2.3.4 Commissioning
Before switching on the device, it must be ensured that the following points are
fulfilled:
The power supply must correspond to the voltage indicated on the nameplate.
All covers required for contact safety must be fitted.
If the device is linked to other devices and/or equipment, consider the impacts and
take appropriate precautions before switching it off.
The protective conductor connection in the respective device carrier must be
connected to the protective conductor (for devices with protection class I).
Warning of personal injury and property damage!
Any interruption of the protective earth in the equipment carrier can result
in the device becoming a hazard. Intentional interruptions are not
permitted. If there is a suspicion that it is no longer possible to operate
the device safely, it must be shut off and secured against being
unintentionally switched on.
Attention!
The device must never be put into operation even if damage is
recognisable.
2.3.5 Troubleshooting
At the beginning of troubleshooting, all possible sources of faults on additional devices or
supply lines (measuring lines, wiring and downstream devices) should be taken into
consideration. If the fault is not found after checking these points, we recommend sending the
device to the supplier.
Danger of Electrocution!
Do not open the device when it is connected to the voltage! When
opening the devices or removing covers and parts, live parts may be
exposed. Connection points can also be live!
2.3.6 Decommissioning
Attention!
If the device is to be taken out of operation, the auxiliary power must
be switched off at all poles. The device must be protected against
unintended operation. If the device is linked to other devices and/or
equipment, consider the impacts and take appropriate precautions
before switching it off
.