HAKO Sweepmaster P900 R Training Download Page 32

IR/KUD/102023

Page 32

Troubleshooting

Wiring

Description

Alarm description

Alarm Code

Check the motor's wires
Check internal motor resistance
If ok and the controller repeats this alarm, change it

A1.M(PIN1) at M1.PIN(A2) and
A1.M2(PIN2) at M1.PIN(A1)

Controller has protected itself, cause of
an external short circuit

Overcurrent (short circuit)

7x flash

If the controller repeats this alarm and the power connections are
o.k., change it

G1.PIN(P) to X0PIN(P) to F1.PIN1/PIN2
at A1.PIN (B+) and
A1.PIN(B-) to X200 to X0PIN(N) at
G1.PIN(N)

Controller detects a failure on the
external power fuse or power
connections

Power fuse or on-board contactor
damaged

8x flash

Check battery's charge. Check your parameter settings: if the
controller repeats this alarm, change it

G1.PIN(P) to X0PIN(P) to F1.PIN1/PIN2
at A1.PIN (B+) and
A1.PIN(B-) to X200 to X0PIN(N) at
G1.PIN(N)

Battery voltage lower than value set by
parameter (< 18V)

Undervoltage

9x flash

Check the battery status

/

Battery voltage higher than 45V

Overvoltage

10x flash

Check the motor power consumption (25A max. 60s long)

A1.M(PIN1) at M1.PIN(A2) and
A1.M2(PIN2) at M1.PIN(A1)

/

Overload protection

11x flash

Check wiring to A1.X1PIN6
Eliminate reason for deactivation.
Then reset with key switch OFF-ON

A1.X1PIN8 (only if A1.X1PIN5 (24V)) to
K3.PIN86 and K3.PIN85 to A1.X1PIN7
Required feedback: X200 to K3.PIN30
Switch.fct. K3.PIN30 to 87a (not switched
=> GND = deactivated); PIN30 to 87
(switched => A1.PIN6 OPEN)

Controller is disabled

Disable switch on

12x flash

Check the key switch wiring

G1.PIN(B+) to X0PIN(B+) to X100 to
F2PIN1/2 to X2PIN1 to S1PIN(BAT)
Switch.fct. S1 PIN(BAT) ... (OPEN);
PIN(BAT) to PIN1+2(CLOSED)
S1 to X2PIN3 to F3PIN1/2 at
A1.X1PIN15

Key switch was opened

Key-off sequence detected

13x flash

If the controller repeats this alarm, change it

/

Internal memory fail

14x flash

Check wiring of seat contact switch and seat contact switch

G1.PIN(B+) zu X0PIN(B+) zu X100 zu

F2PIN1/2 zu X2PIN1 zu S1PIN(BAT)

Schaltfkt. S1 PIN(BAT) … (OFFEN);

PIN(BAT) zu PIN1+2(GESCHLOSSEN)

S1 zu X2PIN zu F3PIN1/2 zu X1PIN4 zu

X5PIN1 an S5… (OFFEN);

(GESCHLOSSEN) zu X5PIN2 zu X1PIN5

an A1.X1PIN5

No signal from seat contact

No release

15x flash

Summary of Contents for Sweepmaster P900 R

Page 1: ...IR KUD 102023 Page 1...

Page 2: ...IR KUD 102023 Page 2...

Page 3: ...IR KUD 102023 Page 3...

Page 4: ...h Sweeping speed till 700 970 1240 700 970 1240 mm Sweeping width without with 1 with 2 side brooms till 7450 till 7450 m2 h Theoretical ground coverage with 2 side brooms till 4200 till 4200 m2 h The...

Page 5: ...ank capacity 100 bar Traction drive Electric system 12 45 V Ah Starter Battery 5 6 A Light coil current 24 DC V Operation voltage 0 6 kW Traction drive 0 75 kW Central motor Dust fan Sweeping 1 9 kW T...

Page 6: ...king combustion process 1 1 1 Number of cylinders arrangement 68 56 68 28 55 88 68 27 55 88 mm Bore Stroke 203 205 206 cm3 Displacement 0 10 0 20 0 15 0 28 0 15 0 28 mm Valve clearance with a cold eng...

Page 7: ...IR KUD 102023 Page 7...

Page 8: ...IR KUD 102023 Page 8...

Page 9: ...IR KUD 102023 Page 9...

Page 10: ...IR KUD 102023 Page 10 Adjustment dimension between broom and throwing plate 16 2mm...

Page 11: ...IR KUD 102023 Page 11 2 3 Adjustment hight Adjustment inclination Adjust the swing angle by moving it in the slot Screw should be aligned with the outer edge of the chassis...

Page 12: ...IR KUD 102023 Page 12...

Page 13: ...IR KUD 102023 Page 13...

Page 14: ...IR KUD 102023 Page 14...

Page 15: ...IR KUD 102023 Page 15...

Page 16: ...IR KUD 102023 Page 16...

Page 17: ...IR KUD 102023 Page 17...

Page 18: ...IR KUD 102023 Page 18...

Page 19: ...IR KUD 102023 Page 19 Till S N 650210525062 1 min from S N 650210525073 1 min 1 min...

Page 20: ...IR KUD 102023 Page 20 1 min...

Page 21: ...IR KUD 102023 Page 21...

Page 22: ...IR KUD 102023 Page 22...

Page 23: ...IR KUD 102023 Page 23...

Page 24: ...IR KUD 102023 Page 24...

Page 25: ...when working on the engine and the electrical system Notes for the three phase alternator 1 Only run the engine with the battery connected 2 Do not use a charger to jump start 3 Disconnect the batter...

Page 26: ...IR KUD 102023 Page 26...

Page 27: ...IR KUD 102023 Page 27...

Page 28: ...IR KUD 102023 Page 28...

Page 29: ...IR KUD 102023 Page 29...

Page 30: ...IR KUD 102023 Page 30...

Page 31: ...d A1 X1PIN3 GND to X1PIN3 to X3 PIN3 at R1PIN3 GND R1PIN1 0 5 4 5V to X3PIN2 to X1 PIN2 at A1 X1PIN2 Signal Controller has detected that the potentiometer signal voltage is higher than maximum range P...

Page 32: ...higher than 45V Overvoltage 10x flash Check the motor power consumption 25A max 60s long A1 M PIN1 at M1 PIN A2 and A1 M2 PIN2 at M1 PIN A1 Overload protection 11x flash Check wiring to A1 X1PIN6 Elim...

Page 33: ...IR KUD 102023 Page 33...

Page 34: ...IR KUD 102023 Page 34...

Page 35: ...IR KUD 102023 Page 35...

Page 36: ...IR KUD 102023 Page 36 If parameters have been changed unintentionally the parameter F0 2 can be used to reset the control to the delivery status The driving potentiometer needs to be read in again...

Page 37: ...IR KUD 102023 Page 37...

Page 38: ...IR KUD 102023 Page 38...

Page 39: ...IR KUD 102023 Page 39...

Page 40: ...IR KUD 102023 Page 40...

Page 41: ...vice and parking brake X Check the treads of the wheels X Check hydraulic oil level X Check hydraulic system for leakage X Check hydraulic hoses X X Change hydraulic oil X Change hydraulic oil filter...

Page 42: ...wires and plug connections for ease of movement wear and corrosion n a X Check v belt tension X n a Check v belt for wear and tension X n a Visual inspection of wheel tyre X n a Check service and par...