background image

www.hi-velocity.com

© 1995-2009 Energy Saving Products Ltd.

Module RPM

Refrigerant Module Installation (RPM-E) (3/5)

Module RPM Refrigerant Module Installation (RPM-E) (3/5)

Pipe Sizing

When sizing refrigerant piping, follow 

the outdoor unit manufacturer’s 

recommendations.

Run the pipes in the most direct route possible, taking into 

account structural integrity and building details. If the evaporator 

is located above the condenser, slope any horizontal runs toward 

the condenser. If the condenser is located above the evaporator, 

a P-trap must be installed at the bottom of the vertical riser. For 

long vertical risers, additional P-traps must be installed for every 

twenty feet 

(6m)

. For lines running over 50’ 

(15m)

, a suction line 

accumulator must be installed. Lines running over 100’ 

(30m)

 are 

not recommended. All lines should be piped so as not to restrict 

access to the front panels, filter section, or electrical enclosure.

Piping the RPM-E

Only refrigerant grade pipe and fittings are to be used with 

Hi-Velocity Systems. Plumbing fittings may contain wax or other 

contaminants which are detrimental to the proper operation of 

the system. Insulate the suction line with 3/8” 

(9.53mm)

 insulation 

such  as Armaflex.  In  high  heat  areas,  1/2” 

(12.7mm)

 insulation 

may be needed. If the lines are run in an area where temperatures 

could exceed 120°F 

(49°C)

 or runs longer than 50’ 

(15.24m)

, then 

the liquid line may need to be insulated as well. Support the pipe 

every 5 feet 

(1.52m)

, or whatever local code states.

Brazing & Pressure Testing

The RPM-E comes pre-piped with the coil assembly.  With the 

RPM-E, the Liquid and Suction lines are the only brazing that 

need to be done at the fan coil.  For charging and brazing, remove 

the front access panel of the RPM-E (

Fig. RPM-06

).  With the 

access panel removed, the coil assembly will be accessible.  Wet 

rag the liquid and suction line (or use a heat dissipating paste) 

to ensure no overheating occurs to the pre-piped coil assembly. 

Excess heat may damage the RPM-E components.

Fig. RPM-06 - Remove Front Access Panel

Once the system has been brazed it must be pressure tested. 

Pressure testing must be done with nitrogen and not refrigerant. 

Typically, pressures are tested to the maximum operating pressure 

that the system will see. Allow the system to hold the nitrogen 

charge for at least 15 minutes to ensure there are no leaks. Check 

with local codes for proper testing procedures. 

After the piping is installed and all components have been 

brazed together, a vacuum pump must be used to evacuate the 

system from both the low and high side to 1500 microns 

(200 

pa)

. Add pressure to the system to bring the pressure above zero 

psig. After allowing the refrigerant to absorb moisture, repeat the 

above procedure. Evacuate the system to 500 microns 

(67 pa)

 on 

the second evacuation, and ensure that the system holds at the 

vacuum pressure. If not, check for leaks and evacuate again.  At 

this point open service valves on pre-charged condensing units, 

and add refrigerant to the system if necessary.   

Evacuating

The use of an electronic leak detector is recommended, as it is 

more sensitive to small leaks under the low pressures.

Once the system has been determined clean and ready for 

charging, refrigerant can be added. The access ports on the 

condenser must be open at this point. Never leave the system 

unattended when charging. With the system running, slowly 

add refrigerant. The typical operating point of an RPM-E coil 

is that of a saturated suction temperature of 38-40°F 

(3-4°C) 

and a suction line temperature of 42-44°F 

(6-7°C)

. In order to 

prevent overcharging during this stage, refrigerant should be 

added in steps. This will allow time for the system to settle and 

prevent ‘overshooting’ the ideal charge. Condenser pressures and 

temperatures remain similar to those in a conventional forced air 

system.  It is recommended that the coil be charged on a high load 

day at the compressor’s highest speed.

Charging

Summary of Contents for RPM-E Series

Page 1: ...Small Duct Heating Cooling and Indoor Air Quality Systems Hi Velocity Systems RPM E Cooling Installation Module RPM RPM E Cooling Installation 052813 www hi velocity com www hi velocity com Manufactured By ...

Page 2: ...access hatch The liquid and suction lines have male solder connections at a standard width making connections to the condenser lines quick and easy Fig RPM 01 RPM E Cooling Module Configurations When installing follow the recommendations shown in Table 01 demonstrated in Fig 01 For example a horizontal application could use A to B while highboy applications could use A to B1 Do not use a combinati...

Page 3: ... with a 19mm primary and secondary outlet The condensate drain must have a vented p trap installed Fig RPM 05 and run at a slope of 6 7mm per foot in the direction of the drain When installing the P trap one must be installed on both the primary and secondary outlets The P traps must have a minimum depth of two inches 51mm Due to the high negative pressure of the blower system the RPM E will hold ...

Page 4: ...heat dissipating paste to ensure no overheating occurs to the pre piped coil assembly Excess heat may damage the RPM E components Fig RPM 06 Remove Front Access Panel Once the system has been brazed it must be pressure tested Pressure testing must be done with nitrogen and not refrigerant Typically pressures are tested to the maximum operating pressure that the system will see Allow the system to ...

Page 5: ...airflow rates of SDHV systems The RPM E coil can operate at a level that is different from most other conventional system coils Typically superheat level are low two to four degrees of superheat Adjustment of the valve also differs somewhat Rather than having a large effect on the range of superheat adjustment of the valve has a larger effect on the system pressures superheat maintaining a fairly ...

Page 6: ...h Built in Check Valve Bypass Yes Yes Yes Site Glass Yes Yes Yes Access Ports Yes Yes Yes Freeze Stat Yes Yes Yes Shipping Weight lbs 48 22kg 59 27kg 74 34kg Module Size L x W x H 191 4 x 145 8 x 181 2 489mm x 371mm x 470mm 241 4 x 145 8 x 181 2 616mm x 371mm x 470mm 32 x 145 8 x 181 2 813mm x 371mm x 470mm Tons2 1 5 2 0 5 3 7 0 Kw 2 5 3 0 8 8 10 6 Kw 3 5 5 0 12 3 17 6 Kw 1 Smaller condensers may ...

Reviews:

Related manuals for RPM-E Series