Installing the below-roof unit
■
Apply sealing compound to the roof frame.
■
Release the cable fastening on the below-roof unit frame and carefully insert
the cable into the unit.
Caution
Danger of damaging the unit: Dropping the cable may damage the
heating or cooling coil. Put the cable down carefully.
■
Screw in the transport eyes into the connection module frame and attach the
lifting gear.
–
Heed the minimum length of the lifting ropes (see Fig. 23).
■
Transport the below-roof unit to the roof frame using a helicopter or crane.
■
Turn the below-roof unit to the desired position.
■
Hang the below-roof unit into the roof frame from above.
■
Check the sealing strip on the connection module flange. Improve the seal if
necessary.
■
Remove the transport eyes.
Fig. 24: Applying sealing compound to the roof frame
Fig. 25: Hanging the below-roof unit
min. 2 m
Fig. 23: Minimum length of the lifting ropes
RoofVent
®
RH | RC | RHC | R
Transport and installation
Art.No. 4 214 745-en-04 / Page 35