ASSEMBLY
HOLZMANN MASCHINEN GmbH www.holzmann-maschinen.at
25
SB510V
N O T E
Check the running direction of the motor immediately after making the electrical
connection! The drill/drill chuck must turn clockwise (viewing direction from above)
when the machine is switched on. If necessary, you may need to adjust/
switch two of the three phases (L1/L2 or L1/L3)!
Voltage
Extension
Strand Cross-Section
220 V – 240 V
50 -60 Hz
<27 m
1,5 mm
2
<44 m
2,5 mm
2
<70 m
4,0 mm
2
<105 m
6,0 mm
2
Please note that work on electrical components or equipment may only be carried out by a
qualified electrician or under the direction and supervision of a qualified electrician!
The following also applies in connection with the electrical connection:
The connector plug, if present, must not be tampered with.
The earthing conductor is yellow-green.
The power supply mains must be fused with 16 Ampere.
Check whether the mains voltage corresponds to the requirements of the machine.
After the electrical connection, check the correct running direction (3 phases).
Make sure that any extension cable is in good condition and suitable for power
transmission. An undersized cable reduces power transmission and heats up
considerably.
Replace damaged cables immediately!
14.2
Assembling the machine
The machine has been dismantled for transport purposes. For assembly please observe the
following assembly instructions:
1.
Lift out column / base plate /
table
Lift the pre-assembled column
on the base plate with table out
of the packaging. A crane with
appropriate hoists are
recommended for that operation.
2.
Mount machine head
Put the machine head onto coloumn.
For lifting the Maschinenkopf auf die
Säule aufsetzen. A crane with
appropriate hoists are recommended
for that operation.