Set Shims On Basehorse Locations
Locate basehorse positions along
chalk lines. Spot shim packs at each
basehorse location.
LINE UP
1
Consult With General Contractor
Ask the general contractor if there
have been changes in the building
dimensions since the print you are
using was issued. Also, ask the
points of reference from which you
should take dimensions to locate the
cases.
2
Snap Chalk Lines
Mark floor where cases are to be
located for the entire lineup.
4
Level Floor. Use Laser Transit
Leveling is necessary to assure prop-
er case alignment. Locate highest
point on chalk line as reference for
determining height of shim-pack
levelers. A laser transit is recom-
mended for precision and requires
just one person.
BASE RAIL
BASE RAIL
3
S n a p L i n e s O n B a s e R a i l
Locations
Snap lines where base rails are posi-
tioned, not the front or back edges of
the cases. See case cross section
drawings, pages 4-8, for rail location
dimensions.
6
Position First Case In Lineup,
Remove Casters, Level
Roll first case into position. Raise
case from end under cross support
using “J” bar. Remove cotter pins
and casters. [CAUTION! Keep hands
from under case] Level case on
shims.
Summary of Contents for ONRB
Page 2: ......
Page 4: ......
Page 6: ...2...
Page 24: ...20 WIRING DIAGRAMS 15 16 ORB ORBH ONRB ONRBH 2 DOOR...
Page 25: ...21 WIRING DIAGRAMS 15 16 ORB ORBH ONRB ONRBH 3 DOOR 8...
Page 26: ...22 WIRING DIAGRAMS 15 16 ORB ORBH ONRB ONRBH 4 DOOR 12...
Page 29: ...25 WIRING DIAGRAMS GFI...
Page 42: ...38 NOTES...