background image

Associated hardware procedures

This chapter describes the hardware operations carried out prior to and after installing or removing a hardware option, or
performing system maintenance or troubleshooting.

Before performing these hardware operations, review and observe system warnings and cautions.

Installing the power supply

Procedure

1. Connect the power cord to the power connector at the rear of the system.

2. Power up the system.

Powering up the system

If the system is connected to a power source, it powers up automatically. It needs to be powered up only after a manual
shutdown or after autopower off.

To power up the system, press the Power On/Standby button.

Powering down the system

Before powering down the system for any upgrade or maintenance procedures, you must back up critical system data and
programs.

Use one of the following methods to power down the system:

• Press and release the Power On/Standby button.

This method initiates a controlled shutdown of applications and the OS before the system enters standby mode.

• Press and hold the Power On/Standby button for more than 4 seconds to force the system to power down.

This method forces the system to power down without properly exiting applications and the OS. If an application stops
responding, you can use this method to force a shutdown.

Before proceeding, you must ensure that the system is in standby mode by verifying that the system power LED is off.

Mounting the system

The following kits are available to mount your system:

Wall mounting kit

Rail mounting kit

Before mounting the system, make sure that you do the following:

• Read the site requirements for the system:

System installation site requirements on page 18

• Read the safety and compliance information on the HPE website:

http://www.hpe.com/support/safety-compliance-enterpriseproducts

Associated hardware procedures

47

Summary of Contents for Edgeline EL300

Page 1: ... September 2019 Edition 3 Abstract This document is for the person who installs administers and troubleshoots servers and storage systems Hewlett Packard Enterprise assumes you are qualified in the servicing of computer equipment and trained in recognizing hazards in products with hazardous energy levels ...

Page 2: ...r copying Consistent with FAR 12 211 and 12 212 Commercial Computer Software Computer Software Documentation and Technical Data for Commercial Items are licensed to the U S Government under vendor s standard commercial license Links to third party websites take you outside the Hewlett Packard Enterprise website Hewlett Packard Enterprise has no control over and is not responsible for information o...

Page 3: ...llation site requirements 18 Space and airflow requirements 18 Power requirements 19 Temperature requirements 19 Hardware options installation 20 Power adapter option 20 Installing the power adapter option 20 SD card option kit 20 Installing the SD card option 20 SFF to M 2 adapter option 22 Installing the SFF to M 2 adapter option 22 M 2 device option 25 Installing an M 2 device 25 Wireless netwo...

Page 4: ...first time 59 Connecting to the iSM web interface using the WiFi Access Point 60 Connecting to the iSM web interface using Ethernet 60 Connecting to the iSM CLI in a serial session 61 iSM web interface 61 Configuring the Internet Explorer JavaScript setting 62 Logging in to the iSM web interface 62 About the iSM web interface controls 63 Quick task Configure the network connection and install an o...

Page 5: ...cense 76 Registering the product 76 Troubleshooting 77 HPE Edgeline Troubleshooting Guide 77 Warranty and regulatory information 78 Warranty information 78 Regulatory information 78 Notices for Eurasian Economic Union 78 Turkey RoHS material content declaration 79 Ukraine RoHS material content declaration 79 Federal Communications Commission notice for Class B equipment 79 European Union CE compli...

Page 6: ...Optional service 88 Accessing Hewlett Packard Enterprise Support 88 Accessing updates 89 Customer self repair 89 Acronyms and abbreviations 90 Documentation feedback 91 6 ...

Page 7: ...e optional software can be used to manage the HPE EL300 system after completing the initial HPE EL300 and HPE iSM setup After setup each HPE EL300 is available to the optional management software About HPE Edgeline Infrastructure Manager The Edgeline Infrastructure Manager EIM supports discovery monitoring and management of Edgeline Converged Edge Systems It is delivered as a Virtual Machine image...

Page 8: ...that perform similar functions Using Workload Orchestrator to centralize management of the OT Link Platform on numerous Edgeline Converged Edge Systems cuts the time and effort required to deploy update and manage the software stack running on those systems HPE Edgeline Workload Orchestrator provides centralized dashboards that depict the operational status across all OT Link systems and consolida...

Page 9: ...rk kits and antennas HPE EL Network WiFi card WiFi antenna HPE EL Network LTE card LTE antenna 5 Mount the system Wall mounting DIN rail mounting Base only bracket kit Standard bracket kit 6 Prepare to configure the system a Verify OS support b Gather OS installation media and necessary keys c Verify network connectivity d Plan for network address 7 Connect to the iSM and configure the system usin...

Page 10: ...as QR codes on all systems Scan one to access important information on your mobile device Not interested is scanning the QR code Click the following link to access the mobile pages for quick setup maintenance and troubleshooting information http www hpe com qref el300 10 Setup and configuration ...

Page 11: ...verged Edge System with no daughter card HPE Edgeline EL300 Converged Edge System with 4 ports 1GBE Ethernet with TSN support daughter card HPE Edgeline EL300 Converged Edge System with 2 ports RS232 422 485 opto isolated daughter card HPE Edgeline EL300 Converged Edge System with 2 ports CAN Bus A B FD 2 0 opto isolated daughter card HPE Edgeline EL300 Converged Edge System with 8 Bits Configurab...

Page 12: ...GBE Ethernet with TSN support daughter card is installed Rear panel components when 2 ports RS232 422 485 opto Isolated daughter card is installed Rear panel components when 2 ports CAN Bus A B FD 2 0 opto isolated daughter card is installed Rear panel components when 8 Bits Configurable GPIO daughter card is installed No daughter card configuration Item Description 1 Mic 2 Line out 3 Line in 4 HD...

Page 13: ...with TSN support daughter card configuration Item Description 1 Mic 2 Line out 3 Line in 4 HDMI port 5 Display port 6 USB 3 0 ports 7 USB 2 0 ports 8 TSN daughter card ports 9 Power connectors 10 Power on button 11 iSM Reset 12 CPU Reset 13 SD card slot 14 Serial port Table Continued Components and site requirements 13 ...

Page 14: ...iguration Item Description 1 Mic 2 Line out 3 Line in 4 HDMI port 5 Display port 6 USB 3 0 ports 7 USB 2 0 ports 8 Serial daughter card ports 9 Power connectors 10 Power on button 11 iSM Reset 12 CPU Reset 13 SD card slot 14 Serial port 15 RJ 45 iSM LAN management port 16 RJ 45 ports 14 Components and site requirements ...

Page 15: ...n 1 Mic 2 Line out 3 Line in 4 HDMI port 5 Display port 6 USB 3 0 ports 7 USB 2 0 ports 8 CANBUS card ports 9 Power connectors 10 Power on button 11 iSM Reset 12 CPU Reset 13 SD card slot 14 Serial port 15 RJ 45 iSM LAN management port 16 RJ 45 ports Components and site requirements 15 ...

Page 16: ...ine out 3 Line in 4 HDMI port 5 Display port 6 USB 3 0 ports 7 USB 2 0 ports 8 DIO daughter card port 9 Power connectors 10 Power on button 11 iSM Reset 12 CPU Reset 13 SD card slot 14 Serial port 15 RJ 45 iSM LAN management port 16 RJ 45 ports 16 Components and site requirements ...

Page 17: ...d Critical condition 3 UID Solid blue Activated Flashing blue Active firmware update in progress 4 SSD11 Solid green Drive activity Off No drive activity 5 SSD22 Solid green Drive activity Off No drive activity 6 Wireless White Wireless network enabled 1 This LED indicates activity for M 2 SATA SSD that is installed under the top cover Components and site requirements 17 ...

Page 18: ...mends that you install or position the system in a location with restricted access where the access is secured and controlled The users technicians handling the system should be informed about the restrictions applied and precautions to be taken Space and airflow requirements To allow for servicing and adequate airflow observe the following space and airflow requirements Leave a minimum 20 cm 7 9 ...

Page 19: ...otection of Electronic Computer Data Processing Equipment For electrical power ratings on options see the product rating label or the user documentation supplied with that option Temperature requirements To ensure continued safe and reliable equipment operation install or position the system in a well ventilated climate controlled environment Configuration Temperature EL 300 System 0 C to 70 C 158...

Page 20: ...supports the HPE EL300 80W 12 VDC power adapter option This option is supported only when the system is installed with the HPE EL300 12V DC Transfer board Installing the power adapter option Procedure Connect the power adapter to the EL300 system The installation is complete SD card option kit The system supports installation of an 8 GB SD card Installing the SD card option Prerequisites Before yo...

Page 21: ...e serial port connector 3 Insert the SD card in the slot Make sure to insert the card with the label side downwards 4 If removed install the serial port connector 5 Reinstall the SD port cover Hardware options installation 21 ...

Page 22: ...ure that you have the following items available T 15 security screwdriver Phillips screwdriver M 2 SSD module Hex nut screwdriver Procedure 1 Power down the system 2 Remove all power a Disconnect the power cord from the power source b Disconnect the power cord from the system 3 Depending on the surface the system is installed on do one of the following a Dismount the system from wall b Dismount th...

Page 23: ...the standoff Hex nut screw securing the SATA cable and I2C cable Retain the standoff Hex nut for installing the M 2 adapter board 7 Remove the SFF drive cage 8 Install the M 2 adapter board on the drive cage Hardware options installation 23 ...

Page 24: ...the SATA cable and the I2C cable on the drive cage Ensure that the I2C clip holder installed on the connector is in upward direction 10 Install the stand off nut on the drive cage 24 Hardware options installation ...

Page 25: ...ete M 2 device option The first M 2 device is preinstalled in the HPE Edgeline EL300 Converged Edge System Additional M 2 devices can be installed using the SFF to M 2 adapter Installing an M 2 device NOTE The M 2 SSD installed on the drive cage does not have any activity LED associated Prerequisites Before you perform this procedure make sure that you have the following items available M 2 device...

Page 26: ... from wall b Dismount the system from the rails 4 Remove the security cover 5 Remove the drive cage cover 6 Install the M 2 adapter on the drive cage 7 Install the M 2 device on the drive cage and secure it with the standoff screw a Insert the M 2 device into the slot b Press down the M 2 device in horizontal direction c Install the M 2 mounting screw to secure the M 2 device 8 Install the drive c...

Page 27: ...before installing 10 Install the security cover 11 Do one of the following Mount the system on wall Mount the system on rails 12 Connect the power cord to the system 13 Connect the power cord to the power source 14 Power up the system The installation is complete Hardware options installation 27 ...

Page 28: ...line EL300 Converged Edge System This option kit comprises of WiFi network card and WiFi antennas Installing the WiFi card Prerequisites Before you perform this procedure make sure that you have the following items available T 15 security screwdriver Phillips screwdriver Procedure 1 Power down the system 2 Remove all power a Disconnect the power cord from the power source b Disconnect the power co...

Page 29: ...ting the antenna cables 10 Install the heat spreader 11 Install the drive cage cover 12 Install the security cover 13 Install the preferred bracket option 14 Install the WiFi antennas 15 Do one of the following Mount the system on wall Mount the system on rails Wireless network kit and antenna installation 29 ...

Page 30: ...es Before you perform this procedure Make sure that the bracket option is installed on the HPE Edgeline EL300 system Make sure that you have the T 15 security screwdriver available Procedure 1 Locate the correct antenna slot 2 Install the antenna The antenna shown in the image might look different from the antenna for your system 30 Wireless network kit and antenna installation ...

Page 31: ...te management of the EL300 system This option enables 4G LTE network connectivity for the HPE Edgeline EL300 system The HPE Edgeline Wireless WAN 4G LTE EM7565 Wide Temperature option kit comprises of LTE network card and LTE antennas Installing the LTE network card Prerequisites Before you perform this procedure make sure that you have the following items available T 15 security screwdriver Phill...

Page 32: ...stalled on do one of the following a Dismount the system from wall b Dismount the system from the rails 4 Remove the security cover 5 Remove the drive cage cover 6 Remove the heat spreader 7 Install the LTE card 8 Connect the LTE antenna cables CAUTION The connectors on the card are fragile take utmost care when connecting the antenna cables 32 Wireless network kit and antenna installation ...

Page 33: ... system on rails 17 Connect the power cord to the system 18 Connect the power cord to the power source 19 Power up the system The installation is complete Installing the SIM card IMPORTANT The SIM cards are supplied by your preferred mobile broadband provider and cannot be ordered from HPE The SIM cards must be nano SIM form factor The EL300 system supports installation of two SIM cards The first ...

Page 34: ...cedure Make sure that the LTE network card is installed Procedure 1 Install the SIM card in primary slot location 2 Optional Install a secondary SIM card 3 Install the heat spreader Make sure to remove the gap pad liner from the heat spreader 34 Wireless network kit and antenna installation ...

Page 35: ...rce 10 Power up the system Installing the LTE antennas Prerequisites Before you perform this procedure Make sure that the bracket option is installed on the HPE Edgeline EL300 system Make sure that you have the T 15 security screwdriver available Procedure 1 Locate the correct antenna slot 2 Install the antenna The antenna shown in the image might look different from the antenna for your system Wi...

Page 36: ...3 Install the antenna holders 36 Wireless network kit and antenna installation ...

Page 37: ...e of the bracket options can be installed on the HPE Edgeline EL300 Converged Edge System Base only bracket option kit The base only bracket option offers installation support for the EL300 base system only This bracket option does not support expansion unit installation The following components are available with the option kit Base bracket panels 2 T 15 screws Cable management bracket Reusable c...

Page 38: ...s installed when additional expansion board support is required The standard bracket option can be installed to support the following hardware configurations HPE Edgeline EL300 base unit HPE Edgeline EL300 base unit 1 expansion unit HPE Edgeline EL300 base unit 2 expansion units The following components are available with the option kit Standard bracket panels 2 T 15 screws Bracket handles Cable m...

Page 39: ... security screwdriver available Procedure 1 Attach the bracket handles to the bracket panels 2 Place the system on a flat level surface 3 Attach the brackets on the system a Place the brackets on the side of the system b Secure the brackets with T 15 screws 4 Install the cable management bracket System mount options 39 ...

Page 40: ...ne 5 6 inch drill bit Procedure 1 For hollow wall Install the wall mounting base panel a Identify the location for installing the mounting panel b Place the wall mount base panel on the selected position on the wall and mark the screw locations NOTE Align minimum one column out of the three middle panels to the internal wall stud c Drill pilot holes on the marked screw locations and install the wa...

Page 41: ...position of all the screw mounting holes c Drill pilot holes on the marked screw locations and install the wall anchors d Install the top two screws halfway and hang the wall mount e Secure the base panel by tightening all the screws 3 Install the system on the wall mount base panel a Align the system mounted on brackets with the spools of the base panel b Secure the system with screws System moun...

Page 42: ...you perform this procedure Make sure that the preferred bracket option is installed on the HPE Edgeline EL300 system Make sure that you have the T 15 security screwdriver available Procedure 1 Attach the DIN rail clips to the DIN mounting panel a Align the rail clips to the DIN panel b Install the screws For two rail option loosely install the clips for the lower rail Single rail 42 System mount o...

Page 43: ... Install the mounting panel on the rails a Slide up the base of the rail clip b Install the bottom screw When installing two rails the distance between the rails should be 178 8mm Single rail System mount options 43 ...

Page 44: ... Dual rails 3 Secure the rails installed by tightening the screws on the rail clips Single rail 44 System mount options ...

Page 45: ... Dual rails 4 Install the system on the rail mounted panel a Align the system mounted on brackets with the spools of the base panel b Secure the system with screws System mount options 45 ...

Page 46: ...The installation is complete 46 System mount options ...

Page 47: ...e of the following methods to power down the system Press and release the Power On Standby button This method initiates a controlled shutdown of applications and the OS before the system enters standby mode Press and hold the Power On Standby button for more than 4 seconds to force the system to power down This method forces the system to power down without properly exiting applications and the OS...

Page 48: ...screwdriver available Procedure 1 Power down the system 2 Disconnect all cables connected to the system 3 Remove the system from the wall mounting panel Dismount the system from a rail mount panel Prerequisites Before you perform this procedure make sure that you have the T 15 security screwdriver available Procedure 1 Power down the system 2 Disconnect all cables connected to the system 3 Remove ...

Page 49: ...m the system 3 Depending on the surface the system is installed on do one of the following a Dismount the system from wall b Dismount the system from the rails 4 Place the system on a flat level surface 5 Locate the correct antenna slot 6 Remove the antenna The antenna shown in the image may be different from your system Associated hardware procedures 49 ...

Page 50: ... power cord from the power source b Disconnect the power cord from the system 3 Depending on the surface the system is installed on do one of the following a Dismount the system from wall b Dismount the system from the rails 4 Remove all the cables routed through the cable management bracket 5 Place the system on a flat level surface 6 Remove the cable management arm 50 Associated hardware procedu...

Page 51: ...alled bracket panels Base only bracket Standard bracket Removing the security cover Prerequisites Before you perform this procedure make sure that you have the following items available Associated hardware procedures 51 ...

Page 52: ...nt the system from the rails 4 Place the server on a flat level surface with the top cover facing down 5 Remove the antennas on the system 6 Remove the installed bracket option 7 Remove the security cover a Remove the screws securing the security cover b Detach the pins of the security cover from the system and then remove the security cover Installing the security cover Prerequisites Before you p...

Page 53: ... on the system b Install the screws on the security cover and secure it to the system 2 Install the preferred bracket option 3 Install the antennas 4 Do one of the following Mount the system on wall Mount the system on rails 5 Connect the power cord to the system Associated hardware procedures 53 ...

Page 54: ...connect the power cord from the power source b Disconnect the power cord from the system 3 Depending on the surface the system is installed on do one of the following a Dismount the system from wall b Dismount the system from the rails 4 Place the system on a flat level surface with the top cover facing down 5 Remove the antennas on the system 6 Remove the installed bracket option 7 Remove the sec...

Page 55: ...make sure that you have the Phillips screwdriver available Procedure 1 Install the drive cage cover using the Phillips screwdriver 2 Install the security cover 3 Install the preferred bracket option 4 Install the antennas 5 Do one of the following Associated hardware procedures 55 ...

Page 56: ...er Phillips screwdriver Procedure 1 Power down the system 2 Remove all power a Disconnect the power cord from the power source b Disconnect the power cord from the system 3 Depending on the surface the system is installed on do one of the following a Dismount the system from wall b Dismount the system from the rails 4 Remove the antennas on the system 5 Remove the installed bracket option 6 Remove...

Page 57: ...re make sure that you have the following items available T 15 security screwdriver Phillips screwdriver Procedure 1 Install the heat spreader 2 Install the drive cage cover 3 Install the security cover 4 Install the preferred bracket option Associated hardware procedures 57 ...

Page 58: ...nas 6 Do one of the following Mount the system on wall Mount the system on rails 7 Connect the power cord to the system 8 Connect the power cord to the power source 9 Power up the system 58 Associated hardware procedures ...

Page 59: ...portable media the drive must have enough space to store a complete OS image with enough space left over for OS reporting files HPE recommends that portable media have a minimum of 32GB of space before storing installation images NOTE An iSM Advanced license is required to use virtual media 3 Verify network connectivity Ensure that the network connection is active if needed 4 Verify Internet conne...

Page 60: ...m the chassis tag WiFi enabled laptop or mobile device Procedure 1 Search for available WiFi connections on your device The WiFi SSID starts with iSM following by a dash and up to 12 letters and numbers For example iSM 813d2g5144fd 2 Select the WiFi connection and then enter the password 3 Open a browser window to 192 168 0 1 The login page for iSM is displayed Log in with the credentials printed ...

Page 61: ...OTE If your system was shipped with an HPE Edgeline Dual Serial Port daughter card do not use serial daughter ports for initial configuration of the system 2 Start a terminal SSH session using a standard SSH tool like PuTTY Use the following settings Specification Value Baud rate 115200 Data bits 8 Parity None Stop bit 1 8 N1 Flow control XON XOFF 3 Log in by entering the default credentials shown...

Page 62: ...tart Internet Explorer 2 Select Tools Internet options 3 Click Security 4 Click Custom level 5 In the Scripting section set Active scripting to Enable 6 Click OK 7 Refresh your browser window Logging in to the iSM web interface Procedure 1 Enter https iSM host name or IP address When you access the iSM web interface you must use HTTPS HTTP exchanged over an SSL encrypted session The iSM login page...

Page 63: ...ne help for the iSM web interface Confirmation status and error messages Some pages of the iSM web interface require you to scroll down to see all the options available or to reach an Apply button Confirmation status and error messages display at the top of the page so remember to scroll back up to the top of the page after clicking Apply Quick task Configure the network connection and install an ...

Page 64: ...ession or changing the host boot order An iSM Advanced license is required to use virtual media and the remote console For detailed information about the iSM Advanced license see the HPE Edgeline Converged Edge System Licensing Guide at http www hpe com support EL Converged Edge System Licensing en 4 Update the host boot order in BIOS iSM GUI or by using the iSM CLI so that the next reboot of the ...

Page 65: ...angeable MAC address of the iSM network interface FQDN The fully qualified domain name of the system IPv6 Default Gateway When IPv6 is enabled the gateway is the default IP address iSM uses to access the network When not enabled this entry is blank Speed Mbps The speed of the wired network measured in megabits per second WiFi Network The SSID of the WiFi network if connected Cellular Network The b...

Page 66: ...less network Strength A measure of how powerful the signal strength of the connection is to the WiFi network Status The status of the WiFi connection connected or not connected Security The type of security in use on the WiFi connection LTE Summary details Enabled Indicates whether LTE is enabled True or False APN The access point name which may or may not include an operator identifier Status Ind...

Page 67: ...ess correctly and that no namespace conflicts exist Flush the DNS name if you make any namespace changes Configuring IPv4 settings Prerequisites iSM Admin privilege Procedure 1 Click Wired and Wireless Network in the navigation tree and then click the IPV4 tab 2 Configure the DHCPv4 Configuration setting 3 Configure the IPv4 Address Configuration settings 4 Configure the DNS Configuration settings...

Page 68: ...re used Tertiary DNS Server This value is supplied automatically when DHCP is enabled If you are using a static IP address no name servers are used Configuring IPv6 settings Prerequisites iSM Admin privilege Procedure 1 Click Wired and Wireless Network in the navigation tree 2 Click the IPv6 tab 3 Configure the Global IPv6 Configuration setting 4 Configure the IPv6 Configuration settings 5 Configu...

Page 69: ...p www hpe com info EIL IPv6StaticAddress When assigning static IPv6 addresses enter the main IP address here IPv6StaticAddress PrefixLength When assigning static IPv6 addresses enter the prefix length here IPv6DefaultGateway When assigning static IPv6 addresses enter the default IPv6 gateway here DNS Configuration When assigning static IPv6 addresses enter the Primary Secondary and Tertiary DNS Se...

Page 70: ... Enabling or disabling the access point may cause iSM network connections to become unresponsive for 10 seconds Configuring LTE settings iSM can connect to an LTE network to provide cellular data access to the user interface NOTE When disabling and then re enabling the APN there is a delay before the settings are restored and appear on the page Wait until the settings reappear before continuing Pr...

Page 71: ...ay change when the host system is rebooted 6 Using a terminal program connect to the COM port found in the previous step in a serial session Set the serial session configuration to 115200n8 7 In the terminal session enter the command ati1 and record the results to get the settings relevant to completing the LTE configuration in iSM The settings you will need include APN IMEI IMSI IP Connecting the...

Page 72: ...base image are listed Firmware details The Firmware page displays the following information for each listed firmware type Firmware name The category name of the firmware Firmware version The currently installed version number of the firmware Updating firmware While firmware can be updated using components uploaded to the iSM Repository you can also update firmware directly Prerequisites iSM Admin ...

Page 73: ...l 3 Click Yes install now The update begins immediately Boot order The System Boot Order feature enables you to set the system boot device priority Changes made to the boot order might require a system reset An error occurs if you try to change the system boot order when the system is in POST You cannot modify the boot order during POST If this error occurs wait for POST to finish and then try aga...

Page 74: ...te a graceful shutdown after a momentary press or to ignore this event Hewlett Packard Enterprise recommends using system commands to complete a graceful operating system shutdown before you attempt to shut down by using the Virtual Power button Press and Hold The same as pressing the physical power button for 5 seconds and then releasing it The system is powered off as a result of this operation ...

Page 75: ...h and Event logs on the Logs page Enabling the Trusted Platform Module as TPM 2 0 Procedure 1 During the system startup sequence press the F9 key to access System Utilities 2 From the System Utilities screen select System Configuration BIOS Platform Configuration RBSU Server Security Trusted Platform Module options 3 Verify the following Current TPM Type is set to TPM 2 0 Current TPM State is set ...

Page 76: ...dge System Licensing en Why register your iSM Advanced license Registration activates a unique HPE Support Agreement ID SAID Your SAID identifies you and the products you use You can obtain quicker HPE Support Services by using your SAID Obtain access to the HPE Support Center Obtain access to software updates in the HPE Update Center Receive important product alerts Track your HPE product license...

Page 77: ...uide provides procedures for resolving common problems and comprehensive courses of action for fault isolation and identification issue resolution and software maintenance on the Edgeline System The document is available in the Hewlett Packard Enterprise Information Library Troubleshooting 77 ...

Page 78: ...customers with information about the chemical substances in our products as needed to comply with legal requirements such as REACH Regulation EC No 1907 2006 of the European Parliament and the Council A chemical information report for this product can be found at www hpe com info reach For Hewlett Packard Enterprise product environmental and safety information and compliance data including RoHS an...

Page 79: ...owing conditions This device may not cause harmful interference This device must accept any interference received including interference that may cause undesired operation This equipment has been tested and found to comply with the limits for a Class B digital device pursuant to part 15 of the FCC Rules These limits are designed to provide reasonable protection against harmful interference in a re...

Page 80: ...mpliance Table 1 Intel AC 9260 module Operating frequency band Maximum radio frequency RF power transmitted dBm EIRP Bluetooth 9 5 BLE 5 5 WLAN 2 4 GHz 20 WLAN 5 GHz 23 Table 2 EM7565 module Operating frequency band Maximum radio frequency RF power transmitted dBm conducted LTE bands Bands 1 2 3 4 5 8 9 12 13 18 19 20 26 28 66 24 Bands 7 41 42 43 23 8 Band 30 23 UMTS bands Band 1 IMT 2100 12 2 kbp...

Page 81: ... regulations the radio transmitters in this device may only operate using an antenna of a type and maximum or lesser gain approved for the transmitter by Industry Canada To reduce potential radio interference to other users the antenna type and its gain should be so chosen that the equivalent isotropically radiated power e i r p is not more than what is necessary for successful communication WARNI...

Page 82: ...préjudiciable aux systèmes de satellites mobiles utilisant les mêmes canaux 2 Le gain maximal d antenne permis pour les dispositifs utilisant les bandes 5 250 MHz 5 350 MHz et 5 470 5 725 MHz doit se conformer à la limite de p i r e 3 Le gain maximal d antenne permis pour les dispositifs utilisant la bande 5 725 MHz 5 825 MHz doit se conformer à la limite de p i r e spécifiée pour l exploitation p...

Page 83: ...is not supplied with this equipment please contact your supplier For all other cases please use an input cable that matches the DC voltage and current rating which complies with the safety standard of your particular country region Warranty and regulatory information 83 ...

Page 84: ...ds to prevent electrostatic discharge Several methods are used for grounding Use one or more of the following methods when handling or installing electrostatic sensitive parts Use a wrist strap connected by a ground cord to a grounded workstation or computer chassis Wrist straps are flexible straps with a minimum of 1 megohm 10 percent resistance in the ground cords To provide proper ground wear t...

Page 85: ... 40 F to 185 F Relative humidity noncondensing 95 relative humidity at 40 C 1 All temperature ratings shown are for sea level An altitude derating of 1 0 C per 304 8 m 1 8 F per 1000 ft to 3048 m 10 000 ft is applicable No direct sunlight allowed Maximum rate of change is 20 C per hour 36 F per hour Mechanical specifications Specification Value Length 23 2 cm 9 13 in Depth 10 4 cm 4 09 in Width 20...

Page 86: ... 1uA when in use system on top cover closed Maximum Battery Life Cycle 550 mAh 10 9 uA 50458 hours 550 mAh 6 1 uA 90163 hours Maximum Battery Life Cycle under Storage Mode 50458 hours 365 x 24 5 76 years Battery in Storage Mode System Powered Off all day RTC battery is in use Maximum Battery Life Cycle under Operation Mode 90163 hours 365 x 24 10 29 years Battery in Operation Mode System Power On ...

Page 87: ...lett Packard Enterprise Information Library www hpe com info EIL Hewlett Packard Enterprise Edgeline Documentation www hpe com info edgeline docs Hewlett Packard Enterprise Edgeline Information www hpe com info edgeline Websites 87 ...

Page 88: ...s and get you to technical experts when there is one 6 Hour Call to Repair1 4 Hour 24x7 Next Business Day Deployment service for both hardware and software Hewlett Packard Enterprise Education Services Help train your IT staff 1The time commitment for this repair service might vary depending on the site s geographical region For more service information available in your site contact your local He...

Page 89: ...he Hewlett Packard Enterprise Support Center More Information on Access to Support Materials page www hpe com support AccessToSupportMaterials IMPORTANT Access to some updates might require product entitlement when accessed through the Hewlett Packard Enterprise Support Center You must have an HPE Passport set up with relevant entitlements Customer self repair Hewlett Packard Enterprise customer s...

Page 90: ...ory express PCIe Peripheral Component Interconnect Express PXE preboot execution environment SD secure digital SATA serial ATA SFF small form factor SIM subscriber identification module SSD solid state device UID unit identification WiFi wireless fidelity WLAN wireless local area network WWAN wireless wide area network 90 Acronyms and abbreviations ...

Page 91: ...ggestions or comments to Documentation Feedback docsfeedback hpe com When submitting your feedback include the document title part number edition and publication date located on the front cover of the document For online help content include the product name product version help edition and publication date located on the legal notices page Documentation feedback 91 ...

Reviews: