Procedure:
1. Remove the top two screw connections (1, Fig. 02) on the boiler foot (1a, Fig. 02).
2. Remove front wooden crossbeam.
3. Using a winch (2, Fig. 02) raise the front of the boiler.
4. Take out the side beam (3, Fig. 02) at the front to the side (see Fig. 02).
5. Push in the front feet and screw on.
6. Using a winch (2, Fig. 02) raise the rear of the boiler.
7. Take out the side beam (3, Fig. 02) at the rear to the side (see Fig. 02).
8. Push in the rear feet and screw on.
9. Remove the step board protection (4, Fig. 02). Remove the securing pins (5, Fig. 02) and carefully fold the step
board down. In types (850-1150) fold up 2nd and 3rd step board or remove ladder.
3
1a
1
2
Types (850-1150) (H (1000))
with six feet
5
4
Types (575-1150) (H (720, 1000))
Suspension possibilities for crane
1b
Fig. 02
Adjustable foot height is set after installation
of the neutralisation unit.
9
4 217 215 / 00
INSTALLATION
Summary of Contents for UltraGas 1000