Preparation for Installation
Installation must be carried out by authorized personnel. Follow the steps below:
1. Position the machine on a flat surface and allow at least 50cm clearance on both
sides as well as the back side, this is essential for the hot air ventilation and also
to allow enough room for maintenance personnel to carry out necessary service
and maintenance
2. Adjust the foot stand so that the machine is level and stable.
3. Loosen all packing cable ties and materials in order to free up all machine
movements.
4. Connect the power plug to a suitable outlet with at least 10A capacity. Make sure
grounded and reliable.
5. Locate the air hose supplied with the machine. Connect one end to the inlet of the
compressed air water filter at the back side of the machine; connect the other end
to a compressed air supply such as air compressor or central air supply. Make
sure the compressed air supply has at least 0.4Mpa (4 bar) of pressure.
6. Install the tensioner at the top of the machine and align the tape spool at right
angle to the working table of machine. (see diagram below)
7. Turn on the power,later it will show the languages page.(shown in Figure 1)