Maintenance

C. Routine maintenance

To reduce accidents, the owner or operator should ensure that an appropriate routine maintenance schedule is established, implemented and 

maintained. This should take into account local conditions and the manufacturer's instructions that can affect the necessary inspection 

frequency. The schedule should list the components to be maintained and should also give procedures for dealing with complaints and 

breakdowns.

The routine maintenance of playground equipment and surfaces should consist of preventative measures to maintain their level of safety, 

performance and compliance with the relevant part(s) of EN 1176. Such measures should include:

a) tightening of fastenings;

b) re-painting and re-treatment of surfaces;

c) maintenance of any impact attenuating surfaces;

d) lubrication of bearings;

e) marking of equipment to signify loose fill finished surface level;

f) cleaning;

g) removal of broken glass and other debris or contaminants;

h) restoring loose fills to the correct level; and

i) maintenance of free space areas.

D. Corrective maintenance

Corrective maintenance should include measures to correct defects, or th re-establish the necessary levels of safety of the playground 

equipment and surfaces. Such measures should include:

a) replacement of fastenings;

b) welding of welding repairs;

c) replacement of worn or defective parts; and

d) replacement of defective structural components.

E. Personal safety

Repairs during operation that could put the safety of maintenance personnel of the public at risk, should be avoided.

F. Equipment alterations

Alterations to parts of a piece of equipment or structure that could affect the essential safety of the equipment should only be carried out 

after consultation with the manufacturer or a compete person.

Summary of Contents for GS-PD8003

Page 1: ...ing condition each rope Screwing the turn buckle and conversion the turnbuckle in anchors plate see for this work step turnbuckle assembly 2 Abrasion condition of rope Checking of all rope surface Str...

Page 2: ...0m Use zone L 11 5 m ASTM EN W 11 5 m Completed Net Features The series is a steel framed climbing structure made of steel loaded Nylon cables and comes protected against UV The GS PD8003 features GS...

Page 3: ...BS EN 1176 1 ASTM F1487 CSA Z614 The use zone for stationary play equipment shall extend no less than 72 in 1830mm from all sides of the play structure Fall Height 1 855mm from surface The Fall heigh...

Page 4: ...5 326 9026 65 Saengnim daero 259beon gil Saengnim Myeon Gimhae si Gyeongsangnam do Republic of Korea PLAY DOME MODEL NO Rev_1 2017 11 GS PD8003 4 Foundation layout Attach Frame plate to footing Founda...

Page 5: ...LAY DOME MODEL NO Rev_1 2017 11 GS PD8003 CON C 300 1000 CON C 2 x 2 3 8 x L125 Set Anchor POST PLATE 500 800 800 800 CON C 4 x 6 5 8 x L200 SET ANCHOR 1000 300 FRONT VIEW PLAN FRONT VIEW PLAN 300 300...

Page 6: ...ea PLAY DOME MODEL NO Rev_1 2017 11 GS PD8003 6 Overall Assembly Overall Assembly Assemble the parts in the following order 1 Check number of the parts and locations as next drawing Post s location is...

Page 7: ...gsangnam do Republic of Korea PLAY DOME MODEL NO Rev_1 2017 11 GS PD8003 7 Overall Assembly Pipe Lower part GALVANIZED STEEL PAINTED POST Frame Assembly Assemble the parts in the following order 1 Scr...

Page 8: ...yeon Gimhae si Gyeongsangnam do Republic of Korea PLAY DOME MODEL NO Rev_1 2017 11 GS PD8003 8 Overall Assembly Net Assembly Assemble the parts in the following order 1 Check the stair net s location...

Page 9: ...5 Saengnim daero 259beon gil Saengnim Myeon Gimhae si Gyeongsangnam do Republic of Korea PLAY DOME MODEL NO Rev_1 2017 11 GS PD8003 9 BOLT EYE BOLT POST Assemble GSWeb clamp in the attach with stainle...

Page 10: ...im daero 259beon gil Saengnim Myeon Gimhae si Gyeongsangnam do Republic of Korea PLAY DOME MODEL NO Rev_1 2017 11 GS PD8003 10 No 103 Bolt for Clamp x 2 No 62 GSWeb Clamp POST No 105 M10 x L35 No 106...

Page 11: ...ecommended that subsequent checks on tension should be carried out at monthly intervals and adjusted as required This will increase the overall longevity of the product Checking 1 month Refer to IPEMA...

Page 12: ...local regulations B Procedures Defects that occur during operation and which put safety at risk should be corrected without delay If this is not possible the equipment should be secured against use e...

Page 13: ...sures should include a tightening of fastenings b re painting and re treatment of surfaces c maintenance of any impact attenuating surfaces d lubrication of bearings e marking of equipment to signify...

Reviews: