10
Start-Up Operation
Multiple Systems With Multiple
Evaporators
(Requires A Smart
Controller)
• Check all wiring connections to be sure
they are correct and tight.
• On the condensing units
-
Check setting of time delay relay.
It should be set at 1 minute
(the second marker).
-
Check the low pressure switch
setting on freezer units. It must be set
to 0 psig cut-out, 10 psig cut-in to
allow positive start and operation,
especially in cold ambient. This
can be changed to a higher value in
warmer climates. On cooler units,
the low pressure switch has a fixed
setting and cannot be adjusted.
• Turn power on.
S
S
S
M
CU
S
S
S
M
CU
S
S
S
M
CU
M
S
S
S
CU
SMART
CONTROLLER
SYSTEM 1
SYSTEM 2
SYSTEM 3
SYSTEM 4
M
= Master Evaporator
S
= Slave Evaporator
CU
= Condensing Unit
MULTIPLE SYSTEM CONNECTION
(See Smart Controller instruction manual for more details)
• On the MASTER evaporator
-
DO NOT REMOVE the room sensor
from any evaporator
• On the SLAVE evaporators. All Beacon II
boards are shipped with the factory
default as a “MASTER” evaporator.
-
Each SLAVE evaporator must be
changed to identify it as a SLAVE.
Use the “
PROGRAM REVIEW
”
button to scroll until
“SLA”
appears,
then use the “
SELECT
” knob to
select
“YES”
then press
“ENTER.”
• Use the Beacon II Smart Controller to
set system parameters. See Beacon
II Smart Controller installation
instructions for more details.
Summary of Contents for BEACON II H-IM-79E
Page 2: ...2 2007 Heatcraft Refrigeration Products LLC ...
Page 28: ...28 Wiring ...
Page 29: ...29 Wiring ...
Page 30: ...30 Wiring ...
Page 31: ...31 Wiring ...
Page 32: ...32 Wiring ...
Page 33: ...33 Wiring ...