background image

Supplied By www.heating spares.co  Tel. 0161 620 6677

10

12

Expansion Tank:

The expansion tank must be of the diaphragm

type and should be connected close to the inlet side of the pump.
The expansion vessel must suit the volume of the system -

Safety Valve:

A safety valve complying with the requirements of

BS759 must be fitted to the flow pipe as near as possible to the boiler
with no restriction in the flow before the valve. (Refer to Fig. 12)
The valve should be fitted by a horizontal or vertically upwards
connection and accessible for testing.
The valve should be so positioned so that any discharge of steam
or water cannot cause any harm to occupants or electrical
installations.

Pressure Gauge:

A pressure gauge with a range of 0-4 bar

must be fitted so that it is visible to the person filling the system.

3.7.2

SEALED SYSTEMS

The system pressure should be not less than the static height, 
this being the highest point in the system above the 
expansion tank.

The expansion vessel has to be suitable to accommodate the
change in volume of the water in the system when heated
between 10°C to 110°C.  See BS5449:1 for further information.

Hot Water Cylinder:

The cylinder used should be of the

indirect type, suitable to operate at a total pressure of 0.35 bar 
(5 lb/in

2

) plus the pressure at which the safety valve is set.

Do Not Use A Single Feed Indirect Cylinder.

Filling Point:

The system must be provided with a low level filling

point fitted with a stop cock.  The method adopted for filling the
system should comply with local Water Authority regulations.

Provisions should be made for replacement of system water losses
by using a make-up vessel which must be fitted above the highest
point in the system, or by pre-pressurising the system.

Refer to BS5376:part 2:1976 clause 14.3.5.

The primary flow and return pipework between the boiler and the
hot water cylinder must be 28mm and be connected to the 28mm
connections, the flow to the top manifold and the return to the
bottom manifold. (Refer to Fig. 11)
‘Street’ elbows, 

must

be used for the 28mm gravity connections

to the boiler to provide adequate clearance for fitting the right
hand inner case.
The central heating flow 

must

be connected to the 22mm

connection on the top manifold.
The central heating return 

must

be connected to the 22mm

connection on the bottom manifold to ensure correct operation of
the integral injector system.
Gravity systems require a minimum circulating head of 1m where
there is no horizontal pipe run.  An increase in circulating head of
0.5m is required for each 1m of horizontal run.

Note:

Gravity runs near the minimum circulating head may

result in prolonged cylinder recovery.

Note:

It is recommended that when used on a gravity domestic

hot water application a Honeywell “C Plus” plan or equivalent is
fitted to the system to give suitable control over the domestic hot
water temperature.  The cylinder thermostat should be set 

NO

higher than 60°C.  The Honeywell “C Plus” will allow the pump
overrun to operate (should it be necessary) without warming the
radiators when the domestic hot water only is on. The bypass
should have the same water volume, 7 litres minimum, but should

NOT

incorporate any radiators.  The flow sensing temperature is

limited to 6O°C in the gravity mode, when the CH pump is off. This
is to prevent the DHW cylinder from overheating.

BS5449:1:1977, clause 25.
VOLUME OF WATER IN APPLIANCE = 3.0 litre.

Vessel Charge &
Initial System

bar

0.5

1

1.5               

Pressure

psi

7.3

14.5

21.8

For expansion vessel capacity,
multiply system volume by:

0.0833

0.109

0.156

3.7.1.2

COMBINED PUMPED 

SEALED WATER SYSTEM

CH & GRAVITY DHW SYSTEMS

Halstead Boilers manufacture a Sealed System Pod that
fits directly below the appliance. This incorporates an
expansion vessel, pump, pressure relief valve with
interconnecting pipe work.

AUTOMATIC
AIR VENT

HOT WATER
CYLINDER

FILL PIONT

PUMP

SAFETY
VALVE

EXPANSION
VESSEL

DRIAN
COCK

PRESSURE
GAUGE

BY -PASS WITH
LOCKSHIELD VALVE
WATER CONTENT
7 LITRES MINIMUM

FLOW

RETURN

HEATING
CIRCUIT

AIR RELEASE
VALVE

NON RETURN
VALVE

MAKE UP BOTTLE:
Observe minimum
static head requirements

The open vent may be connected to the un-used connection on
the top manifold. (Refer to Fig. 10)
The combined heating and hot water return must be connected to
the bottom manifold, use either the 28mm or 22mm connections.
The cold feed may be connected to the un-used connection on the
bottom manifold.

Summary of Contents for Best db 30

Page 1: ...st 50 G C No 41 333 52 Best 60 G C No 41 333 53 SUPPLY PRESSURE 20 mbar 0 0 8 6 TO BE LEFT WITH THE USER FOR USE WITH NATURAL GAS ONLY G20 CAST IRON WALL MOUNTED FAN ASSISTED BOILER B R I T I S H M A...

Page 2: ...ne radiator which should be fitted with lockshield valves only Gravity It is recommended that when used on a gravity domestic hot water application a Honeywell C Plus plan or equivalent is fitted to t...

Page 3: ...kw 8 79 11 72 14 65 17 58 Btu hr 30000 40000 50000 60000 kw 5 86 8 79 11 72 Btu hr 20000 30000 40000 60000 kw 11 13 14 75 18 43 22 37 Btu hr 37975 50315 62893 76326 kw 7 71 11 42 14 84 Btu hr 26316 3...

Page 4: ...CT VERTICAL SOCKET 90 ELBOW NON FLANGED STANDARD DUCT 90 ELBOW NON FLANGED EXTENSION DUCT 2 d FLUE WITH 90 BEND TERMINAL DUCT STANDARD DUCT FLANGED ELBOW 90 ELBOW NON FLANGED EXTENSION DUCTS 2 e HORIZ...

Page 5: ...a Standard flue assembly using either side or rear outlet Flue length L measured from the boiler outlet centre line to the outside wall face max 820mm Maximum wall thickness Wr Rear outlet 620mm max M...

Page 6: ...rd flue assembly Equivalent Length Shown is 3045mm Where Lb is 919mm and Lw is 820mm Lw is measured to the outside wall face Fig 4b As 4a but with one additional extension in length Lb Equivalent Leng...

Page 7: ...t length shown is 2325mm Where Lh measured from the top of the boiler casing to the centre line of the extra elbow 551mm and length Lw measured from the centre line of the extra elbow to the outside w...

Page 8: ...LOADED DIAGRAM Drawing amended 7 05 99 79 48 17 47 59 12 4 11 7 13 8 80 5 64 63 81 37 38 39 60 43 21 62 77 19 67 68 66 76 78 26 25 56 49 19 71 75 49 65 73 46 34 35 36 61 55 28 44 15 23 18 19 22 14 30...

Page 9: ...T be installed so that the terminal is exposed to the external air 3 1 STATUTORY REQUIREMENTS 3 2 BOILER LOCATION SAFETY INSTALLATION AND USE REGULATIONS 1984 AS AMENDED It is the law that all gas app...

Page 10: ...temperature difference of 11 C between the flow and return pipes on the boiler The resistance through each model of boiler at the required flow rate may be found in Section 2 3 3 7 WATER SYSTEMS An o...

Page 11: ...MOTORISED VALVE VALVED BY PASS LOOP WATER CONTENT 7 LITRES MINIMUM Fit either two motorised valves or one 3 way motorised valve COLD WATER STORAGE OPEN VENT INDIRECT CYLINDER AUTOMATIC AIR VENT MINIM...

Page 12: ...dequate clearance for fitting the right hand inner case The central heating flow must be connected to the 22mm connection on the top manifold The central heating return must be connected to the 22mm c...

Page 13: ...ned and make the necessary hole s in the ceiling roof Proceed to k f ADDITIONAL ELBOW OR FLANGED DUCT WITH ELBOW Using the wall mounting template and the dimensional information given in section 2 4 2...

Page 14: ...se with the four screws previously removed 4 5 AIR FLUE DUCT INSTALLATION 4 5 1 PREPARING THE AIR FLUE DUCTS If the wall thickness is less than 800mm 31in the air flue duct may be fitted without acces...

Page 15: ...n 425mm L 76mm MAX 319mm 17mm 19 ASSEMBLING THE FLUE SYSTEM TOP 1 SLIDE EXTERNAL SEALING RING UPTO FLUE TERMINAL L 2 STANDARD DUCT Push ducts fully over elbow and drill two 3 3mm dia holes Secure with...

Page 16: ...SEALING RING FIBRE SEAL FITTED 4 5 3 INSTALLING THE AIR FLUE DUCT FROM OUTSIDE THE BUILDING Flue hole diameter 100mm wall liner not necessary a Secure the flue elbow with seal to the appliance using 4...

Page 17: ...conomical heating system However should the boiler be installed for use with a combined PUMPED CH GRAVITY DHW system the small jumper plug in the front of the control box must be repositioned in the g...

Page 18: ...HEATING VALVE HOT WATER VALVE 230V MAINS INPUT OR A B C 4 5 6 8 NOT USED 5 2 1 9 3 8 2 1 10 3 1 2 3 L N E BROWN BLUE GREY ORANGE GREEN YELLOW BROWN BLUE GREY ORANGE GREEN YELLOW 1 3 2 1 2 4 5 2 1 5 1...

Page 19: ...THERMOSTAT 2 1 E N L L N E 9 8 3 2 1 9 2 3 BOILER PUMP 6 3 N L 3 4 N L 6 4 3 2 1 Honeywell ST699B 1002 Link L 5 8 ST 799A ST6400 ST6300 PROGRAMMER 2 Pump Live 1 Switched Live L Permanent Live 230V 50...

Page 20: ...he boiler and system should now be allowed to reach its maximum working temperature and examined for water leaks o Turn off the heating system and drain whilst still hot p Refill and vent ensuring all...

Page 21: ...of the boiler complete with its electrodes d Inspect and if necessary clean the burner assembly If either electrode shows signs of damage or wear replace it e Inspect and if necessary clean the main i...

Page 22: ...ISOLATE the mains electrical supply remove the front painted panel by sliding up and then away from the boiler remove the right hand portion of the inner case by first pulling off the control knob the...

Page 23: ...e the valve manifold assembly from the boiler 7 9 MAIN BURNER a Remove the four screws securing the left hand inner case Remove the case by sliding it forwards and off the appliance b Remove the combu...

Page 24: ...EN YELLOW RED RED WHITE WHITE PINK BROWN BLUE GREEN WHITE GREEN YELLOW GREEN YELLOW BLUE BROWN BLACK PURPLE BLUE RED WHITE WHITE RED BLUE RED BROWN RED BLACK BLACK GREEN YELLOW 2 1 N L ORANGE BLACK OR...

Page 25: ...ignition lockout turn thermostat to maximum setting and ensure programmer is switched on before pressing reset button YES NO Replace the fan Is there 230V at the fan motor Replace the fan YES NO Chec...

Page 26: ...rode All 1 500574 5 Gas Valve Without Ignition Device All 1 500569 6 Ignition Device For Gas Valve All 1 500570 7 Aquastat PCB All 1 600513 8 Thermistor All 1 500572 9 Overheat Cut Off Device All 1 50...

Page 27: ...nd flue are to be positioned and make the necessary hole in the wall s for the air flue duct as defined in section 4 2 c Install the boiler as described in section 4 with the exception of the flue sys...

Page 28: ...ax 01787 474588 SERVICE HOTLINE 01203 351424 Halstead Boilers are continuously improving their products and therefore reserve the right to change specifications without prior notice and accept no liab...

Reviews: