Commissioning and decommissioning
Subject to modifications
53 of 131
5.1.
Commissioning
5.1.1. Safety
Operation, set-up and installation of the CHP plant are only allowed to be carried out by
trained and, if necessary, authorised specialist personnel in compliance with all assembly
and installation regulations.
Perfect function and operational reliability of the CHP plant depend to a large extent on
correct installation on site. Any warranty is excluded for the consequences of faulty
assembly of the CHP plant by third parties.
The following safety instructions must be observed when installing the CHP plant. This
prevents life-threatening injuries, damage to the CHP plant and other damage to property.
The installation work, such as assembly and installation of the CHP plant, is only
allowed to be carried out by qualified persons in compliance with the safety
instructions.
Ensure that a permissible floor load is guaranteed at the installation site of the
CHP plant. The total weight of the CHP plant must be taken into account.
Before installation work starts, the CHP plant must be inspected for transport
damage.
The completeness of all delivered CHP plant parts is to be checked.
Ensure that only authorised persons are present in the working area and that no
other persons are endangered by the installation work.
Proper handling of hazardous substances must be ensured.
All plant connections (cables, hoses and pipelines) must be laid in such a way that
they do not cause any tripping hazards.
When laying cables, hoses or pipelines, the prescribed bending radii in
accordance with DIN must be observed.
The specified tightening torques of the bolted connections must be observed.
The handling instructions (e.g. earthing, ...) for electrostatically sensitive components
must be observed.
Wear personal protective equipment.