Operation
50
Section 3: Operating
Hale Products, Inc., May 2005, Rev-B
3.10
POST OPERATION PROCEDURES
1.
Return the engine to IDLE, then slowly close all valves.
2.
Place the transmission in NEUTRAL, then slowly shift to ROAD to disen-
gage the pump.
3.
Drain the pump (especially important in freezing weather):
❑
Open the discharge valves, remove suction tube caps, and discharge
valve caps.
❑
Open the pump body drain cocks or Hale multiple drain valve. If a multi-
ple drain valve is used, all pump drain lines should be connected to this
valve.
❑
On two-stage pumps, move the transfer valve back and fourth between
the VOLUME and PRESSURE positions.
4.
If sea water, dirty water, alkaline water or foam solution has been used,
FLUSH THE PUMP WITH CLEAN WATER.
5.
If installed, drain the gearbox cooler. After the pump is completely drained,
replace all caps and close all valves.
6.
Remove the wheel chocks only when preparing to leave the scene.
7.
Fill out the Pump Run Log, indicating total pumping and out-of-station time.
8.
Report all pump, vehicle and equipment malfunctions, and irregularities to
the proper authority.
9.
Know and follow all local procedures. See WARNING ! note on page 33.
Summary of Contents for Silencer AP Series
Page 6: ...Overview 6 Silencer Series Booster Pump p n 029 0020 83 0...
Page 22: ...Introduction 22 Section 2 Introduction Hale Products Inc May 2006 Rev B...
Page 32: ...Accessories Options 32 Section 2a Accessories Hale Products Inc May 2006 Rev B...
Page 66: ...Preventive Maintenance 66 Silencer Series Booster Pump p n 029 0020 83 0...
Page 124: ...Installation 124 Basic Installation Hale Products Inc August 06 Rev B...
Page 143: ...143 Appendix F Cavitation Hale Products Inc Nov 2005 Rev A Cavitation...
Page 144: ...Cavitation 144 Appendix F Cavitation Hale Products Inc Nov 2005 Rev A...