HDE PRM-100 Operating Instructions Manual Download Page 5

5

OPERATING INSTRUCTIONS 

continued

Phasing Measurements

We recommend that two person crews take the readings. Since the operation is occurring
near two energized conductors, the use of two person crews allows each person to operate
one stick and maintain high safety standards.

In order to take a reading, each probe must contact an energized line. Be sure that only
those probes intended for the particular application are used (see page 6). Always keep
the connecting cord free and clear of energized phases and ground.

The phase rotation meter requires three connections for proper operation. Always connect
the ground lead first and only to a known good ground. After testing is complete, be
certain to remove and isolate the main contact probes from all voltage sources prior
to disconnecting the ground lead.

Take the Readings

To determine which of the two phases is leading or lagging, two separate readings
are required.

READING 1:

Place one probe (resistor stick) on each of the two phases being
tested and take a reading.

READING 2:

Reverse the probes (resistor sticks) so that they contact the same
two phases but in the opposite direction, and take a reading.

FOR EXAMPLE:

If in Reading 1 the probe with the meter on it was contacting Phase A
and the probe with the junction box was contacting Phase B, then
reverse them so the probe with the meter on it contacts Phase B and
the probe with the junction box contacts Phase A.

Determining the Results

The resistor stick with the meter on it will show a higher indication when it is in contact
with the leading phase. The meter indicates relative phase rotation. The resistor stick with
the meter on the leading phase will indicate a reading of up to 100 at the maximum
voltage for the range selected. The resistor stick with the meter on the lagging phase
will indicate about 60% of the leading phase reading

For three phases there are three pairs of phases, so any two pairs should
be tested as outlined above. For example, with three Phases A, B and C:

1. Test Phases A and B. A is determined to be leading B.
2. Test Phases A and C. C is determined to be leading A.

Now, A leads B from Step 1. C leads A from Step 2. Therefore, the rotation is
C-A-B. This can also be written as A-B-C. This can be verified by testing the
third pair of phases. Test Phases B and C. B is determined to be leading C. 

Summary of Contents for PRM-100

Page 1: ...ion Manual HD ELECTRIC COMPANY 1 4 7 5 L A K E S I D E D R I V E W A U K E G A N I L L I N O I S 6 0 0 8 5 U S A PHONE 847 473 4980 FAX 847 473 4981 website www HDElectricCompany com PHASE ROTATION METER a nd ACCESSORIES ...

Page 2: ...n VMCWL 96 See Instructions DANGER ELECTRIC SHOCK HAZARD ELECTRICAL ARC HAZARD READ INSTRUCTIONS AND OPERATIONS MANUAL BEFORE USE Always wear personal protective equipment including eye and face protection insulating gloves and FR clothing All OSHA and company work practices must be followed Always maintain proper working clearances Use only HD Electric probes appropriate and intended for the work...

Page 3: ...or voltage up to 10kV it should always be kept free and clear from you ground and any other conductors WARNING The phase rotation meter has a range switch and requires add on resistor sticks for higher voltage ranges Always completely remove the phase rotation meter from the live circuit before changing the range switch position or adding or removing add on resistor sticks Always use add on resist...

Page 4: ...e equipment to insure that it is functioning properly and is in safe working condition Failure to do so may cause serious injury or death and may result in erroneous test measurements Before taking any reading test and inspect the phase rotation meter as follows 1 Make certain the instrument is clean dry and waxed to a clear shiny surface 2 Inspect the cord for cracked insulation 3 Be sure that yo...

Page 5: ...cks so that they contact the same two phases but in the opposite direction and take a reading FOR EXAMPLE If in Reading 1 the probe with the meter on it was contacting Phase A and the probe with the junction box was contacting Phase B then reverse them so the probe with the meter on it contacts Phase B and the probe with the junction box contacts Phase A Determining the Results The resistor stick ...

Page 6: ...se on voltages above 15kV up to 45kV 6 ASP 15 25 EA 15 25 ASP 35U OLPS 6 OLPS 5 GCP 1 PROOFTESTER The PT 5000B ProofTester will produce 5kVDC at the test leads to confirm proper operation of the phase rotation meter The PT 5000B operates from one 9V alkaline battery and produces approximately 5kVDC at the connecting leads To use 1 Connect both tester leads to the phase rotation meter probes Isolat...

Page 7: ...e cord for cracking or other damage prior to each use Although we don t specify a calibration cycle we recommend you test measure and calibrate your instrument annually The Calibration and Maintenance Log can be used to record these events Contact HD Electric Company for details DATE CALIBRATED BY REPAIRS All repairs and calibration are performed at HD Electric Company If any damage is found pleas...

Page 8: ...dduetounavailabilityofparts HDElectricCompanywillusecommerciallyreasonableeffortstoobtainsubstitutepartsorconductworkaround design but cannot guarantee its ability to do so Items not found defective will be returned at your expense or failing receipt of instruction from you on return of such items within five 5 business days of our notice to you that the product is not defective HD Electric may di...

Reviews: