5.3 Installation
Caution
Risk of injury caused by falling load and improper handling. During
installation:
– Wear protective equipment (safety helmet, safety goggles, safety shoes).
– Do not stand under suspended loads.
– Use a forklift with sufficient load-bearing capacity.
Preparation
■
Make sure that the following items are on hand for the assembly:
– Installation platform
– Drill Ø 16 mm
–
Socket wrench, width 17
– Socket or open-end wrench, width 13
Installation
■
Install the retaining bracket:
– Cut 1 opening at the top and at the bottom of the casing with the drill (Ø
16 mm, see
7
– Insert the assembly bush
6
into the top opening.
– Position the retaining bracket
3
over the openings.
– Insert M10 screws
4
into the bushes.
– Turn the retaining bracket to the desired position in relation to the unit.
– Tighten the screws to secure the position.
– Place the plugs
5
on the retaining bracket.
■
Install both mounting angles
2
with the M8 screws onto the retaining bracket.
–
3 different inclination angles can be used.
■
Install the unit on the wall or on the ceiling (on-site fastening material).
– Use the packaging box as a drilling template.
± 60°
Fig. 5: Angle of rotation, left/right 60°
■
1
M8 screw with spring washer, nut and
washers (2 sets)
■
2
Mounting angles (x2)
■
3
Retaining bracket
■
4
M10 screw (x2)
■
5
Plug (x2)
■
6
Assembly bush
■
7
Opening
Fig. 6: Unit installation
1
2
3
4 5 6
11
TopVent
®
TV
Design, installation and operation
Transport and installation
4 216 284-en-05