are upgraded to the target ones After confirmed the M2000 skips this step and directly proceeds with the automatic software commissioning l For the NodeB the M2000 downloads the target software and data configuration file from the server to the NodeB and completes software upgrade and configuration activation automatically l For the GBTS the M2000 ins...

Page 41: ...g CS related and PS related counters of the NE to check whether the NE is operating normally When non zero values exist for all the counters the service check is passed otherwise the service check phase is always sustained Completing commissioning After service check is completed the deployment task state is displayed as Confirm Completed Deployment After you confirm that the commissioning task is...

Page 42: ...r delete ongoing MBTS commissioning tasks 4 6 1 Viewing the Progress and Status of an MBTS Commissioning Task This section describes how to view the progress and status of an automatic MBTS commissioning task that is being performed by the M2000 Prerequisite The automatic software commissioning already starts Context User admin can view commissioning tasks created by any user whereas other users c...

Page 43: ... state that is the commissioning is being performed the operations such as version download software upgrade and configuration file upgrade are performed For details about each status see Table 4 5 Table 4 5 Description of the commissioning statuses Status Description Start the MBTS commissioning task The commissioning is abnormal View the alarm information and then handle alarms and perform fault...

Page 44: ...lect an MBTS whose alarms you need to view and then click on the toolbar The alarm monitoring window is displayed For details about the alarm monitoring window see Interface Description MBTS Commissioning Step 3 Select the object to be viewed in the left pane of the alarm monitoring window and then view the alarm information about this object in the corresponding area in the right pane NOTE l If y...

Page 45: ...ration Auto Deployment MBTS Auto Deployment The MBTS Auto Deployment window is displayed Step 2 From MBTS List select an MBTS whose alarms you need to view and then click on the toolbar The alarm monitoring window is displayed For details about the alarm monitoring window see Interface Description MBTS Commissioning Step 3 Perform fault analysis on board alarms E1T1 alarms and antenna alarms 1 Sel...

Page 46: ... service verification Step Description Operation Performed by Users 1 The M2000 collects the performance data related to the GBTS and NodeB services If you do not restart the MBTS commissioning or confirm the completion of the commissioning after the service verification starts the M2000 collects the performance counter data related to the GBTS and NodeB services according to the shortest measurem...

Page 47: ...sults need to be viewed and then click on the toolbar The service verification window is displayed NOTE l If you select an MBTS to view the service verification results you can view the results on both the GBTS side and the NodeB side l You can also choose to view only the service verification results on the GBTS side or the NodeB side In the GBTS List or NodeB List area of the MBTS Auto Deploymen...

Page 48: ...click on the toolbar to delete the selected MBTS commissioning tasks End 4 7 Confirming the Completion of MBTS Commissioning This chapter describes how to confirm an MBTS commissioning task After the service verification of an MBTS is complete the MBTS commissioning task changes to the status for confirmation You need to manually confirm the completion of the MBTS commissioning Prerequisite The MB...

Page 49: ...e Step 1 Choose Configuration Auto Deployment MBTS Auto Deployment The MBTS Auto Deployment window is displayed Step 2 Optional In MBTS List select a commissioning task to be confirmed and then click on the toolbar to export the commissioning report In the exported file select index html to view the detailed commissioning information End 4 9 References for the MBTS Commissioning Interface This cha...

Page 50: ...the window Figure 4 2 Main window for MBTS commissioning Table 4 7 Description No Description 1 Toolbar provides operation entries for commissioning MBTSs 2 MBTS list displays all the MBTSs to be commissioned in the commissioning tasks 3 Operation result area displays the results of the operations performed during the commissioning 4 Status bar of commissioning tasks displays the total number of c...

Page 51: ...Figure 4 3 MBTS alarm monitoring window Table 4 8 Description No Description 1 Object type After selecting an object type you can view all the alarms of this object type in the alarm list on the right 2 Alarm list After selecting an object type you can view all the alarms of this object type in this list You can right click an alarm in the alarm list and then choose a menu item from the shortcut m...

Page 52: ...tion window displays the accumulated values of the performance counters related to the GBTS and NodeB It also indicates whether the accumulation values are normal Figure 4 4 MBTS service verification window 4 9 2 Parameters for the MBTS Deployment List The MBTS deployment list provides the parameters required for commissioning MBTSs After you import the MBTS deployment list into the M2000 the M200...

Page 53: ... MBTS Auto Deployment window If the CME cannot export the value of this parameter you need to edit it manually RNC ID ID of the RNC to which the NodeB belongs The value of this parameter is mandatory to be exported and the parameter cannot be edited in the MBTS Auto Deployment window RNC Name Name of the RNC to which the NodeB belongs The value of this parameter is mandatory to be exported and the...

Page 54: ...he MBTS Auto Deployment window DHCP Server IP Subnet mask The DHCP server IP subnet mask configured for the NodeB The value of this parameter is optional to be exported and the parameter cannot be edited in the MBTS Auto Deployment window AACP Server IP address The AACP server IP address configured for the NodeB If this parameter is configured the value is mandatory to be exported The value of thi...

Page 55: ...oyment window OM VLAN Priority The VLAN priority configured for the NodeB by the RNC If the VLAN is configured the value is mandatory to be exported The value of this parameter is optional to be exported and the parameter cannot be edited in the MBTS Auto Deployment window DHCP VLAN ID The value is the same as the OM VLAN ID If the VLAN is configured the value is mandatory to be exported The value...

Page 56: ...ed and the parameter cannot be edited in the MBTS Auto Deployment window NodeB FTP Path The FTP path of the NodeB The value of this parameter is optional to be exported and the parameter cannot be edited in the MBTS Auto Deployment window NodeB FTP User Name The FTP user of the NodeB The value of this parameter is optional to be exported and the parameter cannot be edited in the MBTS Auto Deployme...

Page 57: ...lue of this parameter is optional to be exported and the parameter cannot be edited in the NodeB Auto Deployment window NOTE When the GBTS side is being commissioned the Auto Deployment Type should be GBTS When the NodeB side is being commissioned theAuto Deployment Type should be NodeB When the MBTS is being commissioned the Auto Deployment Type should be MBTS 4 9 3 Parameters for MBTS Service Ve...

Page 58: ...set up for the CS conversation VP service If the value of this counter is not zero it indicates that the VP service is available PS Conversation Verification Refers to the number of times the PS conversation service is created successfully If the value of this counter is not zero it indicates that the PS conversation service is available PS Streaming Verification Refers to the number of times the ...

Page 59: ...successfully If the value of this counter is not zero it indicates that the HSUPA service is available 3900 Series Multi Mode Base Station Commissioning Guide 4 Commissioning the MBTS in GU Mode on the M2000 Issue 02 2010 07 30 Huawei Proprietary and Confidential Copyright Huawei Technologies Co Ltd 4 33 ...

Page 60: ......

Page 61: ...atically 5 3 Intervening the GBTS Transmission This section describes how to intervene the GBTS transmission By intervening the GBTS transmission you can query the real time status of the E1 T1 port to ensure that the GBTS transmission is normal and that you can proceed with the GBTS deployment 5 4 Commissioning the MBTS on the M2000 The procedure for automatically commissioning the MBTS by the M2...

Page 62: ... the Base Station The operating status of a base station can be viewed in the commissioning report 5 10 Testing the Basic Services of the eNodeB This section describes how to test the basic services of the eNodeB 5 11 Confirming the Commissioning Task After the M2000 finishes commissioning a base station automatically the commissioning task enters the to be confirmed state waiting for manual confi...

Page 63: ...gured and recorded l The M2000 is commissioned it is connected to the corresponding controller and the configuration synchronization is completed In addition the following requirements should be met l Check that the network is normal l The data configuration file and target version software package that map the mode of the base station to be commissioned are ready If a GBTS is to be commissioned t...

Page 64: ...ach mode Procedure Step 1 Create a commissioning task on the M2000 For details see 5 2 Creating a Commissioning Task Step 2 Optional If a GBTS is to be commissioned and Intervening transmission is selected when a commissioning task is created manually check the GBTS transmission state and rectify faults if any For details see 5 3 Intervening the GBTS Transmission Step 3 The M2000 automatically com...

Page 65: ...ommissioning task the M2000 automatically commissions the GBTS You can enable the M2000 to automatically commission GBTSs in batches 5 2 2 Creating a NodeB Commissioning Task This section describes how to create a NodeB commissioning task The M2000 creates a commissioning task for each NodeB based on the planned data in the imported NodeB deployment list After obtaining the software package and co...

Page 66: ...he failure causes are displayed on the Operation Information tab page For details about failure symptoms and solutions see What Should I Do When a Failure Message Is Displayed During the Import of the GBTS Deployment List Step 3 If the version of the imported GBTS software or patch is incorrect or the contact person information is incorrect double click the corresponding information record on the ...

Page 67: ... NodeB deployment list 1 Click 2 Select the NodeB deployment list to be imported TIP If you find that the ESN of a NodeB in the list is inconsistent with the actual ESN after importing the NodeB deployment list you can manually change the value of the ESN In this way the M2000 performs the commissioning task based on the correct data 3 Click Finish The NodeBs whose commissioning tasks are created ...

Page 68: ...iles on the M2000 Server After version files and configuration files are uploaded to the M2000 server they are stored in the following paths l Basic version export home sysm ftproot unKnownNodeB Software version number where version number refers to the uploaded basic version number such as V200R012C00 l Patch version export home sysm ftproot unKnownNodeB Patch version number where version number ...

Page 69: ...SN of the eNodeB the ESN reported by the eNodeB and the imported self configuration data on the M2000 are automatically bound in the case that the ESN reported by the eNodeB is consistent with the ESN in the EDS file l If the M2000 receives the message containing the eNodeB ID the imported self configuration data and the ESN reported by the eNodeB are automatically bound after the mapping between ...

Page 70: ...issioning data template to be uploaded in the local PC 6 In the Test License area click and select the eNodeB commissioning license to be uploaded in the local PC 7 In the Prepare File Data dialog box click OK to return to the eNodeB Auto Deployment tab page 8 View the file uploading progress on the Prepare File Data tab page below the eNodeB Auto Deployment tab page 9 Click in the eNodeB Auto Dep...

Page 71: ...ient is stored in the local computer The EDS file to be imported from the server is stored at a specified directory of the server 3 Click Advanced The Set Steps dialog box is displayed as shown in Figure 5 4 3900 Series Multi Mode Base Station Commissioning Guide 5 Commissioning the MBTS in GL or UL Mode on the M2000 Issue 02 2010 07 30 Huawei Proprietary and Confidential Copyright Huawei Technolo...

Page 72: ...he displayed Set Steps dialog box In this case these cleared steps are skipped in the automatic eNodeB commissioning 5 Click OK to import the EDS file The basic configuration information about each new eNodeB is displayed in the eNodeB Auto Deployment tab page Step 4 Check whether the imported self configuration data and the ESN reported by the eNodeB are automatically bound 5 Commissioning the MB...

Page 73: ...displayed in the eNodeB Auto Deployment tab page The eNodeB automatically downloads the software and data configuration file from the M2000 server Step 6 Repeat step Step 5 to manually bind all ESNs of the eNodeBs that are not automatically bound to the imported self configuration data End 5 3 Intervening the GBTS Transmission This section describes how to intervene the GBTS transmission By interv...

Page 74: ...ight click the task and then choose Intervening transmission or click on the toolbar to open the dialog box for intervening transmission 1 Figure 5 6 shows the dialog box for intervening transmission 5 Commissioning the MBTS in GL or UL Mode on the M2000 3900 Series Multi Mode Base Station Commissioning Guide 5 14 Huawei Proprietary and Confidential Copyright Huawei Technologies Co Ltd Issue 02 20...

Page 75: ... shows the dialog box for querying the E1 T1 port status 3900 Series Multi Mode Base Station Commissioning Guide 5 Commissioning the MBTS in GL or UL Mode on the M2000 Issue 02 2010 07 30 Huawei Proprietary and Confidential Copyright Huawei Technologies Co Ltd 5 15 ...

Page 76: ...y are set to 0 l Querying the E1 T1 port status does not affect the transmission 3 Figure 5 8 shows the dialog box for confirmation 5 Commissioning the MBTS in GL or UL Mode on the M2000 3900 Series Multi Mode Base Station Commissioning Guide 5 16 Huawei Proprietary and Confidential Copyright Huawei Technologies Co Ltd Issue 02 2010 07 30 ...

Page 77: ...omatically commissioning the MBTS by the M2000 varies according to the base station mode Refer to the procedure for the commissioning accordingly 5 4 1 Procedure for Automatically Commissioning the GBTS by the M2000 This section describes the process of automatic GBTS commissioning performed by the M2000 5 4 2 Procedure for Automatically Commissioning the NodeB by the M2000 The procedure for autom...

Page 78: ...ng the GBTS the M2000 automatically sets the maintenance mode of the GBTS to testing so that all alarms reported by the GBTS during the commissioning are not to be displayed on the M2000 alarm interface by default This avoids the alarms from affecting normal network monitoring You can use the monitoring function provided by the GBTS commissioning to query all alarms generated during the GBTS commi...

Page 79: ...00 automatically proceeds with the next procedure l If the OML is normal and you have set intervention on the commissioning task during the task startup the commissioning switches to the Intervening transmission status and a transmission loopback test is required l If the OML is abnormal after the OML detection is performed three times the M2000 determines that the OML is faulty In this case the c...

Page 80: ...rvice Automatically Load and Activate Switch Determined by the vercfg xml file in the software package NOTE The upgrade of the GBTS configuration data is not controlled by the M2000 After the GBTS software is upgraded and the GBTS is reset the GBTS automatically sends a request to the GBSC for loading configuration data You can set the M2000 to skip the software upgrade when starting the commissio...

Page 81: ... used to check whether the antenna system of the GBTS is faulty This test is performed according to the settings that you configure during the startup of the commissioning task The test results are saved in the commissioning report Regardless of whether the test succeeds the M2000 automatically proceeds with the next sub procedure after the test l GBTS alarm monitoring Monitors all alarms of a cer...

Page 82: ...d the commissioning switches to the Confirming completed status Otherwise the service verification persists 6 Complete the commissi oning When the commissioning switches to the Confirming completed status you need to confirm the completion of the GBTS commissioning After the commissioning is complete the M2000 automatically restores the GBTS status to normal status so that the GBTS alarms can be m...

Page 83: ...lly During the commissioning only faults need to be noted All the reported alarms are displayed on the monitoring interface of the M2000 In addition the fault diagnosis access that facilitates quick fault location is available and the associated handling suggestions are provided Verifying the services When detecting that the logical cell of the NodeB is available the M2000 starts service verificat...

Page 84: ...missioning success 5 5 4 Restarting a GBTS Commissioning Task This section describes how restart a GBTS commissioning task that is still in progress according to the actual requirement A GBTS commissioning task in progress indicates that it is not in Waiting or Completed status If you restart a commissioning task all commissioning operations that are already performed are cleared and the commissio...

Page 85: ...e the fault according to the alarm reference End 5 5 2 Performing the GBTS Fault Diagnosis This section describes how to perform the GBTS fault diagnosis When exceptions occur during GBTS commissioning you can use the automatic fault diagnosis function provided by the M2000 to check whether the GBTS that is being commissioned is faulty E1T1s and antennas support the automatic fault diagnosis funct...

Page 86: ...he shortcut menu to view the diagnosis results Step 4 Perform the following steps to handle an alarm 1 Double click the alarm to be handled and then click the link in Reason And Advice in the displayed dialog box that shows the alarm details 2 Handle the fault according to the alarm reference End 5 5 3 Viewing the GBTS Service Verification Results This section describes how to view the GBTS servic...

Page 87: ...ioning completion are displayed in the service verification window l If is displayed in each counter value you can infer that the GBTS service verification succeeds In this case you can check and confirm the completion of the commissioning For details see 5 11 1 Confirming a GBTS Commissioning Task l If is displayed in the value of a certain counter you can infer that the services related to this ...

Page 88: ...s to the performance counters of the logical cells of this NodeB and checks whether the NodeB services are normal based on the counter values At this stage you can check whether each cell of the NodeB has passed the service verification and view the accumulated value of each counter 5 6 4 Performing a NodeB Task Again or Deleting the Task When a NodeB commissioning task is running you can perform ...

Page 89: ...ndled No operation needs to be performed The commissioning is being performed normally You need to confirm whether to complete the commissioning The commissioning is complete without errors End 5 6 2 Viewing NodeB Alarms After the NodeB software is upgraded automatically during the NodeB commissioning you can view the alarms of this NodeB and the relevant alarms of the RNC managing this NodeB thro...

Page 90: ...hen choose Diagnose Report from the shortcut menu to view the diagnosis result Step 4 Perform the following steps to handle an alarm 1 Double click the alarm to be handled 2 In the displayed dialog box that shows the alarm details click the link in Reason And Advice 3 Rectify the fault based on the alarm reference End 5 6 3 Viewing Service Verification Results After a NodeB commissioning task is a...

Page 91: ... the verification l If all the performance counters of a cell have passed the verification it indicates that this cell has passed the verification l If all the logical cells of a NodeB have passed the verification it indicates that this NodeB has passed the verification 5 6 4 Performing a NodeB Task Again or Deleting the Task When a NodeB commissioning task is running you can perform this task aga...

Page 92: ...ning task can be restarted as required 5 7 1 Viewing the eNodeB Commissioning Progress After the eNodeB commissioning task is created the user can view the task progress and related information to handle problems during the eNodeB commissioning Prerequisite The eNodeB commissioning task is created Context Table 5 4 describes the automatic eNodeB commissioning process Table 5 4 Automatic eNodeB com...

Page 93: ...plete After the testing and verification is complete the user decides whether to end the eNodeB commissioning based on the actual situations When the eNodeB commissioning is complete the M2000 restores the eNodeB to the normal state Thus the eNodeB alarms can be reported as usual Procedure Step 1 On the M2000 client choose Configuration Auto Deployment eNodeB Auto Deployment The eNodeB Auto Deploy...

Page 94: ...ioning Task During the automatic eNodeB commissioning on the M2000 a commissioning task can be deleted and a terminated commissioning task can be restarted as required Prerequisite The eNodeB commissioning task is created Procedure Step 1 On the M2000 client choose Configuration Auto Deployment eNodeB Auto Deployment The eNodeB Auto Deployment tab page is displayed Step 2 Right click one or multip...

Page 95: ...GBTS commissioning report records the task information about a commissioned GBTS and the information about the commissioning process When a commissioning task is still in progress or is complete you can obtain and analyze the commissioning report to learn the commissioning details to view the exceptions that occur during the commissioning or to determine whether to complete the commissioning Prere...

Page 96: ...ssioning report you want to view Step 3 Click Step 4 Specify a local save path and then click Confirm You can customize the file name of a commissioning report If you do not specify the file name the M2000 uses user name report exporting time as the file name by default For example admin 2009_10_16_15_37_21 End 5 8 3 Obtaining an eNodeB Commissioning Report The eNodeB commissioning report includes...

Page 97: ...Waiting for Acknowledgement you can infer that the service verification is complete The obtained commissioning report can help you determine the running status of the GBTS l The commissioning report records all the commissioning information generated from the start of the commissioning task to the moment the report is generated Therefore the commissioning report that records the information about ...

Page 98: ...odeB commissioning task Procedure Step 1 View the NodeB commissioning report to infer the running status of the NodeB Step 2 View the alarm list and clear the active alarms according to the NodeB Alarm Reference NOTE There are two methods of viewing the alarm list l Export the alarm list when the commission report is exported Then the commissioning report includes the alarm list l Open the alarm l...

Page 99: ...ettings conflict alarm check Check the consistency of inter system parameter settings for the BBU board Inter system cabinet configuration conflict alarm check Check the consistency of inter system configurations for the cabinet Inter system monitoring device parameter settings conflict alarm check Check the consistency of inter system parameter settings for the monitoring device Inter system boar...

Page 100: ...peer MME GE FE port status check Check the parameter settings of the Ethernet port E1 T1 port status check Check the parameter settings of the E1 T1 port Remote maintenance channel status check Check the data configuration on all the remote maintenance channels of the eNodeB SCTP link status check Check the parameter settings of the SCTP link IP Path status check Check the parameter settings relat...

Page 101: ... services is available l The WWW server for testing the basic services is available Procedure l Test the web page browsing service Testing Method Access the WWW server and browse the web pages through a UE Perform the test 20 times Expectation Success rate 95 Web browsing is normal l Test the file uploading service Testing Method Access the FTP server and upload files through a UE Perform the test...

Page 102: ...ning 5 11 1 Confirming a GBTS Commissioning Task This section describes how to confirm the completion of GBTS commissioning After the GBTS service verification is complete the commissioning task switches to Confirming completed status and you need to manually confirm the completion Context If some alarms are still not cleared during the commissioning it is recommended that you not confirm the comp...

Page 103: ... to confirm that the commissioning is complete After the commissioning is complete the M2000 performs the following operations l Stop monitoring the alarms on the NodeB and its RNC l Stop subscribing to the service verification performance counters of the NodeB End 5 11 3 Confirming an eNodeB Commissioning Task After the eNodeB health check is complete the status of the commissioning task changes ...

Page 104: ...ance counters that are monitored in the service verification procedure during GBTS commissioning 5 12 1 Interface Description GBTS Commissioning This section describes the layout of the GBTS Auto Deployment window for commissioning GBTSs and provides the information about each element displayed in the window This section mainly describes the following tab pages in the GBTS Auto Deployment window l...

Page 105: ...perations that you perform in the GBTS Auto Deployment window Monitor Tab Page Figure 5 11 shows the Monitor tab page The Monitor tab page displays all alarms of a certain GBTS and all relevant alarm of the GBSC managing the GBTS which are generated during the commissioning If the fault cause cannot be located according to the alarm information you can select one object or alarm to perform the fau...

Page 106: ...e M2000 creates a fault diagnosis task and displays the diagnosis progress After the fault diagnosis is complete you can obtain the fault diagnosis report to view fault location information NOTE E1T1s and antennas support the fault diagnosis Service Verification Tab Page Figure 5 12 shows the Service Verification tab page The Service Verification tab page displays the accumulation values of the pe...

Page 107: ...cedure that a commissioning task is in Description Details of the current commissioning procedure that a commissioning task is in BTS Software Version Version of the target GBTS software BTS Hot Patch Version Version of the target hot patch User Name Name of the user who creates a commissioning task Contact Contact person of the GBTS to be commissioned and his or her contact information 5 12 3 Par...

Page 108: ...tion about each GBTS and the current status start time and end time of each GBTS commissioning task You can click a GBTS name to navigate to the pages of details of this GBTS For the examples of the pages of details see Figure 5 14 and Figure 5 15 3 Filtering conditions of the GBTS list If the information about multiple GBTSs is contained in the commissioning report you can type the name of a GBTS...

Page 109: ...splays the basic information about a commissioned GBTS 2 This area displays the details of a commissioned GBTS If the service verification starts and you have manually triggered the automatic fault diagnosis the information shown in Figure 5 15 is also displayed in this area 3900 Series Multi Mode Base Station Commissioning Guide 5 Commissioning the MBTS in GL or UL Mode on the M2000 Issue 02 2010...

Page 110: ...the parameters of the performance counters that are monitored in the service verification procedure during GBTS commissioning Parameter Description Parameter Description SDCCH Verification If the value is not 0 you can infer that the counter meets the requirement TCH Verification If the value is not 0 you can infer that the counter meets the requirement 5 Commissioning the MBTS in GL or UL Mode on...

Page 111: ...ndow during NodeB commissioning You can learn about the components of this window 5 13 2 Parameters of the NodeB Deployment List The NodeB deployment list records the parameter information required for NodeB commissioning After the NodeB deployment list is imported to the M2000 the M2000 can automatically commission the NodeBs in the NodeB deployment list 5 13 1 Interface Description NodeB Commiss...

Page 112: ...ed by all users You can also filter the commissioning tasks created by a user by specifying User Name 3 Status bar of commissioning tasks The status bar displays the total number of commissioning tasks and number of commissioning tasks in each status 4 Operation result area This area displays the results of operations performed in the NodeB Auto Deployment window NodeB Auto Deployment window Monit...

Page 113: ...eated in this area After the diagnosis task is complete you can right click it and then choose Diagnose Report from the shortcut menu to view the diagnosis result NOTE The objects that support automatic diagnosis are boards transmission physical ports and antennas NodeB Auto Deployment window Validate tab page The Validate tab page displays the accumulated values of the performance counters monito...

Page 114: ...e NodeB is finished by using the CME exporting the NodeB deployment list from the CME is recommended For the detailed operations see the Exporting the Deployment List and Configuration Files of Physical NodeBs section in the online help The principles of exporting parameters using the CME are listed as follows l The planned information must be exported from the CME l The unplanned information cann...

Page 115: ...planned This parameter can be optionally exported from the CME It is configurable in the NodeB Auto Deployment window NodeB TRANS IP address OM IP address of the NodeB configured at the RNC This parameter must be exported from the CME It is not configurable in the NodeB Auto Deployment window NodeB TRANS IP Subnet mask OM IP subnet mask of the NodeB configured at the RNC This parameter must be exp...

Page 116: ...urable in the NodeB Auto Deployment window Next Hop IP Subnet mask to DHCP Server IP subnet mask of the next hop from the NodeB to the DHCP server it must be exported from the CME if it is configured This parameter can be optionally exported from the CME It is not configurable in the NodeB Auto Deployment window Next Hop IP address to AACP Server IP address of the next hop from the NodeB to the AA...

Page 117: ...t configurable in the NodeB Auto Deployment window NodeB Type Type of the NodeB to be commissioned This parameter must be exported from the CME It is not configurable in the NodeB Auto Deployment window NodeB BaseLine Software Version Baseline version of the target NodeB it must be exported from the CME if the target version is planned This parameter can be optionally exported from the CME It is c...

Page 118: ...can be optionally exported from the CME It is not configurable in the NodeB Auto Deployment window NodeB FTP Password Password for login to the FTP server of the NodeB This parameter can be optionally exported from the CME It is not configurable in the NodeB Auto Deployment window Contact Information about the contact person in the field This parameter can be optionally exported from the CME It is...

Page 119: ...or local commissioning The preparation of the USB disk for local commissioning varies according to the base station mode Therefore you must prepare the USB disk based on the mode of the base station to be commissioned 6 3 Upgrading Software and Configuring Data by Using the USB Disk You can locally upgrade software and configure data of a base station by using the USB disk on the base station side...

Page 120: ...missioned and the system works properly The negotiation data of the MBTS to be commissioned is configured and recorded l The M2000 is commissioned it is connected to the corresponding controller and the configuration synchronization is completed The USB disk for local commissioning should be ready for this commissioning mode For details see 6 2 Preparing the USB Disk for Local Commissioning NOTE l...

Page 121: ...oning the MBTS using USB and M2000 3900 Series Multi Mode Base Station Commissioning Guide 6 Commissioning the MBTS by Using USB and M2000 Issue 02 2010 07 30 Huawei Proprietary and Confidential Copyright Huawei Technologies Co Ltd 6 3 ...

Page 122: ... upgraded 2 The base station automatically upgrades the software and data For details see 6 3 Upgrading Software and Configuring Data by Using the USB Disk 3 Check whether the MBTS hardware is normal according to the LED status For details see 6 4 Checking the Status of the LEDs and Rectifying the Faults 4 Remove the USB disk before leaving the site l Remote end of the MBTS NOTE When the MBTS is c...

Page 123: ...e the USB disk based on the mode of the base station to be commissioned Context NOTE Files required for both modes must be saved to the USB disk when base stations supporting two modes are deployed 6 2 1 Arranging the USB Disk for Local GBTS Commissioning The USB disk should be ready before it is used for local GBTS commissioning 6 2 2 Arranging the USB Disk for Local NodeB Commissioning The USB d...

Page 124: ...nd wait for 3 seconds If the LED on the USB disk blinked once it indicates that the USB disk is functional If the USB disk fails the preceding test change the USB disk Step 3 Obtain the software package for the upgrade 1 Three days before the upgrade visit the website http support huawei com and click Software to download the software package 2 Decompress BTS3000V100R012C00SPCXXX_VER zip to obtain...

Page 125: ...M Precfg ini Data configuration file BTS3900 GSM SiteName TranCfg ini End 6 2 2 Arranging the USB Disk for Local NodeB Commissioning The USB disk should be ready before it is used for local NodeB commissioning Procedure Step 1 Prepare the USB disk with a LED The requirements are as follows when there is no read or write operation on the USB disk the LED on the USB disk is ON when there is any read...

Page 126: ...of PKCS 10 which is generated by the operator s root CA certificate or the operator s child CA certificate that is used for the certification of eNodeB security GW and M2000 l The CR CRL database is deployed on the server of the DeMilitarized Zone DMZ of the operator and supports FTP Thus the files on the CR CRL database can be downloaded in FTP mode l The USB storage device is ready l The eNodeB ...

Page 127: ...certificate required by the eNodeB That is save the operator s cross certificate operator s root CA certificate and operator s CRL file optional to the USB storage device NOTE You can save either or both of the cross certificate and operator s root CA certificate to the USB storage device Step 3 Obtain the eNodeB software package and data configuration file NOTE The eNodeB software package is read...

Page 128: ...et Switches Operation Manual is ready and can be downloaded from http support huawei com l The infoX AAA Commissioning Guide is ready and can be downloaded from http support huawei com l If the IEEE 802 1x authentication is adopted the operator should use the authentication access equipment that supports 802 1x authentication and the corresponding AAA server that supports Extensible Authentication...

Page 129: ...cate domain should be configured according to the authentication mode specified in the ike proposal The local id type item must be name the remote name item must be s segw the ike proposal item should be configured according to previous configurations and the ike version item can be V1 or V2 ipsec proposal The encapsulation mode item must be tunnel the transform item must be esp the esp authentica...

Page 130: ...es Ethernet Switches Operation Manual Step 4 Configure the eNodeB CA certificate for the AAA server The AAA server may vary with different operators The descriptions here take the infoX AAA as an example For details see the infoX AAA Commissioning Guide 1 Upload the CA certificate of a terminal user to the iscc2 config secert directory of infoX AAA 2 Change the file names of the user certificate a...

Page 131: ...S automatically activates the software and then resets Context l Software upgrade by using a USB disk is supported from GSM BTS3000 V100R009C00SPC058 l Transmission configuration by using a USB disk is supported from GSM BTS3000 V100R009SPC072 l Within 3 minutes after GBTS started GBTS cannot perform the USB upgrade or configuration During the 3 minute period GBTS is trying to connect with BSC and...

Page 132: ...ftware and data configuration file from the USB disk Blinking Blinking ON for 0 125s and OFF for 0 125s About 10s The GTMU activates the software ON Blinking ON for 0 125s and OFF for 0 125s About 3 to 4 minutes The GTMU resets ON first OFF for a while and then ON ON first OFF for a while and then ON About 2 minutes The GTMU is running properly ON Blinking on for 1s and off for 1s The BTS configur...

Page 133: ...ta configuration file the NodeB checks the consistency between the active software version and configuration data and the software version and configuration data in the USB disk If they are inconsistent the software and configuration upgrade is automatically started If they are consistent the upgrade is not performed Note the following situations when the software and configurations are upgraded f...

Page 134: ... of the RUN LED on the WMPT in this process see Table 6 5 Table 6 5 LEDs on the USB disk and the WMPT Status of the LED on the USB Disk State of the RUN LED on the WMPT Duration When the USB disk is plugged into the corresponding port on the WMPT the WMPT automatically detects the USB disk ON Blinking on for 1s and off for 1s About 1s to 2s The WMPT downloads the software and data configuration fi...

Page 135: ... ready for use The required files are saved in the USB storage device For details see 6 2 3 Arranging the USB Disk for Local eNodeB Commissioning CAUTION If one USB storage device is used repeatedly the target eNodeB software and data configuration file in the USB storage device should be updated before the USB storage device is used for an eNodeB deployment When you save the eNodeB software and d...

Page 136: ...ation file and the eNodeB software version The eNodeB performs the following activities If the eNodeB software is upgraded successfully but is not compatible with the data configuration file or if the download and activation of data configuration fail the eNodeB uses the minimum configuration of the target version When the active eNodeB software is consistent with the target software version softw...

Page 137: ...nd then perform the commissioning through the USB storage device If the download or activation still fails perform the local eNodeB commissioning on the LMT Table 6 6 lists the status of LEDs when the software and data configuration file are downloaded and activated through the USB storage device Table 6 6 LED status Status of the LED on the USB Storage Device Status of the RUN LED on the LMPT Aut...

Page 138: ...the software and data configuration Then the eNodeB resets Step 4 When the download and activation are successful unplug the USB storage device and proceed with checking the status of the LEDs and rectifying the faults End Postrequisite CAUTION The eNodeB software package contains the LMT software To reduce the eNodeB deployment duration some of the files of the LMT software are automatically down...

Page 139: ... 1s CPRI LED on the GTMU WBBP LBBP MRFU RRU3908 ON green VSWR LED on the MRFU RRU3908 OFF NOTE If the transmission is unavailable in the local USB commissioning scenario the GBTS automatically resets at intervals of 10 minutes During this period you need not check the status of the ALM LEDs on the MRFU RRU3908 working in the GSM system GTMU and UBRI Check the status of co cabinet MRFU RRU3908 modu...

Page 140: ...ulty l Check whether the base station is powered on If not power on the base station l Reinstall the board to check whether the fault is rectified If the fault persists replace the board 2 Check the ALM LEDs on the GTMU WMPT LMPT WBBP LBBP UERI UTRP MRFU RRU3908 If the ALM LED Is It Indicates That Then OFF The GTMU WMPT LMPT WBBP LBBP UERI UTRP MRFU RRU3908 are not faulty Go to Step 1 3 ON The GTM...

Page 141: ...8 to check whether the fault is rectified l If the GPS antenna system is configured check whether it is properly connected 3 Check the STATE LED on the FAN If the STATE LED Is It Indicates That Then Blinking green The board works properly Go to Step 1 4 Blinking red The board is faulty Reinstall the board to check whether the fault is rectified If the fault persists replace the board 4 Check the C...

Page 142: ... ON for 1s OFF for 1s The RRU or LRFU on the CPRI link reports the VSWR alarm Handle the alarm according to the suggestions For details see Alarm Reference Blinking red ON for 0 25s OFF for 0 25s The RRU or LRFU on the CPRI link is faulty Handle the alarm according to the suggestions For details see Alarm Reference Step 2 Check the ALM LEDs on the PMU AFMU EMUA If the ALM LED Is It Indicates That ...

Page 143: ... The system with the download control right upgrades the co modulated RRU3908 MRFU and the USCU software during software upgrade Prerequisite l M2000 server terminal is working properly and M2000 is logged on l The connection between BTS and M2000 is working properly If the BTS is GSM BTS the connection between the BSC and M2000 needs to work properly Procedure Step 1 Run the corresponding MML com...

Page 144: ......

Page 145: ...d rectify faults if any in time At the M2000 you can check the MBTS operating status 7 2 Running the GBTS SMT To run the GBTS site maintenance terminal SMT you need to first set the IP address of the SMT client connect the base station and the SMT and then log in to the SMT 7 3 Configuring the Basic Data of the GBTS This section describes how to configure the basic data of the GBTS such as the GBT...

Page 146: ...odeB software and data configuration file on the LMT The upgraded eNodeB software and data configuration file take effect after the eNodeB is automatically reset The process for upgrading the eNodeB software and data configuration file takes about 45 minutes 7 9 Downloading the eNodeB License By downloading the license to the eNodeB on the LMT you are authorized to use the eNodeB software 7 10 Dat...

Page 147: ...nd commissioned and the system works properly The negotiation data of the MBTS to be commissioned is configured and recorded l The M2000 is commissioned it is connected to the corresponding controller and the configuration synchronization is completed In addition the following requirements must be met l A portable computer used for local commissioning is ready l The portable computer is installed ...

Page 148: ...cal maintenance terminal and M2000 7 Commissioning the MBTS by Using Local Maintenance Terminal and M2000 3900 Series Multi Mode Base Station Commissioning Guide 7 4 Huawei Proprietary and Confidential Copyright Huawei Technologies Co Ltd Issue 02 2010 07 30 ...

Page 149: ... eNodeB LMT For details see 7 9 Downloading the eNodeB License 9 Check the connection status of the base station and rectify faults if any For details see 6 4 Checking the Status of the LEDs and Rectifying the Faults l Remote end of the MBTS NOTE When the MBTS is commissioned remotely on the M2000 commission the base station of a mode and then commission the base station of the other mode The two ...

Page 150: ... is established you can operate and maintain the base station on the SMT 7 2 3 Logging In to the SMT This section describes how to log in to the base station through the SMT 7 2 1 Setting the IP address of the SMT Client This section describes how to set the IP address of the SMT client The IP address of the SMT client is on the same network segment as the IP address 192 168 0 72 255 255 255 0 of ...

Page 151: ... XP operating system choose Start Run at the lower left corner of the computer s desktop In the Run dialog box enter cmd and click OK The MS DOS command prompt window is displayed Step 3 Run ping 192 168 0 72 to verify the network connection between the SMT client and the base station NOTE 192 168 0 15 is the IP address of the base station l If the information similar to that in the following exam...

Page 152: ... the SMT client and the base station is established a dialog box shown in Figure 7 2 is displayed The SMT is successfully started l If the SMT client cannot communicate with the base station the Communication failed dialog box is displayed as shown in Figure 7 3 Go to Step 2 Figure 7 2 SMT login interface 7 Commissioning the MBTS by Using Local Maintenance Terminal and M2000 3900 Series Multi Mode...

Page 153: ...nance Terminal System window click User and select User Login Enter User Name Omc by default and User Password omc by default End 7 3 Configuring the Basic Data of the GBTS This section describes how to configure the basic data of the GBTS such as the GBTS boards and logical objects You must configure the basic data of the GBTS before performing the local commissioning on the GBTS side 3900 Series...

Page 154: ...u must obtain the site management rights after logging into the base station at the local end Prerequisite You have logged in to the base station through the SMT Procedure Step 1 In the Site Maintenance Terminal System window select Site and double click Site Management Right The Site Management Right dialog box is displayed Step 2 Click Obtain The Warning Message dialog box is displayed as shown ...

Page 155: ...ed click Close End 7 3 2 Configuring Base Station Boards This section describes how to configure RF units and other boards of the base station on the SMT Context Table 7 1 shows the types of configurable RF units on the BTS Table 7 1 Configurable RF units on the BTS BTS Type Configurable TRX Types BTS3900 GSM DRFU GRFU and MRFU BTS3900A GSM DRFU GRFU and MRFU BTS3900L GSM DRFU GRFU and MRFU DBS390...

Page 156: ...m the configuration l The RF units of the DBS3900 must be configured in the Topology Configuration window Procedure Step 1 Click Board in the navigation tree The Board Configuration and Board Management windows are displayed Step 2 Double click Board Configuration The Board Configuration window is displayed as shown in Figure 7 7 Figure 7 7 Board Configuration window 7 Commissioning the MBTS by Us...

Page 157: ...layed Topology Configuration window as shown in Figure 7 8 Figure 7 8 Board Configuration window Step 4 Choose RXU from the shortcut menu as shown in Figure 7 8 The Deploy RXU dialog box is displayed Set Card Type to MRFU as shown in Figure 7 9 3900 Series Multi Mode Base Station Commissioning Guide 7 Commissioning the MBTS by Using Local Maintenance Terminal and M2000 Issue 02 2010 07 30 Huawei P...

Page 158: ... displayed as shown in Figure 7 10 Figure 7 10 Topology Configuration window Step 7 Click Close The Board Configuration window is displayed Right click an idle slot and then choose the board to be configured from the shortcut menu 7 Commissioning the MBTS by Using Local Maintenance Terminal and M2000 3900 Series Multi Mode Base Station Commissioning Guide 7 14 Huawei Proprietary and Confidential C...

Page 159: ...n and Board Management windows are displayed 2 Double click Board Management The Board Management window is displayed 3 In the Board Management window right click PMU and then choose Parameter Management from the shortcut menu The Parameter Management dialog box is displayed 4 On the Parameter Management dialog box click Parameter Set Select APM30 or other options under APMU Type according to the ...

Page 160: ...uration data Context NOTE The following part describes the configuration and binding of carriers based on one MRRU configured with two carriers Procedure Step 1 Add a cell Click Site0 and double click Site Configuration in the Function area The Site Configuration dialog box is displayed as shown in Figure 7 13 7 Commissioning the MBTS by Using Local Maintenance Terminal and M2000 3900 Series Multi...

Page 161: ...pecify Object No and Object Name In the Object Operation area Cell0 is added as shown in Figure 7 14 3900 Series Multi Mode Base Station Commissioning Guide 7 Commissioning the MBTS by Using Local Maintenance Terminal and M2000 Issue 02 2010 07 30 Huawei Proprietary and Confidential Copyright Huawei Technologies Co Ltd 7 17 ...

Page 162: ...ed in the Boardtype drop down list box Set the board type to MRRU as shown in Figure 7 15 7 Commissioning the MBTS by Using Local Maintenance Terminal and M2000 3900 Series Multi Mode Base Station Commissioning Guide 7 18 Huawei Proprietary and Confidential Copyright Huawei Technologies Co Ltd Issue 02 2010 07 30 ...

Page 163: ...arrier is bound to the number 0 pass of the TRX whose Board No is 0 as shown in Figure 7 16 Pass 0 is also called carrier A The pass number of the TRX depends on the carrier number 3900 Series Multi Mode Base Station Commissioning Guide 7 Commissioning the MBTS by Using Local Maintenance Terminal and M2000 Issue 02 2010 07 30 Huawei Proprietary and Confidential Copyright Huawei Technologies Co Ltd...

Page 164: ...No to 0 and Pass No to 1 as shown in Figure 7 17 The MRRU 0 is configured with two carriers 7 Commissioning the MBTS by Using Local Maintenance Terminal and M2000 3900 Series Multi Mode Base Station Commissioning Guide 7 20 Huawei Proprietary and Confidential Copyright Huawei Technologies Co Ltd Issue 02 2010 07 30 ...

Page 165: ...alog box 5 3900 Series Multi Mode Base Station Commissioning Guide 7 Commissioning the MBTS by Using Local Maintenance Terminal and M2000 Issue 02 2010 07 30 Huawei Proprietary and Confidential Copyright Huawei Technologies Co Ltd 7 21 ...

Page 166: ...displayed as shown in Figure 7 18 Figure 7 18 User Error dialog box Step 6 Click Site0 The Set button is available Click Set Configuring cell succeeded is available as shown in Figure 7 19 7 Commissioning the MBTS by Using Local Maintenance Terminal and M2000 3900 Series Multi Mode Base Station Commissioning Guide 7 22 Huawei Proprietary and Confidential Copyright Huawei Technologies Co Ltd Issue ...

Page 167: ...ne as shown in Figure 7 20 The data is configured but not activated To activate the data go to Step 8 3900 Series Multi Mode Base Station Commissioning Guide 7 Commissioning the MBTS by Using Local Maintenance Terminal and M2000 Issue 02 2010 07 30 Huawei Proprietary and Confidential Copyright Huawei Technologies Co Ltd 7 23 ...

Page 168: ...8 If the operation succeeds go to Step 9 If the operation fails go to 8 2 2 Check whether data configuration conflict exists If there is configuration conflict modify the configuration If the configuration is incorrect turn to GBTS engineers for help 7 Commissioning the MBTS by Using Local Maintenance Terminal and M2000 3900 Series Multi Mode Base Station Commissioning Guide 7 24 Huawei Proprietar...

Page 169: ...ee Step 8 Figure 7 22 Cell Opstart dialog box Step 10 The site configuration takes effect Step 11 Make the attributes of other TRXs take effect Choose BT0 BT Opstart OK The BT Opstart dialog box is displayed as shown in Figure 7 23 3900 Series Multi Mode Base Station Commissioning Guide 7 Commissioning the MBTS by Using Local Maintenance Terminal and M2000 Issue 02 2010 07 30 Huawei Proprietary an...

Page 170: ...se Repeat Step 12 to set the frequencies of other carriers The RC Attributes Management dialog box is displayed as shown in Figure 7 24 Figure 7 24 RC Attributes Management dialog box Step 13 Choose RC0 RC Opstart OK The RC Opstart dialog box is displayed as shown in Figure 7 25 7 Commissioning the MBTS by Using Local Maintenance Terminal and M2000 3900 Series Multi Mode Base Station Commissioning...

Page 171: ...tep 14 SFP Port Logic Inconsistency Alarm is not displayed The transmission is unavailable and the LAPD Alarm persists Therefore the GTMU state is Active Fault As shown in Figure 7 26 3900 Series Multi Mode Base Station Commissioning Guide 7 Commissioning the MBTS by Using Local Maintenance Terminal and M2000 Issue 02 2010 07 30 Huawei Proprietary and Confidential Copyright Huawei Technologies Co ...

Page 172: ...d UTRP if the UTRP is installed and how to check the connections of the E1 cable and E1 surge protection transfer cable to ensure that the BBU properly communicates with the BSC 7 Commissioning the MBTS by Using Local Maintenance Terminal and M2000 3900 Series Multi Mode Base Station Commissioning Guide 7 28 Huawei Proprietary and Confidential Copyright Huawei Technologies Co Ltd Issue 02 2010 07 ...

Page 173: ...F The E1 T1 link is normal End this task The LED is on or on for 0 125s and off for 0 125s The E1 T1 link is faulty Go to Step 4 NOTE You need to check the status of only the LIU LED corresponding to the E1 T1 link in use The LIU LEDs corresponding to the unused E1 T1 links are on l For the BBUs that are not connected in cascading mode if the LIU LED for the E1 T1 link is off the communication bet...

Page 174: ...side 1 For a pair of E1s T1s connecting the BTS and BSC through the DDF port A is connected to port C and port B is connected to port D In the loopback test disconnect port A from port C and port B from port D and then connect port A to port B as shown in Figure 7 27 In this way the TX end and RX end of the E1 T1 cable are connected and the physical loopback is formed on the BTS side Figure 7 27 P...

Page 175: ...Windows XP system 7 5 2 Connecting the LMT Client and the Base Station This section describes how to set the route from the LMT client to the NodeB in remote maintenance mode If you do not set the route in remote maintenance mode you fail to log in to the NodeB through the LMT client 7 5 3 Logging In to the LMT This section describes how to log in to the NodeB LMT 7 5 1 Setting the IP address of t...

Page 176: ...Network Connections dialog box is displayed Right click Local Area Connection Step 4 Choose Properties from the shortcut menu The Local Area Connection Properties dialog box is displayed Step 5 Select Internet Protocol TCP IP Step 6 Click Properties The Internet Protocol TCP IP Properties dialog box is displayed Step 7 Select Use the following IP address Step 8 Set the IP address subnet mask and d...

Page 177: ...te maintenance mode If you do not set the route in remote maintenance mode you fail to log in to the NodeB through the LMT client Procedure Step 1 On the LMT client choose Start Run and then run the cmd command The command window is displayed Step 2 Run the ROUTE ADD Networkaddress MASK netmask gatewayaddress command in the command window to add a route from the PC to the gateway Then set Networka...

Page 178: ...rmal Procedure Step 1 Choose Start All Programs HUAWEI Local Maintenance Terminal If the Local Maintenance Terminal is started choose System Logout or click The User Login dialog box is displayed as shown in Figure 7 29 Figure 7 29 User Login dialog box Table 7 4 describes the fields in the User Login dialog box Table 7 4 Fields in the User Login dialog box Field Description User Name Type the use...

Page 179: ...n in Figure 7 30 you can infer that the language version of the NodeB does not match that of the LMT In this case switch the NodeB language so that you can log in to the NodeB through the LMT Figure 7 30 Switching the language CAUTION The NodeB is reset after you switch the NodeB language Step 6 Click Yes to switch the NodeB language NOTE If you click No a dialog box is displayed indicating The la...

Page 180: ...Step 3 Choose Software Management Software Update The Software Update dialog box is displayed Step 4 Select Upgrade NodeB Software in the dialog box Click Next The Update NodeB Software dialog box is displayed Step 5 Select Download Data Configuration File Download NodeB Software Package Download by Configuration Effective Data Configuration File and Activate NodeB Software in sequence and set the...

Page 181: ...stall the latest version l If you cannot log on to the LMT after JRE upgrade restart the browser and log on to the LMT again Context There are two types of LMT users local user and emergency EMS user l Local user refer to the accounts including the default account admin that are separately managed by the LMT The users can operate and maintain the eNodeB when the LMT is disconnected from the M2000 ...

Page 182: ...g shortcuts under Browse l If the colors of the LMT window cannot be displayed perform the following settings Choose Tools Internet Options from the menu of the IE On the General tab page click Accessibility Then clear Ignore colors specified on Web pages under Formatting l In the case of an LMT version upgrade or rollback you need to clear the buffer and cookies of the IE Procedure l Logging in t...

Page 183: ...P1 1 through proxy connections under HTTP 1 1 settings 2 Click Go The Local Maintenance Terminal dialog box is displayed as shown in Figure 7 31 3 Type the user name and the password in the Name Password and Verify Code text boxes Set User Type to EMS NOTE The EMS user names and passwords are authorized by the M2000 server If the verify code is indistinct click Change the verify code to change the...

Page 184: ... configuration file and eNodeB software in sequence Step 2 On the LMT click the Software Management button The Software Management tab page is displayed Step 3 In the navigation tree double click Download and Activate Software The Download and Activate Software interface is displayed as shown in Figure 7 32 Figure 7 32 Download and Activate Software interface Step 4 Select the tasks to be performe...

Page 185: ...g the license to the eNodeB on the LMT you are authorized to use the eNodeB software Prerequisite l The LMT communicates properly with the eNodeB l The license is already obtained Procedure Step 1 Run the INS LICENSE command to download and activate the license on the eNodeB End 7 10 Data Sheet for Commissioning This chapter provides the data sheet that is used to record the process and result of ...

Page 186: ...commissioning are available The commissioning requirements are met Commis sioning Phase Local eNodeB Commiss ioning Through the USB Storage Device The GBTS is upgraded The GBTS hardware is functional SMT LMT Remote Commiss ioning You have logged in to the GBTS through the SMT The GBTS board and logical objects are available The active software version is correct The transmission between the BBU an...

Page 187: ...rect The hardware installation and the data configuration are consistent with each other No alarm related to the GBTS is reported The CS service test is successful The PS service test is successful The environment monitoring alarm can be reported normally The VSWR is correct Record the value of the VSWR The output power of the TRX is normal Record the value of the output power per carrier The ante...

Page 188: ...sult Successful Failed Commissioning Item Conclusion Handling Exceptional Case Commissioning Preparation Phase Faults in the NodeB hardware installation are rectified Yes No Transmission links between the NodeB and RNC are ready Yes No Negotiation data of the NodeB to be commissioned is added to the RNC Yes No Commission ing Phase Local Com missio ning throug h USB The NodeB is upgraded Yes No The...

Page 189: ...commissioned Yes No The NodeB environment alarms are commissioned Yes No Problem Description Impact Unsolved Problems After Commission ing Component P N Faulty Board Record 7 10 3 Data Sheet for eNodeB Commissioning This section provides the data sheet that is used to record the process and results of the eNodeB commissioning The Data Sheet for Commissioning used at different sites may be differen...

Page 190: ...S GW Yes No Software and data configuration file are ready Yes No Remote Commiss ioning on the M2000 Local end of the eNod eB The information regarding the eNodeB such as name ID and ESN is reported Yes No The eNodeB is powered on Yes No Remo te end of the eNod eB The ESN is bound Yes No The software and data configuration file are loaded through the M2000 Yes No The software is upgraded to the ta...

Page 191: ...ct Yes No The running status of the eNodeB is normal Yes No The test result of the basic services is correct Yes No Remo te end of the eNod eB The ESN is bound Yes No The OM channel is established Yes No Local eNodeB Commiss ioning on the LMT Local end of the eNod eB The ESN is reported Yes No The software and data configuration file are loaded through the LMT Yes No The software is upgraded to th...

Page 192: ... eNod eB The ESN is bound Yes No The OM channel is established Yes No Problem Description Impact Unsolved Problems After Commiss ioning Component P N Faulty Board Record 7 Commissioning the MBTS by Using Local Maintenance Terminal and M2000 3900 Series Multi Mode Base Station Commissioning Guide 7 48 Huawei Proprietary and Confidential Copyright Huawei Technologies Co Ltd Issue 02 2010 07 30 ...

Page 193: ...ected to the BSC the local OM of the GBTS can be implemented through this port on the SMT None Table 8 2 Communication ports on the NodeB Prot ocol A Side A Side Port Num ber RX B Side B Side Port Number TX Service Authority Managem ent TCP NodeB 6000 LMT 1024 6553 5 For the LMT to deliver the maintenance command to the NodeB User name password TCP NodeB 6001 LMT 1024 6553 5 For the NodeB to repor...

Page 194: ...ode local maintenance FE port only User name password TCP NodeB 23 Comm issioni ng consol e 1024 6553 5 For telnet debug mode local maintenance FE port only User name password UDP NodeB 67 68 M200 0 server or any other DHCP server 67 68 For DHCP services None UDP M2000 server or any other DHCP server 67 68 NodeB 67 68 For DHCP services None UDP M2000 server RNC BAM or any other SNTP server 123 Nod...

Page 195: ...rot ocol A Side A Side Port Number RX B Side B Side Port Number TX Service Author ity Manag ement TCP eNod eB 6000 LMT 1024 65535 For the LMT to deliver the maintenance command and for the UE to respond Format MML User name passwor d TCP eNod eB 6001 LMT 1024 65535 For the NE to report alarm Format MML None TCP eNod eB 6006 LMT 1024 65535 For maintenance Format BIN None TCP eNod eB 6007 M2000 serv...

Page 196: ... eB 67 68 M2000 server or any other DHCP server 67 68 For DHCP services None UDP M200 0 server or any other DHC P server 67 68 eNodeB 67 68 For DHCP services None UDP M200 0 server or any other DHC P server 123 eNodeB 1024 65535 For synchronizing the NTP time None TCP M200 0 server or any other FTP server 21 eNodeB 1024 65535 For FTP control User name passwor d 8 Communication Port for Multi Mode ...

Reviews: