OVLEREEQ*G  OVLSREEQ*G  OVLESREEQ*G  OVLSEREEQ*G

97882C - (REV. A - 8/04)

Figure 6 – OVL-II SEREE-Q Rough-In

Figure 7 – Rough-In Assembly

Dual-Station Mounting Frames

Models

OVL-II SEREE-Q – OVL-II ESREE-Q

1.

Cut a rectangular wall opening

 37-1/2” (953 mm) W x

37-3/4” H (959 mm) and 4-1/2” (114 mm) above the floor line

(see Figure 7). The dimensions are required to obtain proper

rim and bubbler heights for compliance with ANSI standard

A117.1.

2.

Reinforce the wall opening

 on all sides to adequately

support the water fountain. This reinforcement must support

up to 150 lbs. static load and provide a means for securing

the frame assembly in place.

NOTE:

Building construction must allow for adequate air

flow on both sides and top of remote chiller unit a

minimum of 4” (102 mm) is required.

3.

Install plumbing and electrical rough-ins. 

A junction box

for a (3) wire, 10 amp branch circuit is provided on the

inside of the chiller. (Standard 120 Volts, 60 Hz, and single

phase.)

4.

Remove frames and related hardware

 from packaging.

Release the two shelf rods by cutting cable ties. Attach the

two frames together through the upright supports with (4)

5/16” x 3/4” (19 mm) long bolts and nuts (provided). Tighten

securely.

REVERSED CONFIGURATION:

HIGHER UNIT ON THE RIGHT

STANDARD CONFIGURATION:

HIGHER UNIT ON THE LEFT

40

18

Summary of Contents for OVL-II-EREE-Q

Page 1: ...talled unit for future reference Service to be performed by authorized service personnel only INSTALLER NOTE It is common practice to ground electrical hardware such as telephones computers and other devices to available water lines This can however cause electrical feedback in the plumbing circuit which results in an electrolysis effect occurring in the fountain This may result in water which has...

Page 2: ...lex option Bubbler Gasket Strainer Plate S S Strainer Plate A G Drain Gasket Packing Ring Drain Nut Friction Ring Drain Plug S S Drain Plug A G Drain Tube Drain Tube Waste Tube Gasket Slip Nut Regulator W Red Spring Regulator W Green Spring Regulator Holder Basin S S Basin A G Basin Liner S S Basin Liner A G Screw 8 18 x 37 Top Plate Actuator Bottom Plate Actuator Extended Reach Arm EE S S Extende...

Page 3: ...EE A G Lower Panel OVL II EREE SREE S S Lower Panel OVL II EREE SREE A G Lower Panel OVL II SEREE ESREE S S Lower Panel OVL II SEREE ESREE A G Strainer Supplied with Chiller Union 1 4 Tee 1 4 Poly Tubing 1 4 Cut To Length Bubbler Nipple Assembly Regulator Mounting Bracket Solenoid Valve Assy Power Cord Sensor Clear Hex Nut Unplated Strain Relief Bushing Snap Bushing 50 I D Spacer Regulator Nut Hex...

Page 4: ... up to 150 lbs static load and provide a means for securing the frame assembly in place NOTE Building construction must allow for adequate air flow on both sides and top of remote chiller unit a minimum of 4 102 mm is required 3 Install plumbing and electrical rough ins A junction box for a 3 wire 10 amp branch circuit is provided on the inside of the chiller Standard 120 Volts 60 Hz and single ph...

Page 5: ...with frame upright support edges flush with the finished wall face Secure the frame to the wall through holes with 12 5 16 bolts or screws not provided Tighten securely NOTE Be sure that frame is squared in location Do not use less than required screw quantity and size 6 Attach the chiller shelf support rods to the right side of the frame uprights at the second set of holes counting from the botto...

Page 6: ...orce the wall opening on all sides to adequately support the water fountain This reinforcement must support up to 150 lbs static load and provide a means for securing the frame assembly in place NOTE Building construction must allow for adequate air flow on both sides and top of remote chiller unit Minimum of 4 102 mm is required 3 Install plumbing and electrical rough ins A junction box for a 3 w...

Page 7: ...o the bottom of wall opening Secure the frame sides and top to the wall opening using 10 5 16 bolts or screws not provided NOTE Be sure that frame is squared in location Do not use less than the required screw quantity and size MODEL OVL EREE MODEL OVL SREE Legend Item Description A 1 4 O D Tube Water Outlet Connection B 3 8 O D Tube Water Inlet Connection C 1 1 4 O D Waste Tube D Electrical Inlet...

Page 8: ...strainer provided with chiller by pushing it in until it reaches a positive stop approximately 3 4 19mm on the marked chiller inlet port See Figs 17 18 Attach an unplated and deburred copper water inlet line and a service stop not provided to the chiller Turn on the water supply and flush the line thoroughly 5 Make connection between remote chiller outlet tube and solenoid valve assembly Outlet po...

Page 9: ...l lower stream height For Electronic sensor units only remove bottom access panel and turn adjustment screw on the regulator Item 14 Figs 25 27 Clockwise adjustment will raise stream height and counterclockwise movement will lower stream height For best adjustment stream height should be approximately 1 1 2 38mm above the bubbler guard See Figure 16 15 Mount lower panel Loosen the two 2 10 24 x 5 ...

Page 10: ...ulator Assembly 19 2 20 29 30 31 23 25 27 26 Stream Height Adjustment Sensor Control The sensor has a 2 second delay time If sensor fails to operate valve mechanism or operates erratically check the following a Ensure there are no obstructions within a 40 inch radius from the front of fountain b Check wire connections at the solenoid valve and at the sensor CAUTION Make sure unit is unplugged befo...

Page 11: ... OVLSREEQ G OVLESREEQ G OVLSEREEQ G 97882C REV A 8 04 Figure 23 Push Bar Fountain Assembly Figure 24 Push Bar Fountain Assembly Side View 3 4 16 17 32 5 10 22 6 7 8 9 13 11 8 12 33 See Fig 22 1 See Fig 20 See Fig 21 ...

Page 12: ...R LOCAL DISTRIBUTOR OR VISIT OUR WEBSITE WWW HALSEYTAYLOR COM Figure 25 View of Electronic Sensor Figure 26 View of Solenoid Valve Figure 27 Electronic Sensor Fountain Assembly Side View Connect To Sensor Assy 38 3 4 45 41 40 50 49 51 21 48 42 46 1 44 39 32 33 5 15 14 47 43 12 13 11 9 8 7 6 10 8 REPAIR SERVICE INFORMATION TOLL FREE NUMBER 1 800 260 6640 ...

Reviews: