Note:
Obstacles should be 2000mm off the top of the out-
door unit. Obstacles nearby should be 400mm lower
than the top of the unit.
1. Handing
As there is no protective package for the outdoor unit,so
the following points merit attention:
(1) When forklift is used, insert the fork into the holes in
the base plate.
(2) When crane is used, lift the unit with 4 pieces of steel
rope with diameter above 6 mm.
(3) Put protective materials between the cable and the
unit to prevent deformation and damage of the surface.
2.Mounting
(1) The distance between two connections must not be
less than 20mm.
5.1
Outdoor installation procedure
Warning
Selection of installation site
It should be installed at places where it is firm enough to withstand the weight of the air
conditioner to prevent falling.
Typhoon and earthquake prevention. It should be installed according to specific
requirements.
Inasppropriate installation may lead to accidents.
(1)During installation, connect the outdoor unit and align
the mounting surface(See the figure on the right).Mount
the electric distribution device on the external side of
the unit in accordance to the installation instructions for
electric distribution device.
(2)To ensure good performance of the machine and facili-
tate installation and maintenance, adequate space must
be reserved (See figure on the right).
Installtion space
Blow out
Air inlet
Air inlet
maintenance plate
Over 300mm
Over 20mm
Over
20mm
Over
20mm
Over
20mm
Over
1000mm
(front side)
Air inlet
M12 foot screw bolt
4 screws each unit
Rope
Protection cushion
Base panel
Rope
Commercial Air Conditioner
Model: AU96NATAEA
AD96NAHAEA,
AP96NACAEA
15