2. Unpacking and Installing the Rack Frame
NOTE : When installing the rails in the rack frame that has already been in use, perform the
and the following steps.
NOTE : If you use rack frames other than Hitachi racks, note the following:
• Replace the values of the depth and width described in
with those of your rack frames.
• If the total weight of the storage system is less than 830 kg, follow the procedure
described in
2.1 Unpacking the RKU Rack Frame
. If the total weight of the
storage system is 830 kg or more, calculate the sum of the storage system weight
and the rack weight, and then consult with the person in charge of the building to
which the storage system is carried about the procedure.
2.1 Unpacking the RKU Rack Frame
shows the packed status of the RKU Rack Frame.
1. Unpacking
NOTE : • Unpack it indoors.
Especially, do not unpack it in such places with the outdoor dust, the direct sunlight,
and the infiltration of rainwater.
•
Work on the unpacking in the place where a rapid difference of temperature does
not occur.
It may have dew condensation when it is unpacked in the place where a difference
of temperature is extreme.
• Do not push the side of the RKU rack frame.
For moving the RKU rack frame, push it from the front.
(1) Remove a wooden cap
and polyethylene bag
from the RKU Rack Frame.
(2) Remove two cotton tapes
which fasten the rear door.
(3) Remove four crepe tapes
which fix the leveling bolt.