STEP 13 COMPLETE WARRANTY CERTIFICATE
Mail in the warranty certificate immediately after installing the GutterMelt
®
SR
system. Failure to complete the warranty card could void the manufacturer’s
warranty. The warranty is subject to the guarantee conditions listed on the
warranty certificate, and upon documentation that the required resistance
readings were completed. You may wish to keep a copy of the warranty card
for your reference.
STEP 10 CONNECT POWER SUPPLY & ACTIVATION
The connection of an acceptable ground fault protection device power supply and the activation device must be
done in accordance with the National Electrical Code (NEC) and the Canadian Electrical Code (CEC).
The braided shield from GutterMelt
®
SR Cable must be wired to Ground for all primary power installations.
Caution: Never energize GutterMelt
®
SR until:
1. The GutterMelt
®
SR Cable has been verified to be free of damage.
2. All splices and all power kit and end kit connections have been inspected.
3. A Megohmmeter Test has been used to verify a minimum of 20 MegOhms between the
heating element and the braided shield.
STEP 12 COMPLETE AND ATTACH LABELS
STEP 11 TROUBLESHOOTING
Problem: GutterMelt
®
SR Cable fails the Megohmmeter Test
Potential Causes:
•
Check field installed power/end terminations and connection splices; correct as necessary
•
Inspect the GutterMelt
®
SR Cable for damage to the insulator, exposed braided shield, and/or contact between
the braided shield and the core wire(s). Replace entire length of damaged GutterMelt
®
SR Cable
Call Heatizon Systems technical support @ 801-293-1232 if additional assistance is required.
Note: In the event the power/end termination or splices are not the cause of the failed Megohmmeter
Test and the GutterMelt
®
SR Cable has not been damaged in any way, remove and replace the
entire length of GutterMelt
®
SR. For Warranty claims, please return the entire length of GutterMelt
®
SR to Heatizon Systems, with the end termination and power termination connections intact, for
evaluation prior to replacement.
Place the included labels in the following locations:
•
Electrical Panel Label — Inside door at electrical service panel. This
label matches the information printed on the GutterMelt
®
SR Cable
•
Stop Sign Warning Label — on or near the area to be heated by
GutterMelt
®
SR Cable