Quick Installation Guide
HM-600N/HM-700N/HM-800N AP040240 REV1.2
2
/
2
2. Insert the AC cable from Part 3 to Part 2, and complete the wiring for the L, N and Ground
inside Part 1 AC port accordingly:
*Note: L: Brown wire N: Blue wire G: Yellow/Green wire
Please use 12 AWG cable as AC end cable
3. Plug the AC port Part 2 into Part 1 once complete the wiring, and screw the Part 3 on
and complete the AC extension cable:
B) Connect the AC end cable to the AC male connector of the first microinverter to complete
the circuit.
C) Connect the other side of the AC end cable to the distribution box, and wire it to the local
grid network.
Step 4. Create an Installation Map
A) Peel the removable serial number label from each microinverter (The position of the label
is shown as below.)
B) Affix the serial number label to the respective location on the installation map.
Step 5. Connect PV Modules
A) Mount the PV modules above the microinverter.
B)
Connect the PV modules’ DC cables to the DC input side of the microinverter.
Step 6. Energize the System
A) Turn on the AC breaker of the branch circuit.
B) Turn on the main AC breaker of the house. Your system will start to generate power after
about two-minute wait time.
Step 7. Set Up the Monitoring System
Refer to the DTU User Manual or DTU Quick Install Guide, and Quick Installation Guide for
HMP Online Registration to install the DTU and set up your monitoring system.
Product information is subject to change without notice. (Please download reference manuals
at www.hoymiles.com.)