2. Installation
16
PNEG-1614
Heavy Duty Bin Stairs and Platform Assembly for 2.66" Corrugated Bin
Figure 2Q Horizontal Bracket to Step
Figure 2R Brace Strap Connection
5. Continue adding four (4) step sections until you have reached the bottom of the bin. Each of the
next wall brackets will be placed 32" lower and four (4) bolt spaces or 37-1/2" around the bin farther
than the previous bracket.
6. The last step will need to be supported by a wall bracket assembly. It may be necessary to field cut
and drill the vertical wall bracket for fit-up. The bottom section’s upper handrail will also have to be
field fit with an extra drilled hole for attachment to the bottom handrail post.
Horizontal
bracket
5/16" x 3/4" Truss head bolts
5/16" x 3/4" Truss
head bolt and nut
Tie strap
(STR1078)
Attachment tab