background image

 

 

 

 

12 

 

 

5.52.157.00.01.05 

 

  Hang a new original chain (same size and oiled) in the side opened chain link and insert it. 

  Make sure the chain is not installed twisted. 

  Make sure the chain links are aligned in one direction. 

  Assemble the chain to the end fastening. 

 

11 

Inspection 

 

 

11.1 

Periodic checks 

Independently from the regulations of the individual countries, lifting devices must be checked at least yearly 
by a qualified person or licensed qualified person regarding its functional safety.  

 

11.1.1 

Components to be checked 

The following must be checked: 

  Dimensions of load chain, load hooks, pawls, bolts, ratchet wheels, brake linings. 

 

The dimensions must be compared to the dimensions in the tables. 

  A visual inspection for deformations, cracks and corrosion must be carried out. 

 

   

CAUTION!

 

When the wear limit is reached, the part must be exchanged by a new, original part. 

 

 

at 

commissioning 

daily 

checks 

1st maintenance 

after 

3 months 

Inspection 

Maintenance 

every 

3 months 

Inspection Mainte-

nance 

every 

12 months 

Check screw connections 

 

 

 

Check lifting, lowering functions. 

 

 

 

Check brake function 

 

 

 

for ratchet lever hoists: Check free-wheeling mechanism of the 

chain 

 

 

 

Brake - check wear of brake lining 

 

 

 

 

Check chain wheels, ratchet wheels and pawls. 

 

 

 

 

Clean and lubricate the load chain. 

 

 

Check the load chain for elongation and wear 

 

 

 

 

Check the load hook for cracks and deformation 

 

 

 

 

Load hook - check the safety catch 

 

 

 

Check and lubricate the bearing of the chain pulleys. 

 

 

 

Check the chain pulleys 

 

 

 

Have the equipment checked by a qualified person 

(periodic inspection) 

 

 

 

 

 

 

   

WARNING!

 

If one or several of the dimensions fall below or exceed the dimensions in the table, or if cracks or 
corrosion are found, the parts must be replaced with original spare parts. 

 

11.2 

Checking the load chain 

   

CAUTION!

 

The load chain must be tested over its entire length! 

The measure  of the load chain must be carried out especially in the areas which are subject to the highest 
wear. Through the lifting movement, these are the contact points of the chain with sprocket wheel and 
deflection pulleys. 

 

acc. DIN 685-part 5 

 

L11 = pitch increase over 11 chain links 

 

L1   = pitch increase over 1 chain link 

 

 

Illustration 9 

 

 

dm= detected link diameter (d1+d2)/2 

 

 

Illustration 10   

 

 

Summary of Contents for 50/07

Page 1: ...5 52 157 00 01 05 Rev 05 HADEF Ratchet Lever Hoist Type 50 07 Installation Operating and Maintenance Instructions...

Page 2: ...s Table of Contents 1 Information 3 2 Safety 4 2 1 Warning notice and symbols 4 2 2 Duty of care of the owner 4 2 3 Requirements for the operating personnel 5 2 4 Appropriate use 5 2 5 Basic safety me...

Page 3: ...urance system as per ISO 9001 The production of components at our work is subject to strict intermediate checks After assembly each product is subject to a final test with overload For the operation o...

Page 4: ...or they must be suitable for use in area prone to explosion The owner is responsible for this However in everyday operation this degree of safety can only be achieved if all measures required are take...

Page 5: ...ven devices 20 C 40 C Defective devices and load suspension devices must not be used until they have been repaired Only original spare parts must be used Non compliance will result in any warranty cla...

Page 6: ...ack into operation Do not use a hoist that is defective pay attention to any abnormal noise it makes during operation Stop working immediately in case of disturbances and remedy failures Any damage an...

Page 7: ...ified personnel No liability for any damage resulting from improper transport or improper storage 3 1 Transport The devices are checked and if so adequately packed before delivery Do not throw or drop...

Page 8: ...gular use of the equipment 4 4 Important components Gearbox Gear box parts are made of high quality material Load pressure brake Holds the load in any position Housing Made of steel plate Load chain A...

Page 9: ...uipment The employer must ensure that the operating instructions are available near the equipment and that they are accessible for the operating personnel 7 1 Devices from 750 kg up to 6000 kg Before...

Page 10: ...k there The chain does not move the load cannot be lowered Remedy Charge the ratchet lever hoist again Release the brake by setting down the load OR Turn the switching pin to position Lowering and rel...

Page 11: ...ly placed oiled and in good condition 10 Maintenance 10 1 General All monitoring servicing and maintenance operations are to ensure correct functioning of the equipment they must be effected with utmo...

Page 12: ...ons X X Check lifting lowering functions X X Check brake function X X for ratchet lever hoists Check free wheeling mechanism of the chain X X Brake check wear of brake lining X Check chain wheels ratc...

Page 13: ...to wear or deformation the chain must be replaced 11 3 Checking the load hook Load hook X measuring distance hook mouth width Y measured length from hook no 6 H thickness of hook saddle Illustration...

Page 14: ...not ensure the formation of a lubricating film within the links The adjacent link points must always be lubricated to prevent excessive wear If the same lifting operations are carried out constantly t...

Page 15: ...ree from fracture Avoid oil grease dirt and humidity on the brake linings as this increases wear 12 6 Lubricant Selection FUCHS SHELL ESSO MOBIL TOTAL CASTROL KL BER Renolit FEP 2 Alvania EP 2 Unirex...

Page 16: ...l spare parts Hoist does not lift the whole distance long Hook stucks chain is twisted Place hooks and chains in correct position The brake remains closed stuck the hoist was unloaded without lowering...

Page 17: ...inal decommissioning disposal Measures are as above After disassembly ensure that the disposal of the equipment and any materials it contains is carried out in accordance with environmental regulation...

Reviews: