Dual Fuel (NG & LP) MACH Boiler Supplement                  

 

 

 4 

1.0 

Dual Fuel MACH

® 

Boilers  

 
This manual describes the installation requirements of the Harsco Industrial, Patterson-Kelley MACH

®  

dual fuel 

boilers.  While details may differ slightly, basic operation is the same for all models. This boiler is built to operate with 
natural gas (NG) or propane (LP).   
 
 
 
 
 
 
 
 
 
 
This boiler has been constructed by the factory and shipped as a dual fuel boiler.  It is 

essential

 to read, understand, 

and follow the recommendations of this manual before installing, operating, or servicing this equipment.  Failure to do 
so could result in serious injury, death, and/or property damage. 
 
Each MACH

®  

dual fuel boiler is equipped with two current switches: one switch is in the natural gas valve circuit and 

the other is in the propane gas valve circuit.  These switches are wired in such a manner as to prevent both fuels from 
being fired at the same time.  In the unlikely event that both fuel valves are open at the same time, the current 
switches cause a high gas pressure error which will shut both gas valves and force a manual reset lock-out of the 
ENVI™ control.   
 

2.0 

MACH

®

 C-750GG / C-900GG / C-1050GG DUAL FUEL BOILERS 

2.1 G

AS 

I

NPUT 

C

ONNECTIONS  

 

The MACH

®

 dual fuel boiler is equipped with dedicated connections for each fuel.  The natural gas (NG) connection is 

a 1 1/4” ball valve. The propane (LP) connection is a 1” ball valve.  If a fuel connection is not used, it 

must

 be capped. 

 

  It is imperative that the natural gas line be connected to the 1 1/4” connection 

and the propane line be connected to the 1“ connection.  Incorrect gas connections could result in 
serious injury, death and/or property damage. 

 

Do not exceed maximum pressure limits (14” W.C.) for LP & NG fuels. 

 
Installation of the fuel lines must comply with all applicable codes.  It is the responsibility of the installer to ensure 
compliance with all the requirements of the authority having jurisdiction. 
 
The fuel line ball valves are located on the rear face of the boiler. Each line is labeled for the required fuel.  Attach the 
propane (LP) line to the 1” ball valve labeled “PROPANE”.  Attach the natural gas (NG) line to the 1 1/4” ball valve 
labeled “NATURAL GAS”.   
 
It is recommended to close the ball valve for the non-selected fuel. 
 

Use approved pipe sealer that resists the action of fuel gases such as natural gas or propane.   

 DO NOT USE Teflon™ tape.  

Reorder No. 6020-V2WHPK

Improper use may
result in fire or injury.

Read instructions/safety
manual before installing, 
operating or servicing boiler.

c

!

WARNING

1998 HCS, Inc. 800-748-0241

Summary of Contents for MACH C-750GG

Page 1: ...__ Start Up Date ____________________ Harsco Industrial Patterson Kelley 100 Burson Street East Stroudsburg PA 18301 Telephone 570 476 7261 Facsimile 570 476 7247 www harscopk com OW MACH Dual Fuel Re...

Page 2: ...MACH Gas Fired Boiler Dual Fuel NG LP MACH Boiler Supplement 2...

Page 3: ...9 2 7 Electrical Logic Drawing MACH C 750GG C 900GG C 1050GG 10 2 8 Electrical Layout Drawing MACH C 750GG C 900GG C 1050GG 11 3 0 LIMITED WARRANTY 12 NOTICE The information contained in this documen...

Page 4: ...FUEL BOILERS 2 1 GAS INPUT CONNECTIONS The MACH dual fuel boiler is equipped with dedicated connections for each fuel The natural gas NG connection is a 1 1 4 ball valve The propane LP connection is a...

Page 5: ...MACH Gas Fired Boiler Dual Fuel NG LP MACH Boiler Supplement 5 GAS INPUT CONNECTIONS PROPANE 1 NATURAL GAS 1...

Page 6: ...you must release the switch in the OFF position before switching to the other fuel 5 Start the boiler according to the MACH C750 C1050 Installation Owner s Manual latest edition NOTICE It is recommend...

Page 7: ...test edition of the MACH C750 C1050 Installation and Owner s Manual Service and Maintenance on these units must only be performed by knowledgeable and experienced personnel familiar with its operation...

Page 8: ...when there is excessive manifold gas pressure for the proper operation of the boiler In addition a high gas pressure error could be due to both gas valves being open There are LED indicators on each g...

Page 9: ...C 900GG C 1050GG Mark Description 1 Burner Transition Piece 2 Blower 3 Venturi 4 Pilot Gas Tube LP or NG 5 High Gas Pressure Switch LP and or NG 6 NG Pilot Gas Tube 7 NG Automatic Gas Valve 8 NG Low...

Page 10: ...MACH Gas Fired Boiler Dual Fuel NG LP MACH Boiler Supplement 10 2 7 ELECTRICAL LOGIC DRAWING MACH C 750GG C 900GG C 1050GG...

Page 11: ...MACH Gas Fired Boiler Dual Fuel NG LP MACH Boiler Supplement 11 2 8 ELECTRICAL LAYOUT DRAWING MACH C 750GG C 900GG C 1050GG...

Page 12: ...H Gas Fired Boiler Dual Fuel NG LP MACH Boiler Supplement 12 3 0 LIMITED WARRANTY Warranty information may by found in the latest edition of the MACH Installation and Owner s Manual for each unit seri...

Reviews: